[Request for Reconsideration of Sustained Protest of Army Procurement]

B-246136.3: May 27, 1992

Additional Materials:

Contact:

Office of Public Affairs
(202) 512-4800
youngc1@gao.gov

A firm requested reconsideration of a sustained protest of an Army procurement for engineering services. GAO had held that the Army improperly reopened negotiations after award. In its request for reconsideration, the protester contended that GAO ignored the Army's findings that the solicitation did not include evaluation factors. GAO held that the protester failed to show any legal or factual errors that would warrant reversal or modification of the original decision. Accordingly, the request for reconsideration was denied.