[Request for Reconsideration of Dismissed Protest of Navy Contract Award]

B-246451.2: Apr 27, 1992

Additional Materials:

Contact:

Office of Public Affairs
(202) 512-4800
youngc1@gao.gov

A firm requested reconsideration of its dismissed protest against a Navy contract award for a wiring analyzer. GAO had held that the protester untimely filed with GAO its comments on the agency report more than 10 days after the agency report due date. In its request for reconsideration, the protester contended that it timely filed its responsive letter to the Navy's comments regarding the protest. GAO held that the protester untimely filed its comments or an expression of interest in the protest more than 10 days after receipt of the agency report. Accordingly, the dismissal was affirmed.