[Protest of DGSC Contract Award for Refrigerant Recovery Units]
B-247081: Apr 22, 1992
Additional Materials:
- Full Report:
Contact:
A firm protested a Defense General Supply Center (DGSC) contract award for refrigerant recovery units, contending that DGSC improperly conducted a restricted procurement based on an urgency which resulted from a lack of advance planning. GAO held that the urgency that DGSC used to justify the noncompetitive contract award resulted from a lack of advance planning. Accordingly, the protest was sustained, and GAO recommended that DGSC reimburse the protester for its protest costs.