[Priority of Payment Between Payment Bond Surety and Contractor]

B-238695: Sep 13, 1991

Additional Materials:

Contact:

Shirley Jones
(202) 512-8156
jonessa@gao.gov

 

Office of Public Affairs
(202) 512-4800
youngc1@gao.gov

The Army Corps of Engineers requested an advance decision regarding whether a contractor or its payment bond surety had priority to funds due under a contract. GAO held that federal regulations required the Corps to hold payment until the claimants reached an agreement on the identity of the proper payee or the judicial branch rendered a determination of their rights. Accordingly, the Corps should hold payment.