[Protest of Army Contract Termination and Subsequent Contract Award]

B-242743.3: Oct 3, 1991

Additional Materials:

Contact:

Office of Public Affairs
(202) 512-4800
youngc1@gao.gov

A firm protested an Army contract award termination and subsequent contract award, contending that the Army: (1) did not immediately terminate the original contract; and (2) did not take the initial contract price into consideration in the subsequent evaluation. GAO held that the protester untimely filed its protest regarding the Army's corrective action more than 10 days after it learned of the basis for protest. Accordingly, the protest was dismissed.

Jan 16, 2019

Jan 15, 2019

Jan 11, 2019

Jan 10, 2019

  • Miltope
    We deny the protest.
    B-416859.2,B-416859.3