[Protest of BOP Rejection of Bid for Site Work]

B-241769.2: Mar 1, 1991

Additional Materials:

Contact:

Office of Public Affairs
(202) 512-4800
youngc1@gao.gov

A firm protested the Bureau of Prisons' (BOP) rejection of its bid for site work, contending that BOP improperly determined that its bid bond was defective and nonresponsive. GAO held that BOP reasonably determined that the protester's bid bond did not sufficiently identify the solicitation to ensure the enforceability of its bond. Accordingly, the protest was denied.