[Request for Reconsideration of Protest Against Navy Solicitation]

B-240311.3: Jan 9, 1991

Additional Materials:

Contact:

Office of Public Affairs
(202) 512-4800
youngc1@gao.gov

A firm requested reconsideration of its protest against a Navy solicitation for computer and network support services. GAO had held that the protester untimely filed its protest regarding the Navy's failure to conduct meaningful discussions. In its request for reconsideration, the protester contended that it timely protested the Navy's failure to conduct meaningful discussions, as evidenced by its original protest and the Navy's recognition of the issue in its protest report. GAO held that the protester untimely filed its protest regarding discussions more than 10 working days after it became aware of the basis for protest. Accordingly, the request for reconsideration was denied.