[Protest of Air Force Rejection of Bid for Transformer Replacement]

B-241391.2: Jan 4, 1991

Additional Materials:

Contact:

Office of Public Affairs
(202) 512-4800
youngc1@gao.gov

A firm protested the Air Force's rejection of its late bid for transformer replacement, contending that the Air Force failed to timely deliver its bid to the proper location. GAO held that the Air Force properly rejected the bid, since the bid envelope was not correctly addressed or marked with any identifying information. Accordingly, the protest was denied.