[Protest of BLM Reprocurement of Office and Storage Space]

B-240660: Dec 4, 1990

Additional Materials:

Contact:

Office of Public Affairs
(202) 512-4800
youngc1@gao.gov

A firm protested a Bureau of Land Management (BLM) reprocurement of office and storage space, contending that BLM unreasonably resolicited, rather than making award to it as the next low offeror after terminating the original contract. GAO held that the protester untimely filed its protest more than 10 working days after receiving notice of the resolicitation. Accordingly, the protest was dismissed.