[Protest of Alleged Improper NCI Contract Modification]

B-240458: Nov 21, 1990

Additional Materials:

Contact:

Office of Public Affairs
(202) 512-4800
youngc1@gao.gov

A firm protested an alleged contract modification by the National Cancer Institute (NCI), contending that NCI improperly authorized the awardee to perform services outside the scope of its master agreement order. GAO held that the modification was not materially different from the order, as originally competed. Accordingly, the protest was denied.