[Protest of Army Contract Award for Aircraft Maintenance, Overhaul, and Storage]

B-240980.2: Oct 17, 1990

Additional Materials:

Contact:

Office of Public Affairs
(202) 512-4800
youngc1@gao.gov

A firm protested an Army contract award for aircraft maintenance, overhaul, and storage, contending that: (1) the specified evaluation scheme was defective; and (2) GAO should consider its untimely protest under the significant-issue exception to the protest timeliness requirements. GAO held that, although the evaluation scheme may have been defective, the protest was not of sufficient interest to the procurement community to invoke the significant-issue exception. Accordingly, the protest was dismissed.