[Protest of Army Rejection of Bidder as Nonresponsible]

B-238460: Feb 8, 1990

Additional Materials:

Contact:

Office of Public Affairs
(202) 512-4800
youngc1@gao.gov

A firm protested the Army's rejection of its bid for embankment rehabilitation, contending that the contracting officer improperly determined that its individual sureties were nonresponsible. GAO held that the protester untimely filed its protest more than 10 days after the Army rejected its agency-level protest. Accordingly, the protest was dismissed.