[Protest of NIH Rejection of Bid as Nonresponsive]

B-234560: May 12, 1989

Additional Materials:

Contact:

Office of Public Affairs
(202) 512-4800
youngc1@gao.gov

A firm protested the National Institutes of Health's (NIH) rejection of its bid for asbestos abatement as nonresponsive, contending that the photocopied signatures on its bid bond could be waived as a minor informality, since the sureties had agreed to the liability. GAO held that NIH properly rejected the protester's bid as nonresponsive, since the bid bond was: (1) of questionable enforceability; and (2) a material condition of the bid and not correctable after bid opening. Accordingly, the protest was denied.