[Protest of VA Rejection of Proposal as Late]

B-234823: Mar 28, 1989

Additional Materials:

Contact:

Office of Public Affairs
(202) 512-4800
youngc1@gao.gov

A firm protested the Veterans Administration's (VA) rejection of its late bid. GAO held that VA properly rejected the protester's late bid, since the: (1) hand-carried bid was delivered after bid opening; and (2) protester did not show that VA mishandled the bid or otherwise caused it to be late. Accordingly, the protest was dismissed.

Jul 13, 2018

Jul 12, 2018

Jul 11, 2018

Jul 10, 2018

Jul 3, 2018

Looking for more? Browse all our products here