[Protest of VA Rejection of Proposal as Late]

B-234823: Mar 28, 1989

Additional Materials:

Contact:

Office of Public Affairs
(202) 512-4800
youngc1@gao.gov

A firm protested the Veterans Administration's (VA) rejection of its late bid. GAO held that VA properly rejected the protester's late bid, since the: (1) hand-carried bid was delivered after bid opening; and (2) protester did not show that VA mishandled the bid or otherwise caused it to be late. Accordingly, the protest was dismissed.