[Protest Against Army Solicitation for Petroleum Pipeline Sets]
B-232201: Nov 23, 1988
Additional Materials:
- Full Report:
Contact:
A firm protested an Army solicitation for petroleum pipeline sets, contending that the Army had no reasonable basis to procure the required products on a total-package basis. GAO held that the Army reasonably chose to procure on a total-package basis to ensure component compatability and minimize the technical, schedule, and cost risks. Accordingly, the protest was denied.
Oct 26, 2020
-
Chronos Solutions, LLC; Inside Realty, LLC; BLB Resources, Inc.
We sustain the protests.