[Protest Against Proposed FAA Contract Award for Radar Facility]

B-231605.2: Sep 16, 1988

Additional Materials:

Contact:

Office of Public Affairs
(202) 512-4800
youngc1@gao.gov

A firm protested a proposed Federal Aviation Administration (FAA) contract award for radar facility construction, contending that FAA should have rejected the proposed awardee's bid as nonresponsive, since it did not meet the requirement that it state unit prices. GAO held that the awardee's failure to provide unit prices was a minor irregularity which did not prejudice the protester, since FAA could ascertain the unit price by dividing the total price by the number of units. Accordingly, the protest was denied.