[Protest of Army Rejection of Late Bid]

B-230285: Mar 9, 1988

Additional Materials:

Contact:

Office of Public Affairs
(202) 512-4800
youngc1@gao.gov

A firm protested the Army's refusal to accept its late bid, contending that inclement weather caused the bid's late delivery. GAO held that adverse weather was not a condition which permitted acceptance of late hand-carried bids. Accordingly, the protest was dismissed.

Oct 29, 2020

Oct 28, 2020

Oct 27, 2020

  • Silver Investments, Inc.
    We dismiss the protest as untimely because it was filed more than 10 days after the protester knew, or should have known, the basis for its protest.