[Protest of GSA Rejection of Late Bid for Passenger Buses]

B-229922: Mar 1, 1988

Additional Materials:

Contact:

Office of Public Affairs
(202) 512-4800
youngc1@gao.gov

A firm protested the General Services Administration's (GSA) rejection of its bid for passenger buses as late, contending that: (1) government mishandling caused the late receipt of its hand-carried bid; (2) another federal agency timely received and accepted its bid; and (3) rejection of its bid created a sole-source procurement. GAO held that GSA properly rejected the bid, since the: (1) protester's delivery agent misdelivered the bid; and (2) other agency's acceptance of the bid did not constitute timely receipt. Accordingly, the protest was denied.