A firm protested a Navy contract award to another firm for a training system, contending that the Navy improperly: (1) evaluated its technical proposal; and (2) awarded the contract, since its bid was lower than the awardee's. GAO held that: (1) the Navy properly determined that the protester's proposal was technically unacceptable, since the protester failed to adequately demonstrate its knowledge of the product; and (2) since the protester's proposal was unacceptable, the fact that its bid was low was irrelevant. Accordingly, the protest was denied.
Oct 26, 2020
-
Chronos Solutions, LLC; Inside Realty, LLC; BLB Resources, Inc.
We sustain the protests.