[Protest of VA Rejection of Joint Bid as Nonresponsive]

B-224024: Dec 29, 1986

Additional Materials:

Contact:

Office of Public Affairs
(202) 512-4800
youngc1@gao.gov

Two firms protested the Veterans Administration's (VA) rejection of their bid for a replacement fire alarm system as nonresponsive. GAO held that: (1) since the protesters submitted the bid in the name of one firm and a bid bond in the name of a joint venture consisting of both firms, the bid bond was materially deficient; and (2) since the surety's obligation was unclear, the bid was nonresponsive. Accordingly, the protest was denied.