[Protest of Specifications in Army Corps of Engineers Solicitation for Construction at Training Center]

B-224252: Oct 9, 1986

Additional Materials:

Contact:

Office of Public Affairs
(202) 512-4800
youngc1@gao.gov

A firm protested certain specifications under an Army solicitation for shelving, contending that they described equipment offered by only one vendor. GAO held that: (1) the protester failed to timely file the protest before bid opening; and (2) the protester's oral complaint to the contracting officer before bid opening did not constitute a timely protest. Accordingly, the protest was dismissed.