[Protest of DLA Decision To Award New Contract]

B-222213: Mar 19, 1986

Additional Materials:

Contact:

Office of Public Affairs
(202) 512-4800
youngc1@gao.gov

A firm protested a proposed Defense Logistics Agency contract award for equipment, contending that: (1) the decision to conduct a new procurement resulted in an unnecessary duplication of effort and costs since the equipment could have been acquired by exercising an option in its existing contract; and (2) the proposed awardee's equipment was not a commercially available product. GAO will not consider an incumbent contractor's contention that a contracting agency should exercise an option under an existing contract instead of conducting a new procurement, since it is a matter of contract administration. GAO held that the bid may not be rejected because the equipment offered was a prototype rather than commercial product, and the solicitation did not require that the equipment be commercially available. Accordingly, the protest was dismissed.

Oct 29, 2020

Oct 28, 2020

Oct 27, 2020

  • Silver Investments, Inc.
    We dismiss the protest as untimely because it was filed more than 10 days after the protester knew, or should have known, the basis for its protest.
    B-419028