[Request for Reconsideration of Denial of Protest Under GSA IFB]

B-218730.5: Jan 23, 1986

Additional Materials:

Contact:

Office of Public Affairs
(202) 512-4800
youngc1@gao.gov

A firm requested reconsideration of a decision denying its protest under a General Services Administration solicitation. Bid protest regulations provide that GAO must receive a request for reconsideration not later than 10 working days after the basis for reconsideration is or should have been known. Accordingly, since the request for reconsideration was untimely filed, it was dismissed.