[Protest of Army Bid Rejection]

B-216827: Oct 24, 1984

Additional Materials:

Contact:

Office of Public Affairs
(202) 512-4800
youngc1@gao.gov

A firm protested the Army's rejection of its bid as the result of the Army's nonresponsiveness determination. Bid protest procedures require protests to be filed within 10 working days after the basis of the protest was known. Since the protest was not filed within this timeframe, it was untimely. Accordingly, the protest was dismissed.