[Request for Reconsideration of Decision Which Did Not Recommend Corrective Action]
B-211406.2: Jun 19, 1984
Additional Materials:
- Full Report:
Contact:
Ralph O. White
(202) 512-8278
WhiteRO@gao.gov
Kenneth E. Patton
(202) 512-8205
PattonK@gao.gov
(202) 512-4800
youngc1@gao.gov
(202) 512-8278
WhiteRO@gao.gov
Kenneth E. Patton
(202) 512-8205
PattonK@gao.gov
Office of Public Affairs
(202) 512-4800
youngc1@gao.gov
A firm requested reconsideration of a decision which sustained its protest against a sole-source Army contract award to another firm but failed to recommend corrective action because the contract was to be completed prior to the decision date. With its request for reconsideration, the firm submitted evidence that the contract performance was substantially behind schedule. In view of this information, GAO recommended that the Army consider terminating the present contract and, if feasible, recompeting the remaining requirement. The prior decision was modified accordingly.