[Protest of Failure of Air Force To Extend Closing Date for Receipt of Proposals]

B-215051: May 23, 1984

Additional Materials:

Contact:

Office of Public Affairs
(202) 512-4800
youngc1@gao.gov

A firm protested the failure of the Air Force to extend the closing date for receipt of proposals under a solicitation for a power supply at an Air Force base. The firm did not protest to GAO within 10 working days after learning of the adverse Air Force action on its original protest as required by GAO Bid Protest Procedures. Accordingly, the protest was dismissed as untimely.