[Protest of GSA Bid Rejection]

B-214891: Apr 18, 1984

Additional Materials:

Contact:

Office of Public Affairs
(202) 512-4800
youngc1@gao.gov

A firm protested the rejection of its bid as nonresponsive under a General Services Administration solicitation. Although the firm was notified that its bid was rejected because it failed to meet specification requirements, the firm did not file a protest with GAO until more than 10 days after notification. Bid protest procedures require that a protest must be filed not later than 10 working days after the basis of the protest is known. Accordingly, the protest was dismissed as untimely.