Bid Rejection Protest

B-207145: Apr 28, 1982

Additional Materials:

Contact:

Office of Public Affairs
(202) 512-4800
youngc1@gao.gov

A firm protested the Navy's rejection of its proposal on the basis that the design it proposed did not meet the requirements of the solicitation. The protester conceded that the basis for the Navy's rejection of its proposal was discussed at a debriefing conference. However, the protest was not filed until more than 10 days after the debriefing and was thus untimely. Since the protest was untimely filed, a subsequent request that the 10-day period begin from the time the protester received a summary of the Navy's technical analysis of its proposal was denied. Accordingly, the protest was denied.