Protest Alleging Improprieties in RFP

B-194513: May 10, 1979

Additional Materials:

Contact:

Office of Public Affairs
(202) 512-4800
youngc1@gao.gov

A protester, contending that a request for proposals issued by the Navy was ambiguous, incomplete, and restrictive, filed a protest with the Navy before and after the closing date for receipt of proposals. The protest was not filed with GAO, however, within 10 days of adverse agency action, which was the closing date for receipt of proposals. Therefore, the protest was dismissed as untimely.