Proposal Properly Rejected because of Late Delivery

B-192943: Oct 3, 1978

Additional Materials:

Contact:

Ralph O. White
(202) 512-8278
WhiteRO@gao.gov

Kenneth E. Patton
(202) 512-8205
PattonK@gao.gov

 

Office of Public Affairs
(202) 512-4800
youngc1@gao.gov

A company protested the rejection of its proposal as late, contending that the proposal was received only 5 minutes after the specified time because of a traffic delay. The proposal was properly rejected since the solicitation contained no provision for consideration of late proposals under such circumstances.