Proposal Properly Rejected because of Late Delivery

B-192943: Oct 3, 1978

Additional Materials:

Contact:

Ralph O. White
(202) 512-8278
WhiteRO@gao.gov

Kenneth E. Patton
(202) 512-8205
PattonK@gao.gov

 

Office of Public Affairs
(202) 512-4800
youngc1@gao.gov

A company protested the rejection of its proposal as late, contending that the proposal was received only 5 minutes after the specified time because of a traffic delay. The proposal was properly rejected since the solicitation contained no provision for consideration of late proposals under such circumstances.

Jan 16, 2019

Jan 15, 2019

Jan 11, 2019

Jan 10, 2019

  • Miltope
    We deny the protest.