Protest Based on Cost Estimates and Contractor Selection Process

B-189462: Jul 21, 1978

Additional Materials:

Contact:

Office of Public Affairs
(202) 512-4800
youngc1@gao.gov

A company protested the award of a contract to the incumbent on the bases of cost estimates and the selection process. The protest was denied because the protester's offer of cost savings lacked specific detail, and the decision to award the contract to the incumbent in spite of higher estimated costs was reasonable and consistent with evaluation factors where cost was subordinated to other factors.

Jan 17, 2019

Jan 16, 2019

Jan 15, 2019

Looking for more? Browse all our products here