Sole Source Award Was Justified

B-190331: May 18, 1978

Additional Materials:

Contact:

Ralph O. White
(202) 512-8278
WhiteRO@gao.gov

Kenneth E. Patton
(202) 512-8205
PattonK@gao.gov

 

Office of Public Affairs
(202) 512-4800
youngc1@gao.gov

A company protested the award of delivery orders on the basis of a "brand name" sole source justification. The protest was denied because purchase of protester's equipment from a multiple award Federal Supply Schedule, in spite of an initial price advantage, would result in higher maintenance charges for the life of the equipment, and the protester was not denied the opportunity to compete.