Request for Reconsideration of Protest Based on Compliance with Delivery Schedule

B-188651: Sep 21, 1977

Additional Materials:

Contact:

Office of Public Affairs
(202) 512-4800
youngc1@gao.gov

A company requesting reconsideration of a decision maintained that the delivery date which was to have been submitted by all bidders was a crucial item since failure to submit this information would have resulted in rejection of all bids as nonresponsive. The protester also alleged that the awardee was not performing in accordance with the delivery schedule. The former decision holding that the low bidder did not comply with the delivery schedule in specifications was affirmed since no additional facts or legal arguments showing erroneous decision were offered. The allegation concerning contractor compliance was not considered since this was a matter of contract administration.