Validity of the Army's Evaluation of a Technical Proposal
B-188529
Jul 14, 1977
Skip to Highlights
Highlights
The protester questioned the validity of the evaluation of its technical proposal. The protest that the evaluation scheme was improper was untimely since it was filed after receipt of the technical proposals. It would be improper to reevaluate the protester's technical proposal as supplemented by additional information developed by the protester during agency debriefing and obtained through an agency report submitted in connection with the protest.