Protest against Contract Cancellation Is Denied

B-188124: Feb 8, 1977

Additional Materials:

Contact:

Office of Public Affairs
(202) 512-4800
youngc1@gao.gov

A protest against cancellation of contract for window replacement at a VA Hospital was denied. Usually, contract termination for convenience of Government is within discretion of procuring agency, but GAO reviews awards where procedures were defective. Not all bidders received a mailed "clarification" of specifications prior to bid opening, particularly winning bidder, whose bid was based on original IFB and therefore improper.