Protest Alleging Agency Waived Requirements Was Sustained

B-187116: Jan 31, 1977

Additional Materials:

Contact:

Office of Public Affairs
(202) 512-4800
youngc1@gao.gov

A company protested a contract for a small computer system and ancillary items contending that the successful bidder failed to meet hardware and software requirements and that its live benchmark test demonstration benchmark was unacceptably biased. GAO held that the protest had merit and was sustained. Termination would be too costly to the Government, so no remedy could be effected.