Protest against Delivery Schedule and Restrictiveness of Specifications Are Denied

B-187591: Jan 28, 1977

Additional Materials:

Contact:

Office of Public Affairs
(202) 512-4800
youngc1@gao.gov

Claimant protested rejection of its bid for microfilm readers as nonresponsive. Bid was rejected as nonresponsive because it deviated from the installment delivery schedule, despite contention that delivery of total units would be in same time period. Protest against alleged restrictiveness was untimely and was not considered on merits. (DJM)