Reprocurement Procedures after Defaulted Contract

B-186679: Oct 7, 1976

Additional Materials:

Contact:

Ralph O. White
(202) 512-8278
WhiteRO@gao.gov

Kenneth E. Patton
(202) 512-8205
PattonK@gao.gov

 

Office of Public Affairs
(202) 512-4800
youngc1@gao.gov

Euclid Designs and Development Company protested reprocurement procedures, after defaulting on a contract for barbed tape, claiming irregularities in specifications, sole-source negotiations, and exclusion from competition. The repurchase, considered as a new procurement, was found to be proper and the late proposal properly excluded from consideration.

Oct 29, 2020

Oct 28, 2020

Oct 27, 2020

  • Silver Investments, Inc.
    We dismiss the protest as untimely because it was filed more than 10 days after the protester knew, or should have known, the basis for its protest.
    B-419028

Looking for more? Browse all our products here