Protest Questioning Reprocurement on Account of Defaulted Contractor

B-186158: Apr 8, 1976

Additional Materials:

Contact:

Office of Public Affairs
(202) 512-4800
youngc1@gao.gov

A defaulted contractor protested the resolicitation of its contract, alleging that the reprocurement was not conducted in a manner calculated to mitigate damages. The question of whether the reprocurement was conducted in a manner conducive to mitigating the damages was not for consideration by GAO.