Protest Concerning Awardee's Inability To Meet Delivery Schedule
B-186283: Apr 23, 1976
Additional Materials:
- Full Report:
Contact:
A protester alleged that the contract awardee could not meet the government's delivery requirement and, thus, was not responsible. The protest was not considered since GAO does not review affirmative determinations of responsibility.