Protest Against Rejection of Bid as Nonresponsive for Failure To Furnish Sufficient Bid Guaranty

B-186261: Jun 11, 1976

Additional Materials:

Contact:

Office of Public Affairs
(202) 512-4800
youngc1@gao.gov

The protester objected to the rejection of its bid as nonresponsive for failure to provide a sufficient bid guarantee. The rejection of the bid as nonresponsive was required since the bid guarantee requirement was a material part of the solicitation. The protester's purported certified check without the authorized bank official's signature thereon was unacceptable as a bid guarantee since no commitment existed on the part of the bank to cover the value of the check.