Request for Reformation of Contract

B-185990: Mar 16, 1976

Additional Materials:

Contact:

Shirley Jones
(202) 512-8156
jonessa@gao.gov

 

Office of Public Affairs
(202) 512-4800
youngc1@gao.gov

A contractor requested reformation of a contract, alleging that the contract was inordinately unprofitable. A valid contract cannot be reformed in the absence of a price adjustment clause simply because it was based upon unprofitable rates due to the inexperience of the company's negotiators at the time of the contracting.