Refusal To Extend Time for Preparation of Proposals

B-184052: Sep 26, 1975

Additional Materials:

Contact:

Ralph O. White
(202) 512-8278
WhiteRO@gao.gov

Kenneth E. Patton
(202) 512-8205
PattonK@gao.gov

 

Office of Public Affairs
(202) 512-4800
youngc1@gao.gov

On behalf of one of its members, an association protested the agency's refusal to extend the due date for receipt of proposals. In view of the limited time available to perform the contract, the contracting officer's refusal to extend the period for receipt of proposals was proper.