Rejection of Bid as Unbalanced Was Proper
B-182915
Feb 24, 1975
Skip to Highlights
Highlights
A company protested the rejection of its bid as unbalanced and the subsequent recalculation of bids. Rejection of the bid as unbalanced was proper as the agency discovered that estimates in the solicitation did not properly reflect actual future requirements, and there was no assurance that award based on the unbalanced bid would result in the lowest cost to the government. The protester was not prejudiced by the reevaluation.