This is the accessible text file for GAO report number GAO-09-978R 
entitled 'Defense Acquisitions: Army Aviation Modernization Has 
Benefited from Increased Funding but Several Challenges Need to Be 
Addressed' which was released on September 28, 2009. 

This text file was formatted by the U.S. Government Accountability 
Office (GAO) to be accessible to users with visual impairments, as part 
of a longer term project to improve GAO products' accessibility. Every 
attempt has been made to maintain the structural and data integrity of 
the original printed product. Accessibility features, such as text 
descriptions of tables, consecutively numbered footnotes placed at the 
end of the file, and the text of agency comment letters, are provided 
but may not exactly duplicate the presentation or format of the printed 
version. The portable document format (PDF) file is an exact electronic 
replica of the printed version. We welcome your feedback. Please E-mail 
your comments regarding the contents or accessibility features of this 
document to Webmaster@gao.gov. 

This is a work of the U.S. government and is not subject to copyright 
protection in the United States. It may be reproduced and distributed 
in its entirety without further permission from GAO. Because this work 
may contain copyrighted images or other material, permission from the 
copyright holder may be necessary if you wish to reproduce this 
material separately. 

GAO-09-978R: 

United States Government Accountability Office: 
Washington, DC 20548: 

September 28, 2009: 

The Honorable Neil Abercrombie:
Chairman:
The Honorable Roscoe Bartlett:
Ranking Member:
Subcommittee on Air and Land Forces:
Committee on Armed Services: 

House of Representatives: 

Subject: Defense Acquisitions: Army Aviation Modernization Has 
Benefited from Increased Funding but Several Challenges Need to Be 
Addressed: 

The Army's current efforts to transform and modernize its aviation 
assets began in 1999, seeking to maintain and improve the warfighting 
capabilities of the existing force as well as to invest in science and 
technology in a way that improved the future force. To accomplish these 
goals, the Army focused on upgrading and modernizing existing 
equipment, rapidly fielding new equipment, incorporating new 
technologies as they became available, and restructuring aviation 
warfighting units. Initially, fielding the developmental Comanche 
helicopter was a key focus of modernization, but when the Comanche 
program was terminated in 2004, an investment strategy was presented to 
Congress that would redistribute $14.6 billion of planned Comanche 
funding through fiscal year 2011 to enhance a broad range of Army 
aviation modernization efforts. Furthermore, the Army is currently re- 
evaluating the plans that were established in 2004 by conducting 
several assessments, tracking progress, and assessing future capability 
requirements, and intends to develop an updated Aviation Modernization 
Plan in 2010. 

Given this, you asked us to determine: 

* What is the Army's current investment strategy for its aviation 
forces? 

* How do the current aviation plans differ from the initial post-
Comanche plans and what are the causes of the differences?[Footnote 1] 

* What challenges does the current investment strategy face? 

To address these objectives, we conducted our work at the Department of 
Defense (DOD), Department of Army, Program Executive Office Aviation, 
Program Executive Office Missiles and Space, and selected aviation and 
missile program offices, holding discussions and interviews with 
appropriate DOD and Army officials. For each question, we compared army 
aviation acquisition plans, analyzed investment data from DOD and the 
Army, and identified and recognized possible execution risks in the 
Army plans over the coming years. 

On August 13, 2009, we briefed your staff on our initial observations 
related to the Army's current aviation modernization strategy and the 
challenges it faces. This report transmits the materials we used at the 
briefing, which are reprinted in enclosure I. 

We conducted this audit from November 2008 through September 2009 in 
accordance with generally accepted government auditing standards. These 
standards require that we plan and perform the audit to obtain 
sufficient, appropriate evidence to provide a reasonable basis for our 
findings and conclusions based on our audit objectives. We believe that 
the evidence obtained provides a reasonable basis for our findings and 
conclusions based on our audit objectives. 

Summary: 

The current Army aviation modernization plan, as proposed through 
fiscal year 2010, includes a combination of procuring and upgrading 
existing aviation systems, developing new systems, and buying off-the- 
shelf equipment. Existing aviation systems include the Apache, 
Blackhawk, Chinook, and Kiowa Warrior helicopters. New aviation systems 
include the Joint Air-to-Ground Missile and Sky Warrior unmanned aerial 
system. Off-the-shelf programs include the Light Utility Helicopter and 
Raven unmanned aerial system. Of the $5.8 billion requested by the Army 
for aviation investments in fiscal year 2010, the majority--71.1 
percent--is for existing aviation programs. Development programs 
account for 11.0 percent and off-the-shelf programs, 6.3 percent. 
[Footnote 2] Existing aviation programs are generally meeting their 
cost and schedule goals, as are off-the-shelf programs. However, the 
new development programs have either been delayed or are just starting 
up. 

While aviation plans continue to be dominated by investments in 
existing and off-the-shelf programs, the Army spent considerably more 
on aviation in recent years than originally planned, yet terminated new 
development programs. For fiscal years 2006 through 2010, actual 
spending was about $30.8 billion--including base budget and 
supplemental funds--considerably more than the Army's original target 
of $21.6 billion (in fiscal year 2010 dollars). Major increases in 
funding occurred in several programs: Apache upgrades and procurement, 
unmanned aerial system procurement, Chinook and Blackhawk procurement, 
Hellfire missiles, and Aircraft Survivability Equipment. A sizable 
portion of the increased funding was for replacement aircraft and 
missiles that were lost or used in ongoing conflicts. Also, differences 
exist in several areas due to an expansion in an existing aviation 
program, termination of several programs planned for development, and 
program changes as directed by the Secretaries of Defense and Army. 

Ongoing activities to modernize Army aviation are expected to continue 
for the next several years, but several challenges exist that will have 
an impact on those efforts, including managing within reasonable 
funding expectations, balancing demands to field equipment quickly 
while ensuring the maturity of the technology, and acquiring and 
maintaining needed aviation capabilities. For example, 

Managing within reasonable funding expectations will require the Army 
to provide long-term funding to support upgrading and sustaining the 
Kiowa Warrior helicopter fleet, and potentially develop and procure a 
replacement for the Kiowa Warrior. Furthermore, the Army will need to 
maintain an acceptable inventory of Hellfire missiles (particularly the 
laser variant) until the Joint Air-to-Ground missile is available. 

Balancing demands to field equipment quickly while ensuring the 
maturity of the technology will require the Army to continue to meet 
current aircraft survivability needs with currently available equipment 
and develop follow-on survivability capabilities. Further, the Army 
will need to come to agreement on unmanned aerial system commonality 
issues with the Air Force while resolving Sky Warrior technical issues. 

Acquiring and maintaining needed aviation capabilities will require the 
Army to balance its aviation capabilities to account for the addition 
of unmanned aircraft systems; while many new unmanned aircraft systems 
have been fielded, there have been no reductions in manned aircraft. 
Further, the Army will need to optimize teaming between unmanned 
aircraft, ground forces, and manned aircraft. 

Conclusions: 

Army aviation has not faced funding shortfalls since embarking on the 
post-Comanche plan; in fact, Army funding for aviation has increased by 
about 40 percent. The Army has been relying largely on existing 
aviation programs and off-the-shelf programs while several new 
development programs have experienced cost, schedule, and performance 
problems resulting in termination over the last few years. Cost and 
technical challenges in developing and fielding aircraft and missiles, 
if not addressed, may result in gaps between desired capabilities and 
available resources. Given the growth in aviation funding to date, it 
would not be reasonable to expect an increase in funds as a solution to 
cost and technical problems. 

Recommendation: 

To address various challenges, we recommend the Secretary of the Army 
ensure that the 2010 Army Aviation Modernization Strategy include: 

An assessment of the impact of potentially available funding levels and 
sources on the ongoing and planned aviation programs, and how the Army 
will maximize capabilities within these constraints, 

Specifics on how the Army intends to balance demands to field aviation 
equipment quickly while ensuring that the technology is mature, and to 
apply lessons learned in its new development programs, and: 

An assessment of the feasibility of acquiring and employing future 
aviation capabilities--such as the Joint Future Theatre Lift aircraft--
as well as manage the mix of manned and unmanned capabilities over the 
long term. 

Agency Comments and Our Evaluation: 

In written comments on a draft of this report, DOD concurred with our 
recommendations. DOD's comments appear in enclosure II. 

In its comments, DOD noted that of the $9.1 billion GAO identified in 
its report, $8.0 billion of that amount is primarily due to 
supplemental requests, DOD reprogrammings, and congressional funding 
above the department's request. DOD stated that plans for the Kiowa 
Warrior are fully funded in fiscal year 2010 and the Chinook and 
Blackhawk upgrades are funded acquisition programs to improve the 
capabilities of those aircraft. 

We were unable to verify the $8.0 billion identified by the department; 
our report notes the actual spending though fiscal year 2009 includes 
$4.0 billion in supplemental funding. Additionally, we acknowledge in 
our report several additional drivers of the increased funding 
including DOD program changes and Apache Block III development effort. 

DOD stated that the Army Aviation Strategy is a discrete document that 
is prepared, approved, and presented as a standalone product. DOD 
noted, however, that the strategy is not fully linked to the Army 
aviation budget planning that is contained in Army aviation accounts in 
the annual budget submission. DOD further stated that the complete 
documentation that is submitted in support of the President's budget 
request is the department's formal plan; the strategy may include 
elements of a comprehensive strategy that were not funded, totally or 
partially, in the process of reconciling competing requirements to a 
constrained budget. 

While we understand the role of the DOD budget, we see value in an 
overall Army Aviation Modernization Strategy. We look forward to both 
the strategy and budget submission to determine how DOD and the Army 
address the challenges noted in our report. 

DOD also provided technical comments, which we have incorporated, as 
appropriate. 

We are sending copies of this report to the Secretaries of Defense and 
the Army as well as to other interested parties. In addition, the 
report will be available at no charge on the GAO Web site at 
[hyperlink, http://www.gao.gov]. Contact points for our Offices of 
Congressional Relations and Public Affairs may be found on the last 
page of this report. 

If you have questions or need additional information, please contact me 
at (202) 512-4841 or martinb@gao.gov. Key contributors to this report 
were William Graveline, Assistant Director; Michael Hesse; Anne-Marie 
Lasowski; Wendy Smythe; Marie Ahearn; Hai Tran; and Robert Swierczek. 

Sincerely yours, 

Signed by: 

Belva M. Martin: 
Acting Director, Acquisition and Sourcing Management: 

Enclosures: 

[End of section] 

Enclosure I: 1Army Aviation Modernization: 

Briefing to House Committee on Armed Services Air and Land Forces 
Subcommittee: 

August 13, 2009: 

Overview: 
* Objectives; 
* Background; 
* Objective 1: Current Army Aviation Investment Strategy; 
* Objective 2: Causes of Differences; 
* Objective 3: Future Challenges; 
* Observations; 
* Scope and Methodology; 
* Appendix I. 

Objectives of Our Review: 

As requested, we addressed the following key questions: 

* What is the Army’s current investment strategy for its aviation 
forces? 

* How do the current aviation plans differ from the initial post 
Comanche plans and what are the causes of the differences?[Footnote 3] 

* What challenges does the current investment strategy face? 

Background: 

Army Transformation: 

In 1999, the Army began developing and implementing transformation and 
modernization efforts, including investments in existing aviation 
assets and fielding of the developmental Comanche helicopter. 

The Army’s modernization of aviation assets consists of two parts: 

* Maintaining and improving essential warfighting capabilities of the 
existing force through modernization and recapitalization, and; 

* Investing in science and technology to enable fielding to the future 
force. 

Furthermore, aviation modernization efforts focus on: 

* Rapid fielding of new equipment, 

* Upgrading and modernizing existing equipment, 

* Incorporating new technologies as they become available, and; 

* Restructuring aviation warfighting units into Combat Aviation 
Brigades that are modular, capable, lethal, tailorable, and 
sustainable. 

Comanche Termination: 

In February 2004, the Comanche program was terminated and funds were 
redistributed to meet mission needs. 

Army aviation study identified a variety of issues that needed to be 
addressed in order to “fix” Army aviation. 

The Army presented an investment strategy to Congress which 
incorporated the planned Comanche funding that would: 

* Enhance modernization efforts, and; 

* Work toward a more deployable, modular, and joint force structure. 

The strategy enabled the Army’s modernization efforts. 

* The Army aviation portfolio included the Apache, Blackhawk, Chinook, 
Armed Reconnaissance, and Light Utility helicopters; the Joint Cargo 
Aircraft; Raven unmanned aerial system (UAS), MQ-1C Extended Range 
Multi-Purpose UAS (Sky Warrior), and Shadow UAS; and the Joint Common 
and Hellfire missiles. 

* The portfolio also included aircraft survivability equipment, 
missiles systems, and other aviation support. 

Re-evaluation of 2004 Plans and Army Aviation Portfolio: 

The Army is currently re-evaluating the plans established in 2004 
through several assessments, tracking progress in modernizing aviation, 
and assessing future capability requirements. 

* Army Aviation Study II: 
- Review of findings of 2004 Aviation Study; 
- Review of future helicopter needs; 
- Consider roles of unmanned aviation systems. 

* Future Vertical Lift Capabilities Based Assessment: 
- Consider a variety of airlift issues, including Joint Future Theatre 
Lift capabilities. 

* Quadrennial Defense Review: 
- Look at strategies and programs, including those in the Army Aviation 
arena. 

Objective One: 

What Is the Army’s Current Investment Strategy for Its Aviation Forces? 

The Army Aviation Modernization Plan describes aviation missions and 
available capabilities while discussing planned aviation developments 
and acquisitions. 

The 2010 strategy includes a combination of procuring and upgrading 
existing systems, developing new systems, and buying off-the-shelf 
equipment.[Footnote 4] 

* Existing programs—Apache, Blackhawk, Chinook, and Kiowa Warrior 
helicopters; Shadow UAS; Aircraft Survivability Equipment (ASE); and 
Hellfire missile; 

* Off-the-shelf programs—Light Utility Helicopter (LUH) and Raven UAS; 

* New development programs—Joint Air-to-Ground Missile (JAGM), and Sky 
Warrior UAS are already underway; Armed Aerial Scout system to start in 
the future. 

Composition of the Army’s Fiscal Year 2010 Aviation Investment 
Strategy: 

Of the $5.8 billion in fiscal year 2010 investments in the Army 
aviation portfolio, existing aircraft programs make up about 71.7 
percent. 

New programs (development, 11.0 percent and off-the-shelf, 6.3 percent) 
account for 17.3 percent of the total portfolio with most spending 
being directed to developmental programs. 

Other spending in aviation is 10.9 percent and includes avionics, air 
traffic control, aircraft ground support equipment, and aircraft 
components.[Footnote 5] 

[Figure: Pie-chart] 

Existing: 71.7%; 
Developmental: 11.0%; 
Off-the-Shelf: 6.3%; 
Other: 10.9%. 

Source: GAO analysis of Army data. 

[End of figure] 

9Status of 2010 Army Aviation Programs: 

Programs to procure and/or upgrade existing aircraft are generally 
meeting their cost and performance goals. 

Off-the-shelf programs: 

* LUH and Raven are generally meeting their cost and performance goals. 

New development programs: 

* JAGM is early in its development, 

* Delays in fielding Sky Warrior program of record, and, 

* Armed Aerial Scout development program expected to start in the 
future. 

Objective Two: 

How Do the 2010 Plans Differ from the Initial Post-Comanche Plans and 
What Are the Causes? 

While similarities exist between the Army’s current and initial post-
Comanche plans in terms of investments in existing aircraft and off-the-
shelf programs, key differences have occurred in the portfolio. 

Furthermore, the Army has spent considerably more on Aviation in recent 
years than originally planned. 

Contributing causes for differences in the plans include: 

* Expansion in scope of the program to further upgrade the Apache 
helicopter, 

* Termination of new development programs such as Armed Reconnaissance 
Helicopter, Joint Common Missile, Advanced Precision Kill Weapon 
System, and, 

* Program changes as directed by the Secretary of Defense and Army. 

Table: Aviation Portfolio Similarities and Differences: 

Existing aircraft programs: 

Aviation program: Apache; 
Initial post-Comanche aviation modernization plans: [Check]; 
Current aviation modernization plans: [Check]. 

Aviation program: Blackhawk; 
Initial post-Comanche aviation modernization plans: [Check]; 
Current aviation modernization plans: [Check]. 

Aviation program: Chinook; 
Initial post-Comanche aviation modernization plans: [Check]; 
Current aviation modernization plans: [Check]. 

Aviation program: Kiowa Warrior; 
Initial post-Comanche aviation modernization plans: Upgrades to system 
not included; 
Current aviation modernization plans: [Check]. 

Aviation program: Shadow; 
Initial post-Comanche aviation modernization plans: [Check]; 
Current aviation modernization plans: [Check]. 

Aviation program: ATIRCM/CMWS; 
Initial post-Comanche aviation modernization plans: [Check]; 
Current aviation modernization plans: ATIRCM program being 
restructured. 

Aviation program: Hellfire; 
Initial post-Comanche aviation modernization plans: Additional 
procurement not included; 
Current aviation modernization plans: [Check]. 

Developmental: 

Aviation program: ARH; 
Initial post-Comanche aviation modernization plans: [Check]; 
Current aviation modernization plans: ARH terminated (Replacement being 
studied). 

Aviation program: JCM; 
Initial post-Comanche aviation modernization plans: [Check]; 
Current aviation modernization plans: [Empty]. 

Aviation program: JAGM; 
Initial post-Comanche aviation modernization plans: [Empty]; 
Current aviation modernization plans: [Check]. 

Aviation program: Sky Warrior; 
Initial post-Comanche aviation modernization plans: [Check]; 
Current aviation modernization plans: [Check]. 

Aviation program: APKWS; 
Initial post-Comanche aviation modernization plans: [Check]; 
Current aviation modernization plans: APKWS terminated (No current 
replacement). 

Off-the-Shelf: 

Aviation program: JCA; 
Initial post-Comanche aviation modernization plans: [Check]; 
Current aviation modernization plans: Transferred to Air Force. 

Aviation program: LUH; 
Initial post-Comanche aviation modernization plans: [Check]; 
Current aviation modernization plans: [Check]. 

Aviation program: Raven; 
Initial post-Comanche aviation modernization plans: [Check]; 
Current aviation modernization plans: [Check]. 

Source: GAO analysis of Army data. 

Note: [Check] denotes system included in the plan. 

[End of table] 

Causes of Differences-—Increased Spending for Aviation: 

Overall, the Army has and will continue to spend more resources 
annually to modernize aviation than it had planned to do after the 
termination of Comanche. 

For fiscal years 2006 through 2010, the Army planned to spend $21.6 
billion on aviation modernization. 

Actual and planned spending for those years was about $30.8 billion, 
including base budget and supplemental funds. 

Major increases in funding occurred in these areas: 

* Apache upgrades and procurement as well as Block III development; 

* UAS procurement; 

* Chinook and Blackhawk procurement; 

* Hellfire missiles; 

* Aircraft Survivability Equipment. 

Actual spending through fiscal year 2009 includes at least $4.0 billion 
in supplemental funding used for war replacement purposes. 

Table: Causes of Differences-—Spending for Fiscal Years 2006-2010: 

UAS (includes Raven, Shadow, and Sky Warrior: 
Initial Post-Comanche Plans for 2006-2010: $907.0; 
Actual and Current Aviation Plans for 2006-2010: $4,084.1; 
Difference: $3,177.1. 

Apache: 
Initial Post-Comanche Plans for 2006-2010: $4,225.9; 
Actual and Current Aviation Plans for 2006-2010: $6,370.7; 
Difference: $2,144.8. 

Chinook: 
Initial Post-Comanche Plans for 2006-2010: $4,652.9; 
Actual and Current Aviation Plans for 2006-2010: $6,100.2; 
Difference: $1,447.3. 

Blackhawk: 
Initial Post-Comanche Plans for 2006-2010: $5,106.7; 
Actual and Current Aviation Plans for 2006-2010: $6,519.8; 
Difference: $1.413.1. 

ASE: 
Initial Post-Comanche Plans for 2006-2010: $1,866.0; 
Actual and Current Aviation Plans for 2006-2010: $$3,143.6; 
Difference: $1,277.6. 

Kiowa Warrior: 
Initial Post-Comanche Plans for 2006-2010: $113.0; 
Actual and Current Aviation Plans for 2006-2010: $658.1; 
Difference: $545.1. 

LUH: 
Initial Post-Comanche Plans for 2006-2010: $916.2; 
Actual and Current Aviation Plans for 2006-2010: $1,083.4; 
Difference: $167.2. 

JCA: 
Initial Post-Comanche Plans for 2006-2010: $614.0; 
Actual and Current Aviation Plans for 2006-2010: $518.7; 
Difference: ($95.3). 

Munitions (includes APKWS, JCM, JAGM and Hellfire): 
Initial Post-Comanche Plans for 2006-2010: $1,380.0; 
Actual and Current Aviation Plans for 2006-2010: $1,232.9; 
Difference: ($147.1). 

ARH: 
Initial Post-Comanche Plans for 2006-2010: $1,844.8; 
Actual and Current Aviation Plans for 2006-2010: $1,047.3; 
Difference: ($797.5). 

Total: 
Initial Post-Comanche Plans for 2006-2010: $21,626,4; 
Actual and Current Aviation Plans for 2006-2010: $30,758.7; 
Difference: $9,132.4. 

Source: GAO analysis of Army data. 

Note: Funding includes supplemental dollars. 

[End of table] 

Causes of Differences—Expansion of Apache Block III Development Effort: 

Originally an engineering change proposal, the Apache Block III was 
expanded and upgraded to an ACAT 1D program in 2006. 

Apache Block III, an upgrade to the D model, includes improved drive 
systems; upgraded communications; improved situational awareness, 
targeting, and navigation; and Level 4 UAS capability. 

A milestone C production decision is expected in April 2010 with 
initial capability set for January 2013. 

Causes of Differences—Termination of New Developmental Programs: 

* Armed Reconnaissance Helicopter—Due to cost, schedule, and 
performance problems, DOD terminated the program in October 2008. 

* APKWS Rocket System—Terminated due to contractor problems with cost, 
schedule, and performance expectations caused by technical issues and 
failed testing. 

* Joint Common Missile—Development was established in April 2004, but 
canceled in December 2004 due to future capability needs. 

Causes of Differences—Directed Program Changes: 

* Aircraft Survivability Equipment—In September 2008, the Army 
authorized immediate action to equip Chinook aircraft with an ATIRCM 
system in quick reaction capability (QRC) configuration for wartime 
use. 

* Sky Warrior—As part of the Secretary of Defense direction for a surge 
in intelligence assets, Army used supplemental funds to procure two QRC 
Sky Warrior systems, the first was fielded in July 2009 and the second 
will be fielded in 2010. 
- Systems are to be fielded even though they do not meet all of the key 
performance parameters. 
- DOD has accelerated initial fielding of Sky Warrior by about 
1.5years. 

* Joint Cargo Aircraft—The Secretary of Defense removed all funding 
from the fiscal year 2010 Army budget when responsibility for the 
program was moved to the Air Force. 

Objective Three: 

What Challenges Does the Current Investment Strategy Face? 

Ongoing activities to modernize Army aviation are expected to continue 
for the next several years. 

However, several challenges have emerged, including: 

* Managing within reasonable funding expectations, 

* Balancing demands to field equipment quickly with technology 
maturity, and, 

* Acquiring and maintaining needed aviation capabilities. 

Managing Within Reasonable Funding Expectations—Armed Scout Helicopter: 

Within the Armed Scout Helicopter program, the Army has two initiatives 
in place to sustain and upgrade the armed scout capabilities. 

* Upgrading and sustaining the Kiowa Warrior fleet: 
- Obsolescence and weight reduction initiatives as well as completion 
of the safety enhancement program; 
- Converting A/C models to D models; 
- Upgrades including nose mounted sensor. 

* Developing and procuring a new Armed Aerial Scout system that will 
replace the terminated ARH (which was to replace Kiowa Warrior): 
- Analysis of alternatives to be started soon. 

Both initiatives have been defined and initially approved, but not 
fully budgeted. 

Challenge: match realistic funding with scope of these two efforts. 

Managing Within Reasonable Funding Expectations—Missile Procurement: 

* Army has expended more than 11,000 Hellfire missiles (in Iraq and 
Afghanistan), and plans to purchase 2,373 with supplemental funds in 
fiscal year 2010. 
- Unclear if Army has accounted for usage with unmanned assets in 
future inventory plans. 

* Other than plans to replenish Hellfire missiles with fiscal years 
2009 and 2010 supplemental funds, additional procurement is not 
currently planned in the base budget even though future needs seems to 
be predictable. 

* Initial fielding of Joint Air-to-Ground Missile (which is to replace 
Hellfire) is planned for fiscal year 2016, which could result in a 
significant inventory shortfall prior to JAGM deliveries. 

* Challenge: maintain an acceptable inventory of Hellfire missiles 
(particularly the laser variant) until JAGM is available. 

[Figure: stacked line graph: Number of missile quantities] 

Total Army munitions requirement (TARM): 13,549. 

Fiscal year: 2009; 
Hellfire (base funding): 12,750; 
JAGM (base funding): 0; 
2009 supplement: 0; 
2010 supplement: 0. 
Shortfall: 799. 

Fiscal year: 2010; 
Hellfire (base funding): 11,044; 
JAGM (base funding): 0; 
2009 supplement: 0; 
2010 supplement: 0. 
Shortfall: 2,505. 

Fiscal year: 2011; 
Hellfire (base funding): 10,830; 
JAGM (base funding): 0; 
2009 supplement: 2,500; 
2010 supplement: 0. 
Shortfall: 219. 

Fiscal year: 2012; 
Hellfire (base funding): 9,110; 
JAGM (base funding): 0; 
2009 supplement: 2,500; 
2010 supplement: 2,500. 
Shortfall: (+561). 

Fiscal year: 2013; 
Hellfire (base funding): 7,110; 
JAGM (base funding): 0; 
2009 supplement: 2,500; 
2010 supplement: 2,500. 
Shortfall: 1,439. 

Fiscal year: 2014; 
Hellfire (base funding): 5,110; 
JAGM (base funding): 0; 
2009 supplement: 2,500; 
2010 supplement: 2,500. 
Shortfall: 3,439. 

Fiscal year: 2015; 
Hellfire (base funding): 3,110; 
JAGM (base funding): 0; 
2009 supplement: 2,500; 
2010 supplement: 2,500. 
Shortfall: 5,439. 

Fiscal year: 2016; 
Hellfire (base funding): 1,110; 
JAGM (base funding): 96; 
2009 supplement: 2,500; 
2010 supplement: 2,500. 
Shortfall: 7,439. 

Fiscal year: 2017; 
Hellfire (base funding): 0; 
JAGM (base funding): 624; 
2009 supplement: 1,610; 
2010 supplement: 2,404. 
Shortfall: 8,911. 

Fiscal year: 2018; 
Hellfire (base funding): 0; 
JAGM (base funding): 1,606; 
2009 supplement: 0; 
2010 supplement: 2,014. 
Shortfall: 9,929. 

Fiscal year: 2019; 
Hellfire (base funding): 0; 
JAGM (base funding): ,2974; 
2009 supplement: 0; 
2010 supplement: 14. 
Shortfall: 10,561. 

Fiscal year: 2020; 
Hellfire (base funding): 0; 
JAGM (base funding): 2,498; 
2009 supplement: 0; 
2010 supplement: 0. 
Shortfall: 11,051. 

Fiscal year: 2021; 
Hellfire (base funding): 0; 
JAGM (base funding): 2,295; 
2009 supplement: 0; 
2010 supplement: 0.
Shortfall: 11,254. 

Source: GAO analysis of Army data. 

[End of figure] 

Managing Within Reasonable Funding Expectations—Supplemental Funding 
Resets Aircraft: 

The Army is actively “resetting” many assets in its aircraft fleet and 
buying new aircraft to offset wartime losses. These activities are 
funded through supplemental funding. 

* The Army’s reset program restores aviation equipment to a fully 
mission-capable condition using special technical inspection and repair 
procedures. 

* Total spending on reset through July 2009 for aviation platforms is 
$3.5 billion. 

Challenge: maintain sufficient funding to continue resetting aviation 
equipment as they return from the warfront. 

Balancing Demands to Field Equipment Quickly with Technology Maturity—
Aircraft Survivability Equipment: 

The Army has accelerated fielding of the quick reaction capability 
ATIRCM/CMWS assets to meet warfighters’ immediate needs while 
restructuring the longer term development of the ATIRCM program of 
record. 

* The Army is continuing to meet aircraft survivability needs by 
developing the quick reaction capability and adjusting the mix of 
flares to meet threat changes. 

The ATIRCM program is being restructured and plans to conduct a new 
competition with competitive prototyping once requirements and a 
fielding timeline has been validated through the Joint Requirements 
Oversight Council. 

Challenge: continue to meet current aircraft survivability needs with 
ATIRCM/CMWS and develop follow on ASE capabilities. 

Balancing Demands to Field Equipment Quickly with Technology Maturity—
Unmanned Aircraft Systems: 

In September 2007, DOD directed the Army’s Sky Warrior and the Air 
Force’s Predator programs to be more common by combining them into a 
single acquisition effort but that has not yet been accomplished. 

Efforts to meet urgent warfighter needs through a quick reaction 
capability have delayed initial production deliveries of the Sky 
Warrior program of record. 

* Technical issues in development of the Synthetic Aperture Radar have 
delayed the program of record’s ability to perform as required. 

Challenge: finalize Air Force/Army agreement on commonality issues and 
resolve technical issues faced in Sky Warrior acquisition. 

Acquiring and Maintaining Needed Aviation Capabilities—Mix of Manned 
and Unmanned Aircraft: 

Army has been considering how best to use unmanned aircraft to optimize 
teaming with ground forces and manned aircraft. 

Quantities of unmanned systems expanding: 

* Sky Warrior, Shadow, and Raven; 

* Future Combat System’s unmanned aircraft may be fielded to current 
Army forces in the coming years. 

However, no reduction in number of manned aircraft. 

Challenge: optimize aviation capabilities and size of aircraft 
inventories. 

Acquiring and Maintaining Needed Aviation Capabilities—Joint Future 
Theatre Lift: 

Enhanced capabilities attributed to Joint Future Theatre Lift (JFTL) 
aircraft may offer up opportunity for a new way of fighting. 

* Such as mounted vertical maneuver concept. 

Army and Air Force requirements and proposal now up for consideration 
by the Secretary of Defense. 

* Initial Joint Requirements Oversight Council review and possible 
approval expected by summer 2009. 

* JFTL acquisition may require significant resources. 

The Army requirement for JFTL may have to be reassessed in light of 
recent decisions on the Future Combat System program and the 
modernization of the brigade combat teams. 

Challenge: determine if there is a technically feasible and affordable 
means to implement mounted vertical maneuver concept and, if not, re-
examine the concept. 

Acquiring and Maintaining Needed Aviation Capabilities—Long Term 
Aviation Needs: 

Current “work horse” aircraft, Apache, Blackhawk, and Chinook, are seen 
by the Army as providing at least adequate capabilities for the next 10 
years. 

* Next generation rotorcraft may not be technically feasible and 
affordable right now. 

* User community looking at potential capability gaps for 2015-2024 
time period. 

Based on a recent Secretary of Defense decision, the Joint Cargo 
Aircraft was transferred to the Air Force. 

* Army may have a capability gap for the delivery of mission critical, 
time sensitive cargo, and key personnel to forward deployed units in 
the Joint Operations Area. 

Challenge: minimize capability gaps over the long term. 

Conclusions: 

Army aviation has not faced any funding shortfalls since embarking on 
the post-Comanche plan; in fact, Army funding for aviation has 
increased by about 40 percent. 

While the Army continues to rely largely on procuring and upgrading 
existing systems and procuring off-the-shelf aviation systems, new 
development programs have experienced cost, schedule, and performance 
problems which often resulted in termination. 

Cost and technical challenges in developing and fielding aircraft and 
missiles, if not addressed, may result in gaps between desired 
capabilities and available resources. Given the growth in aviation 
funding to date, it may not be reasonable to expect an increase in 
funds as a solution to cost and technical problems. 

Scope and Methodology: 

We conducted our work at DOD, Department of the Army, Program Executive 
Office Aviation, Program Executive Office Missiles and Space, and 
selected aviation and missile program offices. 

For each question, we analyzed investment data from DOD and the Army as 
well as held discussions and interviews with appropriate DOD and Army 
officials from the listed locations. We: 

1. compared the fiscal year 2006 and 2010 Army aviation acquisition 
plans to determine changes over the last 5 years and determine the 
status of each portion of the plan, 

2. reviewed and analyzed investment strategies and data for aviation 
systems and conducted interviews with DOD and Army officials to 
determine causes of divergences from previous plans, and, 

3. identified and recognized possible execution risks in the Army plans 
over the coming years. 

To accomplish our work, we visited the Pentagon, Arlington, Va. and 
Redstone Arsenal, Huntsville, Ala. 

Appendix I: Systems Included in Current Army Aviation Portfolio: 

* AH-64 Apache: 
* UH-60 Blackhawk: 
* CH-47 Chinook: 
* OH-58D Kiowa Warrior: 
* Shadow Unmanned System: 
* Aircraft Survivability Equipment: 
* Hellfire Missile: 
* Armed Reconnaissance Helicopter Replacement: 
* Joint Air-to-Ground Missile: 
* Sky Warrior Unmanned System: 
* Light Utility Helicopter: 
* Raven Unmanned System: 

Existing Aircraft Program: Apache Helicopter Upgrades: 

* System Description: The Apache helicopter performs attack and 
reconnaissance missions. 

* The D model upgrades add millimeter wave fire control radar, radar 
frequency interferometer, fire and forget radar guided missile, and 
digitization enhancements. 

* The Apache Block III upgrades are expected to amplify performance, 
improve situational awareness, enhance lethality, increase 
survivability, and provide interoperability. 

* Army Plans: Upgrade 618 Apache A model aircraft to Block III 
aircraft. Additionally, as part of the National Guard Modernization 
plan, Apache will also convert the remaining 95 Army National Guard A 
models to Block III. In fiscal year 2010, the Army plans 28 conversions 
and war replacement aircraft. The Apache Block III production decision 
is April 2010 and plans to procure 8 low rate production aircraft. 

Fiscal year 2010 funding request: $1.1 billion. 

[Figure: photograph of Apache Helicopter] 

Source: Army ATTC Office. Fort Rucker; Apache PMO. 

[End of figure] 

Existing Aircraft Program: Procurement of New Blackhawks and Upgrades: 

* System Description: Blackhawk provides utility and assault lift 
capability in support of air assault, medevac, general support, and 
lift helicopter. 

* The M model adds a digital cockpit, upgraded engine, upgraded 
communications, CMWS, and wide chord blades. 

* Army plans to further upgrade the M model (Mu) with fly-by-wire 
technology for integration with FCS, an upgraded cockpit, and a 
composite tail cone; Mu model will continue through fiscal year 2015. 

* Blackhawk A to L conversions will extend service life and add 
capabilities to continue through fiscal year 2015; 38 are planned for 
fiscal year 2010. 

* Army Plans: to procure 1,227 Blackhawk M aircraft. M model 
procurement started in 2005 and will continue through fiscal year 2012. 

Fiscal year 2010 funding request: $1.5 billion. 

[Figure: photograph of Blackhawk Helicopter] 

Source: Army PAO. 

[End of figure] 

Existing Aircraft Program: Chinook D-to-F Upgrade and Procurement of 
New F Models: 

* System Description: The CH-47 provides transportation for tactical 
vehicles, artillery, engineer equipment, personnel, and logistical 
support equipment. 

* The F model features upgraded engine, common avionics, air warrior, 
and digital automatic flight control. 

* The Army plans to acquire 513 F models; 202 new builds and 311 
remanufactured aircraft. In fiscal year 2009, 69 F models were 
delivered. 

Army Plans: Procure 31 aircraft in fiscal year 2010 with plans to 
continue to at least fiscal year 2017. 

Fiscal year 2010 funding request: $1.2 billion. 

[Figure: photograph of CH-47 Helicopter] 

Source: Redstone Arsenal, Alabama; PMO Cargo Helicopter. 

[End of figure] 

Existing Aircraft Program: Kiowa Warrior Life Support 2020 and A/C to D 
Conversions: 

* System Description: The OH-58D Kiowa Warrior is a two-seat, single-
engine, observation, scout/attack helicopter that operates autonomously 
at standoff ranges providing armed reconnaissance, command and control, 
and target acquisition/designation for Apache helicopters and other 
airborne weapons. 

* Increased cost contributed by integration of nose mounted sensor 
results in an acquisition category II designation with the associated 
milestone decision cycle. 

* Army Plans: Sustain the fleet through obsolescence and weight 
reduction initiatives - Kiowa Warrior Life Support 2020. Convert 
existing OH-58 A/C aircraft to D Models to replace combat losses. 
Upgrade all Kiowa Warriors with nose mounted sensor. 

Fiscal year 2010 funding request: $334.8 million. 

[Figure: photograph of Kiowa Warrior Helicopter] 

Source: Redstone Arsenal, Alabama; Kiowa Warrior ASH PMO. 

[End of figure] 

Existing Aircraft Program: Shadow UAS Product Improvement: 

System Description: Shadow provides the tactical maneuver commander 
near-real-time reconnaissance, surveillance, target acquisition, and 
force protection during day/night and limited adverse weather 
conditions. 

* The quantity required to equip and sustain the Army force is 115 
Systems; The Army Procurement Objective is 102 and 100 have been 
procured to date. 

* A decision to enter Engineering and Manufacturing Development was 
made in December 1999. A decision to begin full rate production was 
made in September 2002. 

Army Plans: Procure laser designators and retrofits of the tactical 
common data link which includes a ground control station as well as pre-
planned product improvements. 

Fiscal year 2010 funding request: $609.4 million. 

[Figure: photograph of Shadow UAS] 

Source: Redstone Arsenal, Alabama; Unmanned Aircraft Project Office. 

[End of figure] 

Existing Aircraft Program: Aircraft Survivability Equipment: 

* System Description: ATIRCM/CMWS is an integrated warning and 
countermeasure system to enhance aircraft survivability against 
infrared guided threat missiles. 

* A-kits are wiring and modification hardware necessary to install the 
B-kits, which are the mission equipment. 

* ATIRCM includes an active infrared jammer and a countermeasure 
dispenser for flares and chaff. 

* CMWS is an integrated suite of infrared countermeasures including a 
passive missile warning system and a countermeasure dispenser. 

* CMWS has completed 1,780 A-kit and 913 B-kit installations as of 
January 2009. The ATIRCM program of record is not yet fielded. 

* Army Plans: ATIRCM program restructure began April 2009 separating 
ATIRCM and CMWS. Subprogram next generation ATIRCM is to report back to 
the DAB in 60 days with a new acquisition strategy. 

Fiscal year 2010 funding request: $537.7 million. 

[Figure: photograph of Aircraft Survivability Equipment] 

Source: BAE Systems. 

[End of figure] 

Existing Aviation Program: Hellfire Missiles: 

* System Description: Hellfire is an air-to-ground, point target, 
precision strike missile system designed to defeat hardpoint targets. 

* Two primary variants -Hellfire II semi-active laser guidance and 
Longbow Hellfire millimeter wave radar guidance. 

* Army has a requirement for 13,549 Hellfire missiles. 

* Army Plans: Procure 2,373 missiles in fiscal year 2010. 

Fiscal year 2010 funding request: $250.9 million. 

[Figure: photograph of Laser Hellfire and Longbow Hellfire missiles] 

Source: Redstone Arsenal, Alabama; JAMS Project Office. 

[End of figure] 

New Start Development Program: Armed Aerial Scout: 

* System Description: The developmental ARH was to provide 
reconnaissance and security capability for air and ground maneuver 
teams and replace the aging Kiowa Warrior Helicopter. 

* Due to cost, schedule, and performance problems, DOD terminated the 
ARH program in October 2008. 

* Army Plans: To complete an analysis of alternatives prior to starting 
a program to replace the Kiowa Warrior. 

Fiscal year 2010 funding request: $4.3 million. 

New Start Development Program: Joint Air-to-Ground Missile: 

* System Description: The Joint Air-to-Ground Missile (JAGM) is an air-
launched missile system that provides advanced line-of-sight and beyond-
line-of-sight capabilities. 

* The system will be used with fixed-wing aircraft, rotary-wing 
aircraft, and unmanned aircraft systems. 

* Army Plans: The JAGM is planned to replace the Army’s Hellfire 
Missiles. 

Fiscal year 2010 funding request: $127.4 million. 

[Figure: photograph of Joint Air-to-Ground Missile] 

Source: Redstone Arsenal, Alabama; JAMS Project Office. 

[End of figure] 

New Start Development Program: Sky Warrior Unmanned Aircraft System: 

* System Description: Sky Warrior is an unmanned aircraft system that 
operates alone or with other platforms to perform reconnaissance, 
surveillance, target acquisition, and attack missions. Development 
began in 2005. 

* Sky Warrior includes two efforts: 
- the program of record, with a production decision scheduled for 
November 2009 and; 
- two less-capable “quick reaction” systems added in response to DOD 
direction, the first of which is to be fielded in July 2009. 

* Army Plans: Procure three systems with new equipment training and pre-
planned product improvement. 

Fiscal year 2010 funding request: $651.4 million. 

[Figure: photograph of Sky Warrior Unmanned Aircraft System] 

Source: General Atomics Aeronautical Systems, Inc. 

[End of figure] 

Off-the-Shelf Acquisition: Light Utility Helicopter: 

* System Description: LUH is a commercially procured helicopter 
designed to perform a variety of missions from nongovernmental to 
homeland security. 

* National Guard is the primary user of LUH for conducting missions in 
support of homeland security such as civil search and rescue and 
counter-drug operations. 

* LUH is being procured to replace aging UH-1 and OH-58A/C aircraft. 
LUH will also free up Army National Guard Blackhawk assets. 

* Army Plans: Procure 340 LUH through fiscal year 2015 and 72 aircraft 
have been delivered to date. 

Fiscal year 2010 funding request: $326.0 million. 

[Figure: photograph of Light Utility Helicopter] 

Source: Redstone Arsenal, Alabama; Utility PMO. LUH. 

[End of figure] 

Off-the-Shelf Acquisition: Raven UAS: 

* System Description: The RQ-11 Raven Small Unmanned Aircraft System is 
an “over the hill” rucksack-portable, day/night, limited adverse-
weather, remotely operated, multi-sensor system used in support of 
combat. 

* Total Army acquisition quantity procured to date 1,368 (includes 50 
DDL systems). In addition, 206 system retrofits from analog to digital. 

* The program entered milestone C in October 2005. 

* Army Plans: Procure 729 additional units through fiscal year 2015. 

Fiscal year 2010 funding request: $79.6 million. 

[Figure: photograph of Raven UAS] 

Source: Redstone Arsenal, Alabama; Unmanned Aircraft Systems Project 
Office. 

[End of figure] 

[End of Enclosure I] 

Enclosure II: Comments from the Department of Defense: 

Office Of The Under Secretary Of Defense: 
Acquisition, Technology And Logistics: 
3000 Defense Pentagon: 
Washington, DC 20301-3000: 

September 23, 2009: 

Ms. Belva M. Martin: 
Acting Director, Acquisition and Sourcing Management: 
U.S. Government Accountability Office: 
441 G Street, N.W. 
Washington, DC 20548: 

Dear Ms. Martin: 

This is the Department of Defense (DoD) response to the GAO draft 
report GAO-09-978R, "Defense Acquisitions: Army Aviation Modernization 
Has Benefited from Increased Funding but Several Challenges Need to Be 
Addressed," dated August 17, 2009 (GAO Code 120799). 

The DoD concurs with the three recommendations. The rationale for the 
DoD's position is enclosed. 

We appreciate the opportunity to comment on the draft report. My point 
of contact for this effort is Mr. Michael Walsh, 703-695-1700, 
Michael.Walsh@osd.mil. 

Sincerely, 

Signed by: [Illegible] for: 

David G. Ahern: 
Director: 
Portfolio Systems Acquisition: 

Enclosure: As stated: 

[End of letter] 

GAO Draft Report Dated August 17, 2009: 
GAO-09-978R (GAO Code 120799): 

"Defense Acquisitions: Army Aviation Modernization Has Benefited from 
Increased Funding but Several Challenges Need to Be Addressed" 

Department Of Defense Comments To The GAO Recommendations: 

Recommendation 1: The GAO recommends that the Secretary of the Army 
ensure that the 2010 Army Modernization Strategy include an assessment 
of the impact of potentially changing available funding levels and 
sources on the ongoing and planned aviation programs, and how the Army 
will maximize capabilities within these constraints. 

DoD Response: Concur. See comments below. 

Recommendation 2: The GAO recommends that the Secretary of the Army 
ensure that the 2010 Army Modernization Strategy include specifics on 
how the Army intends to balance demands to field aviation equipment 
quickly while ensuring that the technology is mature, and to apply 
lessons learned in its new development programs. 

DoD Response: Concur. See comments below. 

Recommendation 3: The GAO recommends that the Secretary of the Army 
ensure that the 2010 Army Modernization Strategy include an assessment 
of the feasibility of acquiring and employing future aviation 
capabilities--such as the Joint Future Theatre Lift aircraft--as well 
as manage the mix of manned and unmanned capabilities over the long 
term. 

DoD Response: Concur. See comments below. 

DoD Comments On All Recommendations: The following comments provide 
relevant clarifications: 

* The $9.2B of increases in funding cited in the report, compared to 
original budgets for the FY 2006 to FY 2010 period, include about $8B 
of supplemental funding to replace wartime aircraft losses and to 
purchase survivability equipment, mission equipment packages, Hellfire 
missiles, and other items. The remainder consists of Department-
requested reprogramming actions and increases in Congressional funding 
above the Department request. 

* All planned efforts to improve the Army Kiowa Warrior aircraft were 
fully-funded in the President's Budget Request for FY 2010. 

* The CH-47F and UH-60M upgrades are formal acquisition programs that 
included preceding, funded development efforts to improve the 
capabilities of those aircraft. 

The three recommendations reference the "Army Aviation Strategy" which 
is a strategic communications document presented on the Army's official 
website. The "Strategy" is a discrete document that is prepared, 
approved, and presented as a stand-alone product. It is not fully 
linked to the Army aviation budget planning contained in Army aviation 
accounts in the Department's annual budget submission. The complete 
documentation that is submitted in support of the President's budget 
request is the Department's formal plan; the "Strategy" may include 
elements of a comprehensive strategy that were not funded, totally or 
partially, in the process of reconciling competing requirements to a 
constrained budget. 

The Department's budget balances demands to field equipment quickly, 
ensure technology maturity, and properly mix the capabilities needed by 
the Services within the realism of the Administration's funding 
expectations, The Department's annual budget request addresses each of 
the considerations, and others as well, to include the war fighters' 
immediate needs. The Department's extensive budget preparation process 
and review is a best faith effort to consider and assess all the 
factors and to submit the best possible budget request. Furthermore, 
such assessments are revisited each year. 

[End of Enclosure II] 

Footnotes: 

[1] Initial post-Comanche plans were established after the Comanche 
termination in 2004. 

[2] Totals do not include supplemental requests for fiscal year 2010. 
The remaining 10.9 percent of aviation investments are for avionics, 
air traffic control, and other needs. 

[3] Initial post-Comanche plans were established after the Comanche 
termination in 2004. 

[4] Appendix I describes the programs and provides information on 
quantities and costs. 

[5] Totals do not include supplemental requests for fiscal year 2010. 

[End of section] 

GAO's Mission: 

The Government Accountability Office, the audit, evaluation and 
investigative arm of Congress, exists to support Congress in meeting 
its constitutional responsibilities and to help improve the performance 
and accountability of the federal government for the American people. 
GAO examines the use of public funds; evaluates federal programs and 
policies; and provides analyses, recommendations, and other assistance 
to help Congress make informed oversight, policy, and funding 
decisions. GAO's commitment to good government is reflected in its core 
values of accountability, integrity, and reliability. 

Obtaining Copies of GAO Reports and Testimony: 

The fastest and easiest way to obtain copies of GAO documents at no 
cost is through GAO's Web site [hyperlink, http://www.gao.gov]. Each 
weekday, GAO posts newly released reports, testimony, and 
correspondence on its Web site. To have GAO e-mail you a list of newly 
posted products every afternoon, go to [hyperlink, http://www.gao.gov] 
and select "E-mail Updates." 

Order by Phone: 

The price of each GAO publication reflects GAO’s actual cost of
production and distribution and depends on the number of pages in the
publication and whether the publication is printed in color or black and
white. Pricing and ordering information is posted on GAO’s Web site, 
[hyperlink, http://www.gao.gov/ordering.htm]. 

Place orders by calling (202) 512-6000, toll free (866) 801-7077, or
TDD (202) 512-2537. 

Orders may be paid for using American Express, Discover Card,
MasterCard, Visa, check, or money order. Call for additional 
information. 

To Report Fraud, Waste, and Abuse in Federal Programs: 

Contact: 

Web site: [hyperlink, http://www.gao.gov/fraudnet/fraudnet.htm]: 
E-mail: fraudnet@gao.gov: 
Automated answering system: (800) 424-5454 or (202) 512-7470: 

Congressional Relations: 

Ralph Dawn, Managing Director, dawnr@gao.gov: 
(202) 512-4400: 
U.S. Government Accountability Office: 
441 G Street NW, Room 7125: 
Washington, D.C. 20548: 

Public Affairs: 

Chuck Young, Managing Director, youngc1@gao.gov: 
(202) 512-4800: 
U.S. Government Accountability Office: 
441 G Street NW, Room 7149: 
Washington, D.C. 20548: