This is the accessible text file for GAO report number GAO-04-71R 
entitled 'Space Acquisitions: Committing Prematurely to the 
Transformational Satellite Program Elevates Risks for Poor Cost, 
Schedule, and Performance Outcomes' which was released on December 04, 
2003.

This text file was formatted by the U.S. General Accounting Office 
(GAO) to be accessible to users with visual impairments, as part of a 
longer term project to improve GAO products' accessibility. Every 
attempt has been made to maintain the structural and data integrity of 
the original printed product. Accessibility features, such as text 
descriptions of tables, consecutively numbered footnotes placed at the 
end of the file, and the text of agency comment letters, are provided 
but may not exactly duplicate the presentation or format of the printed 
version. The portable document format (PDF) file is an exact electronic 
replica of the printed version. We welcome your feedback. Please E-mail 
your comments regarding the contents or accessibility features of this 
document to Webmaster@gao.gov.

This is a work of the U.S. government and is not subject to copyright 
protection in the United States. It may be reproduced and distributed 
in its entirety without further permission from GAO. Because this work 
may contain copyrighted images or other material, permission from the 
copyright holder may be necessary if you wish to reproduce this 
material separately.

December 4, 2003:

The Honorable Donald H. Rumsfeld:

The Secretary of Defense:

Subject: Space Acquisitions: Committing Prematurely to the 
Transformational Satellite Program Elevates Risks for Poor Cost, 
Schedule, and Performance Outcomes:

Dear Mr. Secretary,

In a multibillion-dollar effort, the Department of Defense (DOD) plans 
to build a space-based communications system that leverages 
technologies never before used in space. Such a system would enable DOD 
to transform how information is collected on potential U.S. adversaries 
and how military forces are warned of hostile action. The backbone of 
this system will be the Transformational Satellite (TSAT),[Footnote 1] 
which is expected to play a pivotal role in connecting communications 
networks on the ground, in the air, on ships, and in space. TSAT 
represents a potential leap forward in communications speed, security, 
and availability. The Air Force, which heads up DOD's space programs, 
intends for TSAT to be interoperable with similar systems being 
acquired for the National Aeronautics and Space Administration (NASA) 
and the intelligence agencies.

The initial TSAT program is expected to cost about $12 billion from 
2003 to 2015 for development and production. Several billions more are 
to be spent acquiring and supporting the associated ground 
infrastructure, including thousands of user terminals. The Air Force 
intends to start the acquisition program in December 2003 and expects 
to launch the first TSAT in 2011.

To help pay for TSAT, the Air Force has scaled back its acquisition of 
the Advanced Extremely High Frequency (AEHF) satellites currently under 
development. However, because of senior military commanders' concerns 
about TSAT's risks and the potential delay in delivering improved space 
communications, the Air Force plans to reassess the need for future 
AEHF funding in November 2004. If TSAT is considered too high a risk to 
meet the warfighter's expectations, the contingency plan is to take 
TSAT's funding--thereby delaying TSAT's development--and use it to buy 
another AEHF satellite. The Air Force has targeted November 2004 as the 
latest date such a decision could be made and still include funds for 
AEHF in the DOD budget submission for fiscal year 2006.

We conducted this assessment in response to the large investment 
planned and the importance of the communications capabilities promised 
by TSAT and AEHF. Specifically, we assessed the Air Force's readiness 
to (1) initiate a TSAT acquisition program in December 2003 and (2) 
make a decision in November 2004 about whether to take TSAT funding and 
use it to buy another AEHF satellite.

RESULTS IN BRIEF:

Air Force officials have set two imminent deadlines: starting the TSAT 
program in December 2003, and deciding whether to shift funding from 
TSAT to AEHF in November 2004. The Air Force is currently not prepared 
to make an informed decision in either case.

Air Force officials are not ready to initiate the TSAT program in 
December 2003 because they do not have the knowledge to reliably 
establish cost, schedule, and performance goals. At program start, 
program managers are required by law to establish such goals.[Footnote 
2] Our past work on successful acquisition programs has found that 
these goals cannot be set reliably unless the critical technologies and 
design have been determined to meet minimum performance requirements. 
Programs that do not have this knowledge at program start have a much 
greater risk of resorting to costly design changes later in the 
development process, asking the warfighter to compromise on desired 
capabilities, or incurring schedule overruns to correct problems. 
Realizing that TSAT's schedule is ambitious, the Air Force added 2 
years to the acquisition program. However, the extra time was mostly 
allocated to the latter part of the development process, not to the 
front end, when program managers typically need the time to become 
reasonably certain that technologies and early designs will work as 
envisioned.

We are concerned about the Air Force's readiness to make the planned 
decision in November 2004 to take TSAT funding to buy another AEHF 
satellite in case the TSAT program falters. Air Force officials have 
not defined what evaluation criteria they intend to use in making this 
decision. Senior military commanders want assurance that they will get 
at least the level of capabilities promised by AEHF early in the next 
decade. However, senior DOD and Air Force officials told us that if 
funds were shifted from TSAT back to AEHF, then TSAT--the linchpin of 
its plan to transform military communications--would be substantially 
delayed. To promote well-informed and objective investment decisions, 
our past work has found that decision makers establish and use 
measurable criteria for evaluating the costs, benefits, and risks of 
various alternatives.

We are recommending that you direct the Secretary of Air Force to 
develop critical technologies more fully and to conduct early design 
studies before starting the TSAT acquisition program. We are also 
recommending that you direct the Secretary to establish and use 
measurable evaluation criteria for the planned November 2004 funding 
decision. Although DOD agrees to adopt such criteria, it believes the 
acquisition program can be started because sufficient controls are in 
place to allow concurrent development of technology and product design.

BACKGROUND:

DOD intends to develop a new generation of space communications 
systems, taking advantage of rapidly advancing technologies. This 
reflects an increasing demand and reliance on satellite communications 
systems to move larger volumes of information to more users. The Air 
Force reports that the demand for communications bandwidth increased 
473 percent between Operation Desert Storm in 1991 and Operation 
Enduring Freedom in 2001. To help meet this demand, DOD has augmented 
its own satellite communications capability with commercial satellites. 
However, in each major conflict in the past decade, senior military 
commanders still reported shortfalls in communications capacity, 
particularly for rapid transmission of large digital files, such as 
those created by imagery sensors. DOD's communications studies indicate 
the shortfall will continue to grow, despite major improvements in 
communications satellites currently in development.

Investment Strategy for Satellite Communications Revised:

In 1996, DOD developed and began to implement a space investment 
strategy that proposed a new mix of improved communication satellites 
for use in 2010 and beyond. Among the proposed systems were the AEHF 
satellite, the Wideband Gapfiller Satellite (WGS), Advanced Polar 
System (APS), and Advanced Wideband Satellite (AWS), a less capable and 
earlier version of TSAT. At that time, DOD believed that AWS, AEHF, and 
WGS would provide a significant increase in communications capacity and 
would meet the warfighters' needs in 2010 and beyond. (More information 
about these satellite systems and their associated acquisition programs 
is included in enc. I.):

In 2001, DOD developed a new Transformational Communications 
Architecture that uses emerging communications technologies. The 
architecture is expected to transform future combat and intelligence 
operations, with TSAT playing a critical role. The concept is to use 
laser-based and improved radio frequency transmission systems and high-
speed, Internet-like networks that will link communications systems on 
the ground, in the air, on ships, and in space. Instead of circuit-
based systems, such as those used today to link specific sending-and-
receiving devices, future systems are expected to connect multiple 
sending-and-receiving devices at the same time. The ultimate goal is to 
remove the existing constraints to communication and enable 
transmissions regardless of location, size, or message.

Knowledge-based Acquisition Strategy Results in Better Outcomes:

Historically, DOD has had difficulty meeting the cost, schedule, and 
performance goals that were established at the start of its major 
defense acquisition programs such as TSAT. DOD's investments in money 
and time have far exceeded initial estimates for developing and 
acquiring communications satellites and other weapon systems. In 
addition, weapon systems have frequently been saddled with performance 
shortfalls.[Footnote 3] To address some of these difficulties, DOD 
recently implemented a new space systems acquisition policy, which 
intends to provide decision makers in the Air Force with more 
consistent and robust information on costs, technologies, and 
requirements. The new acquisition policy also promotes rapid 
introduction of emerging technologies into space systems and allows 
technology, design, and system development to occur concurrently in an 
effort to speed the acquisition process. A recent GAO report identified 
some positive aspects of the policy; however, the report stated that 
any benefits will be limited because the policy permits major 
investments in new programs before managers know what resources are 
really required to deliver a promised capability.[Footnote 4]

Our work on best practices in weapon system acquisitions has shown that 
program managers have a much higher probability of meeting cost, 
schedule, and performance objectives if the needed technologies are 
mature and the developing contractor has completed early design studies 
before starting the acquisition program. Having this knowledge in hand 
means managers can build a strong business case and ensure their 
products can be successfully developed. A business case provides the 
necessary structure for managers to identify the best product solution 
based on knowledge of performance, constraints and assumptions, and a 
risk-adjusted cost-benefit analysis. In the past several years, GAO has 
developed a knowledge-based acquisition model based on best practices 
by leading companies. The best practices model has three knowledge 
points. Each knowledge point builds on the preceding one. The acquired 
knowledge is used to identify and reduce any risks before moving a 
product to the next stage of development. Figure 1 shows when the three 
knowledge points occur on the best practices model.

The first knowledge point sets the stage for the eventual outcome of an 
acquisition program--desirable or problematic. When the customer's 
needs match the developer's resources (which include technology, design 
knowledge, time, and money) before program start, successful outcomes 
are much more likely to occur. If a match occurs after program start, 
managers often make additional, unanticipated investments in money and 
time because gaps between requirements and resources are discovered 
later in the process.

AIR FORCE IS SETTING COST, SCHEDULE, AND PERFORMANCE GOALS AND STARTING 
TSAT BEFORE CRITICAL KNOWLEDGE IS ATTAINED:

By December 2003, when the TSAT program is scheduled to start, Air 
Force officials are required by law to establish cost, schedule, and 
performance goals, but the knowledge they need to set reliable goals is 
still not available. Critical technologies are underdeveloped and early 
design studies have not been started. Without this essential knowledge, 
the Air Force is likely to have difficulty developing a sound business 
case for starting the TSAT program. If the Air Force proceeds without a 
sound business case, the program is at risk of higher costs, lower 
performance, and delays in providing capabilities to the warfighters. 
Our work has found that successful commercial and DOD development 
programs insist on having mature technologies and early design studies 
to support the business case.[Footnote 5]

Critical Technologies Are Immature:

Critical technologies are necessary building blocks for a system to 
meet its minimum performance requirements. If these technologies are 
not available when needed, the system cannot be completed as planned. 
And because technology development does not happen on a planned or 
predictable schedule, it is difficult to predict when or if a critical 
technology will mature. This is why leading commercial companies demand 
that critical technologies are mature before the commitment to a new 
system is made. Within the federal government, NASA leveraged this best 
practice by developing an analytical tool to assess technology 
maturity. This tool--adopted by many DOD programs--establishes 
Technology Readiness Levels (TRL) for demonstrated performance, with a 
higher value indicating a greater maturity level. (The various levels 
are defined in enc. II.):

According to best commercial practices and DOD guidance, the minimum 
acceptable level for a technology to be included in an acquisition is 
TRL 6. At this level, the technology is considered sufficiently mature 
and has been engineered into a subsystem or prototype that closely 
resembles the final design. Also, the technology has been successfully 
demonstrated to work in a relevant environment. DOD policy[Footnote 6] 
prefers the maturity to reach TRL 7--a prototype demonstration in an 
operational environment. A TRL 7 for a satellite would mean the 
technology prototype has achieved form, fit, and function and has been 
demonstrated in space. Commercial satellite companies frequently meet 
these criteria by including a new technology on an existing satellite 
design for demonstration purposes. Also, NASA usually requires all 
mission-critical technologies to be demonstrated in space before being 
placed on a new system. In some cases, demonstrating space technologies 
in an operational environment is important because operating a system 
in the harsh temperatures and radiation environment of space--where a 
satellite must last essentially maintenance-free for 10 to 15 years--is 
much more challenging than land-based operations. The new space 
acquisition policy does not require a minimum threshold for including 
new technology on a space acquisition program.

Critical technologies for TSAT include laser optics that can transport 
information over long distances in much larger quantities than radio 
waves; high-speed routers that enable multi-user networks, 
sophisticated data packaging; security algorithms and management 
utilities; multi-beam antennas; and software reprogrammable terminals. 
Table 1 shows that most of these technologies were at a TRL 3 or 4 in 
October 2003. When a technology is classified as a TRL 3, it means most 
of the work performed so far has been based on analytical studies and a 
few laboratory tests may have been conducted. A TRL 4 means some of the 
key components have been wired and integrated and have been 
demonstrated to work together in a laboratory environment. Significant 
effort is required to move from these TRL levels to a TRL 6, the 
minimum needed to effectively begin a new acquisition program. As shown 
below, the program office estimates that most of these technologies 
will have reached a TRL 6 threshold by fiscal year 2006.

Table 1: Current and Expected Technical Maturity Levels of TSAT 
Technologies:

Critical technology: Information protection; TRL as of October 2003: 3-
4; When TRL 6 is expected: FY2006.

Critical technology: Laser communication; TRL as of October 2003: 4-5; 
When TRL 6 is expected: FY2006.

Critical technology: Information packet processing; TRL as of October 
2003: 6; When TRL 6 is expected: FY2003.

Critical technology: Antenna for communications on the move; TRL as of 
October 2003: 4-5; When TRL 6 is expected: FY2006.

Critical technology: Information transmission management; TRL as of 
October 2003: 3-4; When TRL 6 is expected: FY2006.

Critical technology: Protected bandwidth efficient modulation; TRL as 
of October 2003: 3-4; When TRL 6 is expected: FY2006.

Source: MILSATCOM Joint Program Office.

[End of table]

If one or more of TSAT's critical technologies encounters development 
problems, a backup technology should be available for insertion into 
the program. The laser communications technology does not have a backup 
provided by another satellite program. Typically, a backup technology 
does not meet all of the user's requirements and/or can negatively 
affect other design requirements of the new system, such as weight and 
power. For example, the alternative for TSAT's communications antenna 
is the current AEHF antenna, which does not provide the essential 
communications-on-the-move capability. Reverting to alternative 
technologies late in a development program results in a series of 
costly design changes and a need to go back to the warfighter to 
determine if the changes are acceptable.

Early Design Studies Have Not Been Started Yet:

As of October 2003, 2 months before TSAT's scheduled start, the Air 
Force had not awarded contracts for early design studies. In the case 
of successful programs, we have found that the developing contractor 
evaluates the early designs according to system engineering principles 
to assure that designs are technically feasible, match the user's 
needs, and can be accomplished within the time frame and funds 
available. Without this disciplined engineering process, programs can 
learn too late that designs needed to achieve the warfighter's 
requirements are not feasible. Program managers then have little choice 
but to ask for more time and money to develop better designs, or they 
must compromise by asking the warfighter to accept a less capable 
backup design or technology. When discovered late in a development 
program, these changes can be costly. Our prior work has shown that the 
cost to change the design increases significantly as a program 
progresses through the key decision points of an acquisition program. 
For this reason, most commercial companies want greater assurance early 
in a program that the design is feasible and producible.

The Air Force plans to competitively award contracts for early design 
studies in December 2003, which is when the TSAT program is scheduled 
to start. These studies are to be completed in 2006, when contractors 
are expected to deliver a design specification in preparation for final 
design efforts. To prepare for the next step--critical design review--
in 2007, the Air Force plans to assess the preliminary designs and 
select one or both contractors to continue with detailed design studies 
and development activities. Figure 2 shows key dates in TSAT's 
acquisition schedule.

After hearing senior warfighters express concerns about the ambitious 
schedule, the Air Force recently extended the launch date for the first 
TSAT from 2009 to 2011. However, the additional 2 years was mostly 
allocated to the build-and-test phase prior to launch. The front end of 
the acquisition schedule--technology development and design--remains 
much as it was before the extension. The technology development phase 
was not extended and the preliminary design and critical design review 
dates did not change. Based on our past reviews, the importance of 
technology development and design to the success of a program is 
critical and TSAT's current status shows significant immaturity to be 
overcome.

LACK OF EVALUATION CRITERIA RAISES CONCERNS ABOUT PENDING DECISION TO 
SHIFT FUNDS FROM TSAT TO AEHF:

Despite intense interest across DOD in the November 2004 decision, Air 
Force officials have not defined what evaluation criteria they intend 
to use to assess alternatives if the TSAT program should falter. Senior 
military commanders have asked for assurances that promised 
communications capabilities will be delivered early in the next decade. 
If TSAT is likely to miss its promised launch date of 2011, they want 
funding to be allocated to complete the AEHF constellation of 
satellites. However, senior DOD and Air Force officials told us that if 
a fourth AEHF were acquired and a full AEHF constellation were 
delivered to the warfighter as originally planned, decision makers and 
funding organizations within DOD may want to wait until AEHF has 
reached the end of its useful life before replacing it with a next-
generation satellite, such as TSAT. If the fourth AEHF is acquired, 
officials believe TSAT will be delayed by at least a decade. To these 
officials, this is not a tenable scenario because they see TSAT as the 
linchpin in DOD's plan to transform military communications and related 
combat systems.

To promote well-informed and objective investment decisions, our past 
work has found that decision makers establish and use measurable 
criteria for evaluating the costs, benefits, and risks of various 
alternatives. Although senior DOD and Air Force officials told us that 
they expect to have accomplished a number of tasks before making the 
November 2004 decision, they have not established measurable evaluation 
criteria for deciding whether to shift funds from TSAT back to AEHF.

CONCLUSIONS:

DOD has embarked on a new transformational communications architecture 
to take advantage of emerging technologies and to remove communications 
constraints from combat. The department has told the warfighter and 
Congress that TSAT is a key system that is necessary to achieve this 
architecture. Responding quickly, the Air Force has set an imminent 
deadline of December 2003 to start the TSAT program. By starting the 
program so soon, the Air Force is moving ahead without mature 
technologies and early design studies--two pillars of knowledge that 
would help program officials to reliably establish cost, schedule, and 
performance goals. This knowledge is not expected to be available until 
2006. Our work over the years has found that when programs have been 
started without the requisite knowledge, program managers and 
contractors are later burdened by unreasonable expectations about cost, 
schedule, and performance. Problems usually arise later that lead to 
cost increases, delays in delivering needed capability to the 
warfighters, and performance shortfalls.

For the planned November 2004 decision about whether to fund TSAT or 
AEHF, Air Force officials would be in a better position to make a well-
informed, objective decision if they establish and use specific 
criteria for evaluating alternative investments. Reporting the Air 
Force's decision-making criteria and rationale to Congress would 
enhance transparency and provide Congress with better information for 
its oversight and funding responsibilities.

RECOMMENDATIONS FOR EXECUTIVE ACTION:

To promote better cost, schedule, and performance outcomes, we 
recommend that you direct the Secretary of Air Force to delay the start 
of the TSAT acquisition program until technologies have been 
demonstrated to be at an acceptable level of maturity (at least TRL 6) 
and until the developing contractor has determined through systems 
engineering that the design is feasible and producible. We also 
recommend that you direct the Secretary to provide the appropriate 
level of funding necessary to gain this knowledge, which is critical 
for building a business case to start the TSAT program at a later time.

To promote a well-informed and objective decision--now scheduled for 
November 2004--about whether to fund another AEHF satellite, we further 
recommend that you direct the Secretary of Air Force to:

* establish measurable criteria for use when evaluating alternative 
investments in TSAT and AEHF and report this criteria in the Air 
Force's 2005 budget submission;

* consider the alternative investments in TSAT and AEHF against these 
measurable criteria; and:

* provide the rationale for how these criteria were applied in the Air 
Force's 2006 budget submission.

AGENCY COMMENTS AND OUR EVALUATION:

In commenting on a draft of this report, the Deputy Assistant Secretary 
of Defense for Networks and Information Integration disagreed with our 
primary recommendation to delay the start of the TSAT acquisition 
program until technologies are sufficiently matured and until the 
contractor determines through systems engineering principles that the 
design is feasible. DOD contends that the new Air Force National 
Security Space Acquisition Policy provides sufficient controls to allow 
concurrent development of technology and product design. DOD states 
that starting the TSAT program enables it to establish the funding and 
program controls--such as managing to the acquisition program baseline-
-provided by the new space acquisition policy. DOD did, however, concur 
or partially concur with the other recommendations to provide funding 
to mature TSAT's critical technologies and early designs, to establish 
criteria for making decisions, and to report these criteria and 
decisions to Congress.

We believe the new space acquisition policy does not have sufficient 
controls to reverse the higher costs and longer schedules that have 
plagued a number of satellite programs. The added risks of concurrent 
technology and product development have not helped improve the typical 
outcome for satellite programs. In a series of best practices reports 
issued over the years, we have identified problems resulting in 
substantially different cost and schedule outcomes when compared with 
initial expectations at the outset of a new acquisition program. We 
have offered improved approaches based on the best commercial and 
defense practices. DOD has endorsed the practices that call for a 
disciplined acquisition approach, one that separates technology from 
product development and bases decisions at key junctures on a set of 
critical product knowledge captured by the decision point. DOD 
incorporated this knowledge-based approach in its new acquisition 
system policy.[Footnote 7]

DOD's new space acquisition policy, on the other hand, is a step 
backward and is similar to an older acquisition policy that contributed 
to many unsuccessful acquisition programs of the past. DOD's history is 
filled with examples of programs that concurrently developed technology 
and new products and made decisions based on risk mitigation plans 
instead of knowledge about the new products. Our June 2003 
report[Footnote 8] on common problems in satellite programs identified 
Milstar, SBIRS-Low, SBIRS-High, AEHF, and others as suffering the 
consequences of this earlier acquisition strategy. Additionally, we 
have found that setting an acquisition program baseline that is not 
rooted in key product knowledge is unreliable and not useful as a 
management tool. In fact, starting the program before technologies are 
mature and a feasible design study is completed reduces accountability 
and straps the program manager and the contractor with unreasonable 
expectations in the baseline. Therefore, we believe that because DOD's 
new space acquisition policy does not require a knowledge-based 
acquisition strategy, it is destined to repeat the problems of the 
past.

DOD stated that extensive studies done over the last two years provide 
sufficient information for the Milestone Decision Authority to 
determine if the TSAT program should be initiated. However, these 
studies do not provide product-specific knowledge for building a 
business case for TSAT. Instead, these studies were focused on 
developing the overarching communications architecture rather than 
detailed technology and design information needed to build and launch 
TSAT.

While it is key to complete early design efforts before starting the 
program, substantial investments in system design and development are 
at risk if the Air Force cannot demonstrate TSAT's technologies, a 
number of which were still in the early paper study phase without 
hardware demonstrations to support that they would work. In its fiscal 
year 2004 budget submission, the Air Force had budgeted over $800 
million in fiscal years 2004 and 2005 for system design and 
development.

To support its case for starting the TSAT program in December 2003, DOD 
states backup technologies exist and are ready to fill any technology 
void that might occur. They believe this will reduce the risk. However, 
there are no backup technologies that will satisfy the two most 
critical warfighter requirements--laser communications (critical to 
transporting intelligence, surveillance, and reconnaissance data) and 
communications on the move (critical to the Future Combat System). 
These capabilities were the primary basis for persuading the warfighter 
to favor the uncertain future of TSAT rather than to acquire the full 
constellation of four AEHF satellites, which would have provided a 500 
percent increase over the communications capability used in Operation 
Iraqi Freedom.

If TSAT's investments were based on knowledge captured from mature 
technologies and feasible design, then these informed decisions would 
reduce the potential for major and costly changes as the program enters 
the build-and-demonstration phase, when it is too late to consider 
other options. We believe it is better to keep options open now, such 
as AEHF, and decide at a later time when enough knowledge has been 
gained to ensure TSAT is the right solution for the 2010 time frame. 
Our past work shows the negative outcomes of the concurrent and risk 
mitigation approach to acquisition. We also have shown the potential 
for more successful outcomes if a knowledge-based approach is applied. 
Therefore, we stand by our recommendation that TSAT's program start 
should be delayed until technologies are mature and the developing 
contractor has completed studies to demonstrate a feasible design.

To ensure that the warfighter is delivered an improved capability no 
later than 2011, DOD intends to decide in November 2004, based on an 
assessment of TSAT's progress, whether funding should be diverted back 
to the AEHF program. In its comments, the Air Force suggests criteria 
for this decision point that can only result in continuing the TSAT 
program. For example, criteria for laser communications or 
communications on the move do not apply to AEHF. These are capabilities 
promised by TSAT, not AEHF. We believe that the criteria should be 
based on the maturity of critical technologies and early design of 
TSAT. To ensure the transparency and objectivity of the decision 
process in November 2004, these criteria should be provided to Congress 
in the fiscal year 2005 budget for TSAT, not--as DOD suggests--in the 
2006 budget, when the decision will already have been made.

In response to DOD's detailed comments, we made changes to the report 
where appropriate to correct technical inaccuracies. DOD's comments are 
provided in enclosure III.

SCOPE AND METHODOLOGY:

In conducting our review, we analyzed the extent to which the TSAT and 
APS programs have acquired the knowledge needed to set specific cost, 
schedule, and performance goals. To do this, we compared the 
acquisition strategy with GAO's knowledge-based acquisition model and 
analyzed the differences between them. We specifically focused on the 
portion of knowledge-based acquisition dealing with the necessity of 
matching user's needs with developer's resources prior to making a 
development commitment. We collected and analyzed information from the 
Office of the Assistant Secretary of Defense for Command, Control, 
Communication and Intelligence (ASDC3I), Defense Information Services 
Agency (DISA), the National Security Agency (NSA), Air Force Space 
Command (AFSPC), U.S. Strategic Command (USSTRATCOM), Military 
Satellite Communication Joint Program Office (MJPO), Joint Forces 
Command (JFCOM), Aerospace Corporation and RAND Corporation. We 
conducted our review from February 2003 through November 2003 in 
accordance with generally accepted government auditing standards.

As you know, 31 U.S.C. 720 requires the head of a federal agency to 
submit a written statement of actions taken on our recommendations to 
the Senate Committee on Governmental Affairs and the House Committee on 
Government Reform not later than 60 days after the date of the report 
and to the Senate and House Committees on Appropriations with the 
agency's first request for appropriations made more than 60 days after 
the date of this report.

We are sending copies of this report to interested congressional 
committees. We will also make copies available to others upon request. 
In addition, the report will be available at no charge on the GAO Web 
site at http://www.gao.gov.

If you or your staff has any questions concerning this report, please 
contact me at (202) 512-4841. Key contributors to this report were Lily 
Chin, Mike Hazard, Dave Hubbell, Travis Masters, and Matt Mongin.

Sincerely yours,

Robert E. Levin:

Director, Acquisition and Sourcing Management:

Signed by: Robert E. Levin:

Enclosure I: Descriptions of Communication Satellites:

The Air Force is developing the following communication satellites.

Wideband Gapfiller Satellite:

The Wideband Gapfiller Satellite (WGS) system is a joint Air Force and 
Army program intended to provide communications to U.S. warfighters, 
allies, and coalition partners during all levels of conflict, short of 
nuclear war. WGS will provide essential communications services for the 
commanders in chief to command and control their tactical forces. 
Tactical forces will rely on WGS to provide high-capacity links to the 
terrestrial portion of the Defense Information Services Network. WGS is 
the next generation wide-band component in the Department of Defense's 
(DOD) future Military Satellite Communications architecture. WGS is 
composed of three principal segments: Space Segment (satellites), 
Terminal Segment (users), and Control Segment (operators). The WGS 
program is leveraging commercial methods and technological advances in 
the satellite industry to rapidly design, build, launch, and support a 
constellation of highly capable military communications satellites.

The WGS program is being conducted as a DOD commercial acquisition and 
as such is not subject to the same milestone and/or review processes 
required in other space acquisition programs. The Air Force reports 
that 95 percent of satellite content will be commercial off-the-shelf 
products. The total budget for purchasing five WGSs is $1.5 billion. 
The contract is firm fixed price over 10 years and was awarded to 
Boeing Satellite Systems in January 2001. The Air Force purchased the 
first two satellites in fiscal year 2002 and the third satellite in 
fiscal year 2003. It plans to purchase satellites four and five in 
fiscal years 2007 and 2008, respectively. The first two WGS satellites 
are scheduled for launch in fiscal year 2005, with the third satellite 
planned for launch in fiscal year 2006.

Upon first launch into geosynchronous orbit in 2005, WGS will be the 
DOD's most capable and powerful communications satellite. Ultimately, 
five WGSs will be in orbit, providing service in both the X-and Ka 
band-radio frequencies. Each satellite is expected to have a capacity 
of at least 2,100 megabits per second. WGS will augment X-band 
communications now provided by the Defense Satellite Communications 
System (DSCS) and one-way Ka-band service provided by the Global 
Broadcast Service (GBS). Additionally, WGS will provide new two-way Ka-
band services. These satellites are not interconnected. They will, 
however, provide communications capacity, connectivity, and 
flexibility for U.S. military forces while maintaining full 
interoperability with existing and programmed DSCS and GBS terminals.

Advanced Extremely High Frequency Satellite:

The Advanced Extremely High Frequency (AEHF) satellite system is to be 
DOD's next generation of high-speed, secure communication satellites. 
This satellite system is intended to replace the existing 
communications satellites with improved, survivable, jam-resistant, 
worldwide, secure communication capabilities at lower launch costs. 
AEHF is to support the entire range of data rates to provide assured 
communications across the entire spectrum of conflict, including 
nuclear war. AEHF is also designed to be "backward compatible" with 
existing satellites, that is, it will support both low and medium data 
rates as necessary until an AEHF constellation with higher data rates 
becomes available at initial operating capability (two satellites on 
orbit). The first satellite is currently planned to launch in 2006 and 
the second is scheduled to launch in 2007.

The Air Force is responsible for funding, developing, and producing the 
AEHF satellites and the associated ground control systems. The Air 
Force's budget for developing and acquiring the first three AEHF 
satellites is $4.8 billion. Each service--Army, Navy, and Air Force--is 
separately responsible for funding, developing, and producing its own 
terminals to communicate with AEHF.

The AEHF program began in August 1998, and the final constellation will 
be composed of satellites in geosynchronous orbit that can transmit 
data to each other via radio frequency cross links, and communicate 
with ground stations and communication terminals carried by air, sea, 
and ground forces. Each satellite will have a capacity of about 250 
megabits per second. Users communicate with the satellites through 
their terminals. The mission control segment provides command and 
control that directs the movements and other operations of satellites.

Transformational Satellite Communications:

The Transformational Satellite (TSAT) communications system is designed 
to provide improved, survivable, jam-resistant, worldwide, secure and 
general purpose communications as part of an independent but 
interoperable set of space-based systems that will support the National 
Aeronautics and Space Administration, DOD, and the intelligence 
community. TSAT will replace the current satellite system and 
supplement AEHF.

The TSAT architecture, requirements, and cost baselines are to be 
approved in December 2003. Initial design contracts are to be awarded 
in December 2003; therefore, the final configuration of the TSAT system 
remains to be determined. Air Force budget documentation for TSAT 
(funded under the Advanced Wideband Satellite budget line) shows a 
total cost of $10.9 billion for purchasing the first five satellites 
plus a spare.

The TSAT system will be the key transport mechanism of DOD's space-
based network communications system, which has individual satellites 
operating as routers in space. The TSAT constellation of five 
satellites will provide continuous communication coverage from 65 
degrees south latitude to 65 degrees north. The satellites will support 
communications in the EHF and Ka band radio frequency bands, in 
addition to passing communications via lasers. The capacity of each 
satellite is expected to be at least 10 times greater than the AEHF 
satellites. The Air Force is currently conducting development 
activities necessary in order to make a decision to start the program 
in December 2003. The Air Force plans to launch the first TSAT in 
fiscal year 2011. The first two satellites will have radio frequency 
satellite cross links to engage the AEHF satellites as well as having 
the laser cross links; the third through the fifth satellites will have 
laser cross links only.

Advanced Polar Satellite:

The Advance Polar System (APS) is a part of the Air Force's 
transformational communication architecture and is being developed and 
acquired as part of the TSAT/APS acquisition program. APS will provide 
the next generation protected EHF band, Ka band, and laser satellite 
communications capability in the north polar region starting in fiscal 
year 2012. APS will support strategic as well as tactical users who 
require anti-jam and low probability of detection EHF satellite 
communications. The results of the transformational communications 
architecture definition will affect the APS program content. 
Requirements are based on the July 1995 Polar Operational Requirements 
Document. According to Air Force program officials, APS is to be a 
"lighter" (i.e., lower capacity) version of the TSAT. The current APS 
plan is to acquire three satellites (two funded with development funds 
and one funded with procurement dollars) and associated ground 
infrastructure for $1.2 billion. The three APS satellites will be 
placed in highly inclined orbits and are expected to provide continuous 
communication services to forces deployed from 65 degrees north to the 
North Pole (90 degrees north).

Enclosure II: Descriptions of Technology Readiness Levels:

The Interim Defense Acquisition Guidebook (formerly DOD 5000.2-R) 
directs that technology readiness assessments, using Technology 
Readiness Levels (TRL) or some equivalent assessment methodology, for 
critical technologies shall occur sufficiently before key decision 
points B and C to provide useful technology maturity information to the 
acquisition review process. TRLs, originally developed by the National 
Aeronautics and Space Administration (NASA), are measured along a scale 
of 1 to 9, starting with paper studies of the basic concept and ending 
with a technology that has proven itself in actual usage on the 
intended product. As the TRL scale increases, the risks associated with 
uncertain technology decrease, because more is known about their 
capabilities and performance. Unexpected problems can arise at every 
level, and effort must be expended to overcome them. This effort takes 
time and can delay the progress to the next readiness level. According 
to our previous reviews of best commercial practices and DOD guidance, 
a minimum level of TRL 6 should be reached before committing to a space 
acquisition program. Table 1 provides a detailed explanation of each 
TRL.

Table 2: TRL Scale for Assessing Critical Technologies:

Technology Readiness Levels: 1. Basic principles observed and 
reported; Technology Readiness Level Description: Lowest level of 
technology readiness. Scientific research begins to be translated into 
technology's basic properties.

Technology Readiness Levels: 2. Technology concept and/or application 
formulated; Technology Readiness Level Description: Invention begins. 
Once basic principles are observed, practical applications can be 
invented. The application is speculative and there is no proof or 
detailed analysis to support the assumption. Examples are still 
limited to paper studies.

Technology Readiness Levels: 3. Analytical and experimental critical 
function and/or characteristic proof of concept; Technology Readiness 
Level Description: Active research and development is initiated. This 
includes analytical studies and laboratory studies to physically 
validate analytical predictions of separate elements of the 
technology. Examples include components that are not yet integrated or 
representative.

Technology Readiness Levels: 4. Component and/or breadboard validation 
in laboratory environment; Technology Readiness Level Description: 
Basic technological components are integrated to establish that the 
pieces will work together. This is relatively "low fidelity" compared 
to the eventual system. Examples include integration of "ad hoc" 
hardware in a laboratory.

Technology Readiness Levels: 5. Component and/or breadboard validation 
in relevant environment; Technology Readiness Level Description: 
Fidelity of breadboard technology increases significantly. The basic 
technological components are integrated with reasonably realistic 
supporting elements so that the technology can be tested in simulated 
environment. Examples include "high fidelity" laboratory integration 
of components.

Technology Readiness Levels: 6. System/subsystem model or prototype 
demonstration in a relevant environment; Technology Readiness Level 
Description: Representative model or prototype system, which is well 
beyond the breadboard tested for level 5, is tested in a relevant 
environment. Represents a major step up in a technology's demonstrated 
readiness. Examples include testing a prototype in a high fidelity 
laboratory environment or in simulated operational environment.

Technology Readiness Levels: 7. System prototype demonstration in an 
operational environment; Technology Readiness Level Description: 
Prototype near or at planned operational system. Represents a major 
step up from level 6, requiring the demonstration of an actual system 
prototype in an operational environment. Examples include testing the 
prototype in a test bed aircraft.

Technology Readiness Levels: 8. Actual system completed and qualified 
through test and demonstration; Technology Readiness Level 
Description: Technology has been proven to work in its final form and 
under expected conditions. In almost all cases, this level represents 
the end of true system development. Examples include developmental 
test and evaluation of the system in its intended weapon system to 
determine if it meets design specifications.

Technology Readiness Levels: 9. Actual system proven through 
successful mission operations; Technology Readiness Level Description: 
Actual application of the technology in its final form and under 
mission conditions, such as those encountered in operational test and 
evaluation. Examples include using the system under operational 
mission conditions. 

Source: GAO based on NASA and DOD guidance.

[End of table]

Enclosure III: Comments From the Department of Defense:

OFFICE OF THE ASSISTANT SECRETARY OF DEFENSE: 
6000 DEFENSE PENTAGON 
WASHINGTON, DC 20301-6000:

NOV 21 2003:

NETWORKS AND INFORMATION INTEGRATION:

Mr. Robert E. Levin:

Director, Acquisition and Sourcing Management: 
U. S. General Accounting Office:

Washington, D.C. 20548:

Dear Mr. Levin,

This is the Department of Defense (DoD) response to the General 
Accounting Office (GAO) draft report, "Space Acquisitions: Committing 
Prematurely to the Transformational Satellite Program Elevates Risks 
for Poor Cost, Schedule, and Performance Outcomes," GAO-04-71R (GAO 
Code 120225) dated October 29, 2003.

The report includes five recommendations to the SECDEF. The Department 
of Defense non-concurs with the first recommendation, and partially 
concurs or concurs with the remaining four. Specific DoD comments on 
each of the recommendations are enclosed as Attachment 1.

The DoD does not agree with the key finding of the GAO report that the 
Air Force is not currently prepared to make informed decisions 
regarding either the starting of the TSAT program in the December 2003 
timeframe or to shift funding from TSAT to AEHF in November 2004. The 
DoD has conducted extensive studies at the architecture and systems 
level over the past two years, by the government and by three 
contractor teams. The government developed a reference architecture 
which validated a point solution that satisfies a set of cost / 
schedule / performance criteria. The users at a Senior Warfighter Forum 
(SWarF) and JROC approved this architecture. The DoD believes that 
contractor, government, and FFRDC studies are providing sufficient 
information to the TSAT Milestone Decision Authority to determine if 
the program is sufficiently mature to warrant transition into a formal 
acquisition program at Phase B of the NSS Acquisition Policy 03-01.

The GAO report expresses concern that moving the TSAT program past KDP-
B before the relevant technologies are at Technology Readiness Level 
(TRL)-6 could induce substantial cost, schedule, and performance risk. 
The DoD has mitigated these risks by developing an evolutionary 
acquisition strategy and technology investment plan structured to have 
all relevant technologies reach TRL 6 prior to system PDR. This 
technology investment plan will allow us to manage progress and, among 
other things, plan in advance if we need to use already identified 
fallback technologies to mitigate risk. We will manage this technology 
investment to detailed milestones in order to be able to make decisions 
as to if and when a fallback technology must be used if the primary 
technology does not mature as planned. These fallback technologies are 
all already at, or above, TRL-6. Even if the initial increment one 
TSAAs have to use all of the fallback technologies, which is not 
likely, they would still be much more capable than AEHF. Additionally, 
even a reduced capability increment one TSAT puts DoD on the path to 
transformation and net-centric capability, so critical to our future 
operations.

While we agree with the GAO that it would be inappropriate to commit to 
a detailed design with immature technology, we note that NSS 
Acquisition Policy 03-01 states that Space Programs are to be baselined 
at the beginning of the Risk Reduction and Technology Development 
phase, which is KDP-B. The increase in reporting requirements, and the 
program reviews associated with a baselined Phase B program facilitates 
increased DoD oversight/insight. The Transformational Communications 
MILSATCOM (TCM) program acquisition strategy has been developed in 
accordance with this precept, which, again, is the reason our 
technology investment plan is structured to have all relevant 
technologies reach TRL 6 prior to system PDR. This approach allows 
development of these maturation plans in synchronization with 
development of the program requirements. This, in turn, allows the 
products based on the technologies to be tailored to best meet and 
refine user needs within cost, schedule and risk constraints. Program 
management and DoD insight are aided by maintenance of an APB 
(Acquisition Program Baseline), through periodic acquisition reports, 
and through the program reviews associated with Phase B (e.g. SDR and 
PDR). User needs are tracked through the transition of the Capabilities 
Development Document (CDD) into the Capabilities Production Document 
(CPD). To expend the funds that the GAO and the Air Force agree are 
required without the reporting and review associated with a baselined 
program may, in fact, limit the effectiveness of the technology 
maturation.

It is also important to realize that the TSAT system will be procured 
using a capabilities based approach. In order to maintain schedule and 
cost, capabilities will be traded in a joint warfighter/ acquisition 
forum. This "cost as an independent variable" (CAN) approach allows the 
DoD to develop affordable increments of militarily useful capability. 
We believe that the best way to provide the most transformational 
capability to the warfighter at the earliest possible date is to pursue 
this approach, and proceed to a KDP-B.

The GAO report itself contains a number of technical and other 
inaccuracies. Detailed comments are provided in Attachment 2.

The DoD appreciates the opportunity to respond to the GAO draft report.

Signed by: 

Michael S. Frankel:

Deputy Assistant Secretary of Defense: 
Networks and Information Integration (C3, Space, and IT Programs):

Enclosures:

DoD Comments to GAO Recommendations Detailed Technical Comments on GAO 
Report:

Attachment 1:

GAO DRAFT REPORT DATED OCTOBER 29, 2003 GAO-04-71R (GAO CODE 120225):

"Space Acquisitions: Committing Prematurely to the Transformational 
Satellite Program Elevates Risks for Poor Cost, Schedule and 
Performance Outcomes":

DEPARTMENT OF DEFENSE COMMENTS TO THE GAO RECOMMENDATIONS:

RECOMMENDATION 1: The GAO recommended that the Secretary of Defense 
direct the Secretary of the Air Force to delay the start of the TSAT 
acquisition program until technologies have been demonstrated to be at 
an acceptable level of maturity (at least TRL 6) and until the 
developing contractor has determined through systems engineering that 
the design is feasible and producible. (p. 9/GAO Draft Report):

DOD RESPONSE: Non-Concur. Technologies selected for incorporation on 
TSAT will be at or above Technology Readiness Level 6 by Preliminary 
Design Review in FY06. The DoD has further mitigated technology risk by 
developing an evolutionary acquisition strategy. This strategy allows 
us to select from identified fallback technologies if required to 
mitigate program risk. These fallback technologies are all already at, 
or above, TRL-6. Even if the initial increment one TSATs had to use all 
o^ the fallback technologies, which is not likely, they would still be 
much more capable than AEHF. Additionally, even a reduced capability 
increment one TSAT puts DoD on the path to transformation and net-
centric capability, so critical to our future operations. Program 
initiation, governed by National Security Space (NSS) Acquisition 
Policy 03-01, begins before PDR.

RECOMMENDATION 2: The GAO recommended that the Secretary of Defense 
provide the appropriate level of funding necessary to gain this 
knowledge, which is critical for building a business case to start the 
TSAT program at a later time.

(p. 9/GAO Draft Report):

DOD RESPONSE: Partially Concur. The DoD is currently reviewing TSAT 
RDT&E funding to ensure that it is adequate to do the technology and 
non-recurring engineering work necessary to acquire the program with 
reasonable risk. The DoD will re-visit funding each year to ensure 
adequate funding is maintained to achieve TSAT program objectives. The 
DoD position is that the Dec 03 - Jan 04 timeframe is the proper time 
to start the TSAT program and establish a program baseline so that 
these investments can be properly tracked and managed. Our evolutionary 
strategy, fallback technologies, and CAIV approach will allow us to 
manage risk while developing an affordable increment of militarily 
useful capability.

RECOMMENDATION 3: The GAO recommended that the Secretary of Defense 
direct the Secretary of the Air Force to establish measurable criteria 
for use when evaluating alternative:

Attachment 1:

investments in TSAT and AEHF and report these criteria in the Air 
Force's 2005 budget submission. (p. 10/GAO Draft Report):

DOD RESPONSE: Partially Concur. The decision will be based on known 
risks balanced against warfrghter requirements. Measurable criteria are 
being developed and will be used to make this decision in November 
2004. For example, one of the criteria we are considering is the 
ability to support communications on the move (COTM) at data rates 
above 250 kbps to a one-foot antenna mounted on a vehicle traveling at 
speeds above 25 mph. Another is the ability to support multiple high 
date rate Airborne ISR missions with interoperable laser communications 
links. The DoD will provide these criteria and resulting decision as 
part of the FY06 President's Budget process.

RECOMMENDATION 4: The GAO recommended that the Secretary of Defense 
direct the Secretary of the Air Force to consider the alternative 
investments in TSAT and AEHF against these measurable criteria. (p. 10/
GAO Draft Report):

DOD RESPONSE: Concur. The investment strategy for TSAT will support an 
evolutionary approach potentially using fallback technologies, this 
approach will allow us to manage risk while developing an affordable 
increment of militarily useful capability much more advanced than AEHF. 
This approach will also start us on the transformational path to net-
centric operations that can be integrated with the DOD's other 
investments in transformational capabilities. These TSAT results will 
be compared to progress on the AEHF program, and against measurable 
criteria to form the basis of our decision. The DoD will use all 
appropriate criteria and consider alternative investments strategies 
that satisfy the needs of the warfighters.

RECOMMENDATION 5: The GAO recommended that the Secretary of Defense 
direct the Secretary of the Air Force to provide the rationale for how 
these criteria were applied in the Air Force's 2006 budget submission. 
(p. 10/GAO Draft Report):

DOD RESPONSE: Concur. We will use the results of our evolutionary 
acquisition strategy as the basis of our FY06 budget submission to 
Congress. When the 2006 DoD budget is submitted in February 2005, the 
investment strategy will support the November 2004 decision to either 
buy a fourth AEHF and potentially slow the TSAT program, or proceed 
with TSAT as planned. The rationale and supporting data will be shared 
with Congress.

[End of section]

(120225):

FOOTNOTES

[1] The TSAT program also includes development of another satellite, 
the Advanced Polar System (APS). Because development efforts for TSAT 
and APS are similar, we are referring to both programs as TSAT in this 
report. More information about APS is included in enclosure I.

[2] 10 U.S.C. sections 2220 and 2435.

[3] U.S. General Accounting Office, Military Space Operations: Common 
Problems and Their Effects on Satellite and Related Acquisitions, GAO-
03-825R (Washington, D.C.: June 2, 2003).

[4] U.S. General Accounting Office, Defense Acquisitions: Improvements 
Needed in Space Systems Acquisition Management Policy, GAO-03-1073 
(Washington, D.C.: Sept. 15, 2003).

[5] U.S. General Accounting Office, Best Practices: Better Management 
of Technology Development Can Improve Weapon System Outcomes, GAO/
NSIAD-99-162 (Washington, D.C.: July 30, 1999); and U.S. General 
Accounting Office, Best Practices: Better Matching of Needs and 
Resources Will Lead to Better Weapon System Outcomes, GAO-01-288 
(Washington, D.C.: Mar. 8, 2001).



[6] DOD Instruction 5000.2, Operation of the Defense Acquisition 
System, May 12, 2003.

[7] DOD Directive 5000.1 and Instruction 5000.2.

[8] U.S. General Accounting Office, Military Space Operations: Common 
Problems and Their Effects on Satellite and Related Acquisitions, GAO-
03-825R (Washington, D.C.: June 2, 2003).