This is the accessible text file for GAO report number GAO-02-1069R 
entitled 'District of Columbia: Status of Construction of the 
Convention Center' which was released on September 24, 2002. 

This text file was formatted by the U.S. General Accounting Office 
(GAO) to be accessible to users with visual impairments, as part of a 
longer term project to improve GAO products' accessibility. Every 
attempt has been made to maintain the structural and data integrity of 
the original printed product. Accessibility features, such as text 
descriptions of tables, consecutively numbered footnotes placed at the 
end of the file, and the text of agency comment letters, are provided 
but may not exactly duplicate the presentation or format of the printed 
version. The portable document format (PDF) file is an exact electronic 
replica of the printed version. We welcome your feedback. Please E-mail 
your comments regarding the contents or accessibility features of this 
document to Webmaster@gao.gov. 

This is a work of the U.S. government and is not subject to copyright 
protection in the United States. It may be reproduced and distributed 
in its entirety without further permission from GAO. Because this work 
may contain copyrighted images or other material, permission from the 
copyright holder may be necessary if you wish to reproduce this 
material separately. 

United States General Accounting Office: 

Washington, DC 20548: 

September 24, 2002: 

The Honorable Constance A. Morella: 
Chairwoman: 
Subcommittee on the District of Columbia: 
Committee on Government Reform: 
House of Representatives: 

Subject: District of Columbia: Status of Construction of the Convention 
Center: 

Dear Madam Chairwoman: 

You asked us to provide periodic briefings on the status of the 
construction of the new convention center in Washington, D.C. The 
convention center is being constructed in accordance with the 
Washington Convention Center Authority Act of 1994, which authorizes 
the Washington Convention Center Authority (WCCA) to construct, 
maintain, and operate a new convention center while continuing to
maintain and operate the existing convention center. 

As agreed with your office, we reviewed information related to the 
status of the convention center construction, costs, and financing as 
of June 2002, the most recent information available at the time of our 
review. 

Specifically, our objectives were to provide information on (1) issues 
related to the Revised Guaranteed Maximum Price agreement (RGMP) 
[Footnote 1] set in January 2002, (2) the status of construction and 
significant construction issues that could delay completion of the 
project, (3) whether the January 2002 estimated total project cost 
[Footnote 2] of $799.5 million has changed, and, if so, the causes and 
nature of the changes, and (4) whether WCCA’s funding appears to be 
sufficient to cover the current estimated total project cost. 

In order to meet these objectives, we reviewed the RGMP, held 
discussions with and obtained information from WCCA officials and the 
DC City Council’s oversight contractor for the project, reviewed the 
construction manager’s (CM) and WCCA’s monthly progress reports and 
WCCA’s financing plan, visited the construction site, and considered 
the results of our prior work, which were most recently reported to you 
in January 2002. [Footnote 3] We conducted our work from April through 
August 2002 in accordance with generally accepted government auditing 
standards. 

On August 22, 2002, we briefed the staff of your subcommittee on the 
preliminary results of our review. This letter transmits material from 
that briefing, which includes data through June 30, 2002, the most 
recent information available at the time we prepared this report. The 
briefing slides are included in enclosure I. 

Results in Brief: 

On January 31, 2002, the RGMP was set by the CM and WCCA at $590.7 
million. As part of the RGMP agreement, WCCA is responsible for cost 
increases resulting from changes in design and scope (and not 
attributable to improper management by the CM and subcontractor error). 
As of June 30, 2002, the RGMP has increased by $7 million to $597.7 
million. These increases were related to changes in design and the 
resulting scopes of work for specific building trades. WCCA officials 
told us that the RGMP would continue to increase as a result of such 
changes and that they are working to quantify the extent. 

The project construction schedule, as established by the RGMP, includes 
the following deadline dates for the project: (1) substantial 
completion [Footnote 4] of convention-ready areas [Footnote 5] by March 
31, 2003, (2) substantial completion of all remaining areas by June 30, 
2003, and (3) final completion [Footnote 6] by October 1, 2003. As of 
July 2002, according to WCCA officials, the convention center 
construction activities were approximately 80 percent complete. 
Although the project was 20 days behind schedule as of June 2002, WCCA 
officials say they are taking steps to meet the current construction 
schedule. WCCA has identified several significant construction issues 
that, if not resolved, could delay completion. WCCA is working with the 
CM and architect/engineering team to address these issues. 

A critical milestone that must be achieved in order for WCCA to 
maintain the construction schedule is completing the facility’s 
exterior shell, which WCCA had initially anticipated occurring in late 
October or early November 2002. WCCA has now set a time frame for this 
to occur in December 2002. Missing the December 2002 milestone could 
significantly affect the project schedule, delaying completion of the
interior work and adding to the risk of delaying the completion of the 
convention center. In the event that WCCA does not meet the December 
2002 milestone, a mitigation plan has been developed which WCCA 
officials described as allowing critical interior work to proceed in a 
dry environment. 

According to WCCA, the total estimated project cost remained at $799.5 
million as of June 2002. However, WCCA has identified several factors 
that will increase the project cost. WCCA has quantified potential cost 
increases of $23.8 million. Additional costs are anticipated by WCCA 
for unspecified mechanical, electrical, and plumbing (MEP) changes and 
to negotiate and settle CM submitted and unsubmitted change orders of 
$38.1 million. As of June 2002, WCCA’s total estimated cost of $799.5 
million included $9.8 million in contingency and owner’s adjustment 
accounts to cover unanticipated cost increases. WCCA is working with 
the CM to minimize the effects of potential cost increases. 

The estimated project funding available as of June 30, 2002, was $822.5 
million, or $6.8 million more than the $815.7 million projected as 
available during January 2002. As of June 30, 2002, $805.4 million, or 
98 percent of the total projected funding has been received. Assuming 
all projected funding is collected and no cost growth occurs, there 
would be residual funding of about $23 million based on the June 30, 
2002, cost and funding estimates. Adding this amount and the 
approximately $9.8 million of contingency and owner’s adjustment 
account balance now included in the $799.5 million estimated project 
cost for unanticipated cost increases, the amount available to absorb 
cost increases could be $32.8 million. As of June 2002, known cost 
increases totaled $23.8 million and there are also a number of known but
unquantified and unnegotiated changes. WCCA officials noted that they 
continue their efforts to implement cost-reducing measures. WCCA 
officials told us that they believe the available funding will be 
sufficient to cover the total estimated project costs, including the 
estimated cost increases associated with factors discussed in this 
briefing through the end of the project. 

We provided WCCA a copy of the transmittal letter and slides for 
comment. WCCA agreed that the draft letter and briefing slides 
accurately reflect the status of the convention center project. WCCA 
also provided some technical comments and clarifications which we have 
incorporated as appropriate throughout the briefing slides. 

We are sending copies of this report to the Ranking Minority Member of 
your Subcommittee. We are also sending copies to the Chairmen and 
Ranking Minority Members of the Subcommittee on the District of 
Columbia; Senate Committee on Appropriations, Subcommittee on the 
District of Columbia; House Committee on Appropriations and other 
interested congressional committees. This letter will also be available 
on GAO’s home page at [hyperlink, http://www.gao.gov]. 

If you have any questions, please contact me at (202) 512-9471 or by e-
mail at franzelj@gao.gov. Key contributors to this letter were Keith A. 
Thompson, Terrell G. Dorn, Arkelga L. Braxton, Maria D. Edelstein, and 
Donell L. Ries. 

Sincerely yours, 

Signed by: 

Jeanette M. Franzel: 
Director, Financial Management and Assurance: 

Enclosure: 

[End of section] 

Enclosure: 

U.S. General Accounting Office: 
Financial Management and Assurance Team: 

District of Columbia Government: 
Status of the New Convention Center Project: 

Briefing for the Staff of the House Committee on Government Reform, 
Subcommittee on the District of Columbia: 

August 22, 2002: 

Introduction/Objectives: 

You asked us to provide periodic briefings on the status of the 
construction, costs, and financing of the new Washington, D.C., 
convention center. 

Our objectives were to provide information on: 

* issues related to the Revised Guaranteed Maximum Price agreement 
(RGMP), which was set in January 2002; 

* the status of construction and significant construction issues that 
could delay completion of the project; 

* whether the January 2002 estimated total project cost of $799.5 
million has changed, and if so, the causes and nature of the changes; 
and; 

* whether the Washington Convention Center Authority’s (WCCA) funding 
appears to be sufficient to cover current estimated project costs. 

Background: 

The Washington Convention Center Authority Act of 1994 authorizes WCCA 
to construct, maintain, and operate the new convention center as well 
as to maintain and operate the existing convention center. 

WCCA’s Managing Director/Development oversees the contract and the 
construction with the assistance of the program manager, a group made 
up primarily of three consulting groups and several subcontractors. 

The Construction Manager (CM) is a joint venture responsible for the 
construction of the new convention center. 

The construction management services agreement between the CM and WCCA 
includes a Guaranteed Maximum Price (GMP) for hard costs--which include
construction costs such as site work, concrete, and metals--but 
excludes soft-cost items. [Footnote 7] 

The GMP is intended to represent the final construction price 
negotiated for hard costs between the CM and WCCA. However, adjustments 
to the GMP may be made to reflect quantities and costs that differ from 
the baseline assumptions as the project progresses. 

The CM and WCCA executed the RGMP agreement for $590.7 million on 
January 31, 2002. 

The DC City Council has hired a contractor to provide periodic status 
reports on the construction of the convention center. 

Results in Brief: 

Although the RGMP was set at $590.7 million in January 2002, WCCA is 
responsible for cost increases resulting from design and scope changes, 
except for such increases that are the result of improper management by 
the CM. 

The RGMP has increased $7.0 million, from $590.7 million at January 31, 
2002, to $597.7 million as of June 30, 2002. These increases were 
related to changes in the design and scope of electrical and roofing 
work, metals work, and mechanical, electrical, and plumbing (MEP) work. 

WCCA officials told us that the RGMP will increase as a result of 
design and scope changes related to steel, MEP, and fireproofing 
trades. 

A critical milestone in maintaining the construction schedule is 
completing the facility’s exterior shell, which WCCA had initially 
anticipated occurring in late October or early November 2002. However, 
WCCA has now set a time frame for this to occur in December 2002. 
Missing the December 2002 milestone could affect the timeliness of 
completion of the convention center. 

According to WCCA officials, the convention center construction 
activities were approximately 80 percent complete as of July 2002, and 
WCCA is taking steps to meet the current construction schedule. 

WCCA is working with the CM and the Architect/Engineer (A/E) team to 
address significant issues that could delay completion of the project. 

Total estimated project cost remained at $799.5 million, according to 
WCCA, including available contingency balances of $9.8 million, as of 
June 2002 (contingency balance outside of the RGMP of $7.2 million and 
owner’s adjustment account in the RGMP of $2.6 million). 

WCCA has identified several factors that could result in a projected 
cost increase of $23.8 million. In addition, WCCA has identified other 
potential increases that are not yet quantified. 

WCCA is working with the CM to minimize the effects of factors that 
could lead to cost increases. 

WCCA has established allowances/reserves to cover costs that are 
anticipated but not completely quantified and a contingency amount to 
cover unanticipated cost increases. 

Available project funding increased from $815.7 million in January 2002 
to $822.5 million in June 2002, according to WCCA. 

The estimated funding sources of $822.5 million, less total estimated 
project costs of $799.5 million, resulted in an estimated residual 
funding, as of June 30, 2002, of $23 million. However, WCCA has stated 
that the total estimated cost will increase. 

The estimated residual funding added to the contingency and owner’s 
adjustment account totals $32.8 million. When compared to the 
quantified potential cost increases, the potential excess available 
funding is $9.0 million as of June 30, 2002. However, all of these 
figures are subject to uncertainty. 

WCCA officials told us that they believe the available funding amount 
will be sufficient to cover the total estimated project costs, 
including identified potential cost increases through the end of the 
project. 

We requested comments on a draft of these briefing slides from WCCA’s 
Chief Financial Officer and Managing Director/Development, who agreed 
that the draft letter and briefing slides accurately reflect the status 
of the convention center project. They also provided technical comments 
and clarification which we have incorporated as appropriate throughout 
the briefing slides. 

Revised Guaranteed Maximum Price: 

On January 31, 2002, the RGMP was set by the CM and WCCA at $590.7 
million. However, WCCA is responsible for cost increases resulting from 
changes in design and scope (and not attributable to improper 
management by the CM and subcontractor error). Any such increase will 
have to be absorbed by WCCA’s available funding. 

The RGMP has increased $7.0 million from $590.7 million at January 31, 
2002, to $597.7 million as of June 30, 2002. These increases were 
related to changes in design and scope for electrical and roofing work, 
metals work, and MEP work. WCCA must absorb these cost increases. 

WCCA officials told us that the RGMP will increase as a result of cost 
increases resulting from changes in design and scope related to steel, 
MEP, and fireproofing trades. WCCA estimated a $3.2 million increase 
related to steel but was unable to determine the amount of the other 
potential increases at the time of our review. 

The RGMP consists of seven cost components. Table 1 shows the 
components and the corresponding amounts as of June 30, 2002. 

Table 1: Components of the RGMP and Costs as of June 30, 2002 (Dollars 
in millions): 

Amount: $496.8; 
Description: Work that was included in the scope of the original GMP 
amendment. This amount includes allowances and reserves for remaining 
purchases, unit rate allowances, and submitted and unsubmitted change 
orders that WCCA tracks separately. 

Amount: $15.9; 
Description: Work related to hazardous material removal cost. 

Amount: $36.2; 
Description: Out-of-scope estimate for Metro station, 
telecommunications, food service, audiovisual, and certain utility 
work. 

Amount: $33.0; 
Description: Estimate for the cost of general conditions and general 
requirements[A]. 

Amount: $12.9; 
Description: Construction fee to be paid to the CM[B]. 

Amount: $0.3; 
Description: Utility relocation fee. 

Amount: $2.6; 
Description: Owner’s adjustment account to be used at WCCA’s 
discretion. 

Amount: $597.7; 
Description: Total cost of RGMP components. 

[A] The estimate for the cost of general conditions and general 
requirements consists of CM field overhead items such as onsite 
trailers, onsite staff, blueprinting, fringe benefits, and consultants. 

[B] The construction fee is the CM’s profit and home office overhead 
for managing the project. It consists of the amount in the original GMP 
of $9.5 million and increases due to change orders and out-of-scope 
work. 

[End of table] 

Status of Construction: 

A critical milestone that must be achieved in order for WCCA to 
maintain the construction schedule is completing the facility’s 
exterior shell, which WCCA had initially anticipated occurring in late 
October or early November 2002. However, WCCA has now set a time frame 
for this to occur in December 2002. 

Missing the December 2002 milestone could significantly affect the 
project schedule, delaying completion of the interior work and adding 
to the risk of delay in timely completion of the convention center. 

In the event that WCCA does not meet the December 2002 milestone, 
mitigating plans include installation of temporary weather walls and 
weather protection that would allow critical interior work to proceed 
in a dry environment. 

The following deadlines were reset in the RGMP: 

* substantial completion [Footnote 8] of convention-ready areas 
[Footnote 9] by March 31, 2003; 

* substantial completion of all remaining areas by June 30, 2003; and; 

* final completion [Footnote 10] by October 1, 2003. 

According to WCCA officials, the convention center construction 
activities were approximately 80 percent complete as of July 31, 2002, 
and WCCA is taking steps to meet the current construction schedule. 

WCCA has identified several significant construction issues that, if 
not resolved, could delay completion of the project. WCCA is working 
with the CM and A/E team to address these issues, including: 

* increasing the number of workers, overtime, or both in order to 
expedite the exterior enclosure work and the interior trades work to 
meet the deadline dates; 

* providing a sufficient period of time to move into the facility and 
establish operations of the major systems, and; 

* expediting the landscape/hardscape [Footnote 11] work, which is
currently several months behind schedule. 

In the event that the CM does not meet the June 30, 2003, substantial 
completion date, the CM would be required to pay $50,000 per day for 
each calendar day of delay. However, unless the delay is the result of 
the CM’s gross negligence in conducting its management responsibility 
or the CM’s deliberate failure to comply with a material directive from
WCCA, WCCA must accept from the CM an assignment of CM claims against 
subcontractors as payment of liquidated damages. 

Status of Costs: 

Estimated Costs: According to WCCA, the total estimated project cost 
remained at $799.5 million as of June 2002 (see table 2). 

Table 2: Comparison of WCCA’s Unaudited Estimated Costs for the New 
Convention Center as of September 1998, January 2002, and June 2002 
(Dollars in thousands): 

Project component: WCCA-estimated hard costs[A]: 
Estimate as of 9/1998: $505,600; 
Estimate as of 1/2002: $590,678; 
Estimate as of 6/2002: $597,669. 

Project component: WCCA-estimated soft costs[B]: 
Estimate as of 9/1998: $118,903; 
Estimate as of 1/2002: $145,524; 
Estimate as of 6/2002: $143,462. 

Project component: Contingency[C]: 
Estimate as of 9/1998: $30,497; 
Estimate as of 1/2002: $9,966; 
Estimate as of 6/2002: $7,159. 

Project component: Estimated cost of outsourced work[D]: 
Estimate as of 9/1998: $59,000; 
Estimate as of 1/2002: $53,380; 
Estimate as of 6/2002: $51,258. 

Project component: Total estimated construction costs: 
Estimate as of 9/1998: $714,000; 
Estimate as of 1/2002: $799,548; 
Estimate as of 6/2002: $799,548; 
Percentage change from 9/1998 to 6/2002: 12.0. 

[A] Hard costs are construction costs related to the physical structure 
of the facility, such as masonry, concrete, hazardous material removal, 
and structural steel. This line item also includes an owner’s 
adjustment account of $2.6 million as of June 30, 2002, which is a 
contingency within the RGMP. 

[B] Soft costs are construction costs that are not related to the 
physical structure of the facility, such as design fees, legal costs, 
and consulting and inspections. This line item also includes $10.8 
million of other costs, which include administrative costs related to
marketing, public affairs, and salaries of staff dedicated to the 
project. 

[C] The contingency is an estimate in the project’s budget that is 
earmarked for cost increases. 

[D] Estimated cost of such outsourced work as work on the Metro 
station, utility relocation, central plant, telecommunications, and
food service, for which WCCA has identified specific funding sources as 
a part of the total available financing. 

Source: WCCA records. 

[End of table] 

WCCA had incurred $576.6 million or 72 percent of the $799.5 million 
total estimated project cost as of June 30, 2002. 

Although construction costs were within the total project cost estimate 
at the time of our review, WCCA has identified factors that will 
increase costs. 

WCCA has quantified potential cost increases of $23.8 million (as shown 
in table 3) related to such factors as: 

* accelerated construction activities; 
* MEP coordination issues [Footnote 12]; 
* second shift and overtime work; 
* projected cost overrun for the Metro station; 
* back-up steel associated with the exterior enclosure, and; 
* Department of Public Works (DPW) hardscape subcontract. 

WCCA officials stated that the quantified potential cost increases may 
not impact the total estimated project cost. WCCA is still assessing 
the exposures and their potential cost impact. 

For other factors that it is working to address, WCCA had not, at the 
time of our review, specified a cost estimate or had not finalized its 
estimate. These factors include: 

* implementing MEP design changes and; 

* the CM’s submitted and unsubmitted change orders outstanding, which 
totaled $38.1 million as of June 2002. 

Table 3: Summary of Potential Cost Increases as of June 2002 (Dollars 
in thousands): 

Potential cost increases: Accelerated construction activities and MEP 
coordination costs[A]; 
Estimated amounts: $13,200. 

Potential cost increases: Second shift and overtime; 
Estimated amounts: $2,600; 

Potential cost increases: Projected cost overrun for Metro station; 
Estimated amounts: $1,800. 

Potential cost increases: Back-up steel associated with exterior 
enclosure; 
Estimated amounts: $3,200. 

Potential cost increases: DPW subcontract; 
Estimated amounts: $3,000. 

Potential cost increases: Subtotal; 
Estimated amounts: $23,800. 

Potential cost increases: MEP design changes; 
Estimated amounts: Unknown. 

Potential cost increases: Resolution of change orders; 
Estimated amounts: Unknown. 

[A[ This line item refers to costs associated with expediting work, 
completing the exterior enclosure, and resolving MEP coordination 
issues. 

Source: WCCA records. 

[End of table] 

WCCA is working with the CM and WMATA to minimize the effects of 
factors that could lead to cost increases. 

* According to WCCA officials, negotiations are ongoing with the CM to 
resolve the $38.1 million in submitted and unsubmitted change orders 
generated since the RGMP was put in place. 

* To address projected cost overruns for expansion of the Metro 
station, WCCA and WMATA meet weekly to discuss ways to reduce costs. 

Status of Costs, Allowances/Reserves and Contingency Balances: 

WCCA has established allowances/reserves and a contingency amount as 
means for absorbing various costs that may occur throughout the 
project. 

An allowance, according to WCCA officials, is an amount set aside 
within a purchased subcontract for known work that did not have a 
detailed scope of work when the subcontract was awarded. 

Reserves, according to WCCA officials, are amounts set aside for a 
known scope of work, within the RGMP, that has not yet been contracted. 

The contingency is an estimated amount earmarked for unanticipated cost 
increases. 

Tracking the balances in the allowances/reserves and contingency that 
have been established outside and inside of the RGMP is key to 
monitoring WCCA’s progress in completing construction on time with
minimal cost overruns. 

See summary of allowances/reserves and contingency balances in table 4. 

Table 4: Summary of Unaudited Allowances/Reserves and Contingency 
Balances (Dollars in thousands): 

Description: Allowances/Reserves: Allowances/reserves; 
January 31, 2002 (RGTMP effective date), Inside RGMP: $14,700; 
January 31, 2002 (RGTMP effective date), Outside RGMP: $4,364; 
January 31, 2002 (RGTMP effective date), Total: $19,064; 
June 30, 2002, Inside RGMP: $10,237; 
June 30, 2002, Outside RGMP: $3,067; 
June 30, 2002, Total: $13,304; 
Change: $(5,760). 

Description: Allowances/Reserves: Pending trade change reserves; 
January 31, 2002 (RGTMP effective date), Inside RGMP: $20,250; 
January 31, 2002 (RGTMP effective date), Outside RGMP: [Empty]; 
January 31, 2002 (RGTMP effective date), Total: $20,250; 
June 30, 2002, Inside RGMP: $19,428; 
June 30, 2002, Outside RGMP: [Empty]; 
June 30, 2002, Total: $19,428; 
Change: $(822). 

Description: Allowances/Reserves: Total; 
January 31, 2002 (RGTMP effective date), Inside RGMP: $34,950; 
January 31, 2002 (RGTMP effective date), Outside RGMP: $4,364; 
January 31, 2002 (RGTMP effective date), Total: $39,314; 
June 30, 2002, Inside RGMP: $29,665; 
June 30, 2002, Outside RGMP: $3,067; 
June 30, 2002, Total: $32,732; 
Change: $(6,582). 

Description: Contingencies: Owner's adjustment account; 
January 31, 2002 (RGTMP effective date), Inside RGMP: $9,800; 
January 31, 2002 (RGTMP effective date), Outside RGMP: [Empty]; 
January 31, 2002 (RGTMP effective date), Total: $9,800; 
June 30, 2002, Inside RGMP: $2,600; 
June 30, 2002, Outside RGMP: [Empty]; 
June 30, 2002, Total: $2,600; 
Change: $(7,200). 

Description: Contingencies: Contingency; 
January 31, 2002 (RGTMP effective date), Inside RGMP: [Empty]; 
January 31, 2002 (RGTMP effective date), Outside RGMP: $9,966; 
January 31, 2002 (RGTMP effective date), Total: $9,966; 
June 30, 2002, Inside RGMP: [Empty]; 
June 30, 2002, Outside RGMP: $7,159; 
June 30, 2002, Total: $7,159; 
Change: $(2,807). 

Description: Contingencies: Total; 
January 31, 2002 (RGTMP effective date), Inside RGMP: $9,800; 
January 31, 2002 (RGTMP effective date), Outside RGMP: $9,966; 
January 31, 2002 (RGTMP effective date), Total: $19,766; 
June 30, 2002, Inside RGMP: $2,600; 
June 30, 2002, Outside RGMP: $7,159; 
June 30, 2002, Total: $9,759; 
Change: $(10,007). 

Source: WCCA. 

[End of table] 

Funding: 

Estimated available funding increased from $815.7 million at January 
2002 to $822.5 million at June 2002, according to WCCA. This is 
attributed to a: 

* $1.4 million increase in the estimate of interest earned on the $25 
million congressional contribution being held by WMATA for Metro 
construction; 

* $5 million increase in the contribution to be received from the 
vendor selected to provide food service, and; 

* $.4 million increase in the estimate of federal highway funds. 

WCCA had received $805.4 million (98 percent of the estimated total 
$822.5 million) of available funding as of July 31, 2002. 

According to WCCA officials, the remaining $17.1 million is expected 
from the following financing sources: 

* $9.4 million in federal highway funds. 

* $5 million in vendor reimbursements [Footnote 13] yet to be 
negotiated. Until these vendor reimbursements are negotiated and 
received, WCCA is at risk for these costs. 

* $2.7 million from interest earned on the $25 million congressional 
contribution being held by WMATA. 

The estimated funding of $822.5 million exceeds total estimated project 
costs of $799.5 million, as of June 30, 2002, by $23 million. However, 
WCCA has stated that the total estimated cost will increase. 

The estimated residual funding combined with the owner’s adjustment 
account and the contingency could be used to cover future increases in 
total project costs not now covered by existing allowances/reserves in 
the cost estimates. (See table 5.) 

WCCA officials told us that they believe the available funding will be 
sufficient to cover the total estimated construction costs, including 
the estimated cost increases associated with factors discussed in this
briefing, through the end of the project. 

Table 5: Analysis of Remaining Funding Available and Quantified 
Potential Cost Increases (Dollars in thousands): 

Description: Estimated project residual funding[A]; 
Estimated amounts: $23,000. 

Description: Contingency; 
Estimated amounts: $7,159. 

Description: Owner's adjustment account; 
Estimated amounts: $2,600. 

Description: Subtotal; 
Estimated amounts: $32,759. 

Description: Less: Quantified potential cost increases[B[; 
Estimated amounts: $23,800. 

Description: Potential excess of available funding over quantified
potential cost increases as of June 2002; 
Estimated amounts: $8,959. 

Note: All of the figures above are subject to uncertainty. 

[A] This figure was calculated using the estimated cost figure of 
$799.5 million, which WCCA has stated will increase. 

[B] Quantified potential cost increases are estimates that are subject 
to change. In addition, potential increases for MEP design changes and 
resolution of change orders have not been quantified. 

[End of table] 

Scope and Methodology: 

In order to determine what was updated as a result of the RGMP 
agreement, we reviewed the RGMP to determine the final settlement of 
pending change orders submitted by the CM, the new RGMP estimate, and 
new construction deadline dates. We also held discussions with WCCA 
officials to discuss issues related to the RGMP. 

In order to determine the status of construction and identify related 
issues, we: 

* held discussions with WCCA officials and the DC City Council’s 
oversight contractor regarding the status of the project as of June 
2002 and observed weekly construction status meetings between the
CM and WCCA, and; 

* reviewed the CM’s and WCCA’s monthly progress reports and visited the 
construction site. 

In order to evaluate estimated cost information, we: 

* reviewed estimated project costs included in WCCA’s monthly status 
reports through June 2002 to identify any cost increases since January 
31, 2002, and held discussions with WCCA officials to discuss factors 
that could affect costs; and; 

* held discussions with the DC City Council’s oversight contractor to 
monitor progress and identify major issues associated with the RGMP and 
the total estimated project cost. 

In order to determine if estimated funding appears sufficient, we 
reviewed WCCA’s financing plan to analyze whether the current estimated 
funding covers the remaining estimated project cost and any identified
project cost increases. 

We conducted our work from April through August 2002 in accordance with 
generally accepted government auditing standards and considered the 
results of our most recent work, which were reported to you in January 
2002. [Footnote 14] 

Agency Comments: 

WCCA agreed that the draft letter and briefing slides accurately 
reflect the status of the convention center project. WCCA provided some 
technical comments and clarification which we have incorporated as 
appropriate throughout the briefing slides. 

[End of enclosure] 

Footnotes: 

[1] The RGMP is intended to represent the final construction price 
negotiated for hard costs between the construction manager and WCCA. 

[2] WCCA established the $799.5 million total project cost estimate in 
January 2002. 

[3] U.S. General Accounting Office, District of Columbia: Status of the 
New Convention Center Project, GAO-02-335T (Washington, D.C.: Jan. 18, 
2002). 

[4] Substantial completion means that the area is completed enough to 
obtain a certificate of occupancy that can be issued on a partial or 
temporary basis. Building support systems and life safety systems must 
be working. 

[5] According to the RGMP, convention-ready areas include the south 
building, central plant area, portions of the north and middle 
buildings necessary to occupy the lower exhibit hall, and the west
concourse necessary to serve the lower exhibit hall. 

[6] Final completion means the completion of all three buildings and 
minor items identified by WCCA during the final walk-through. 

[7] Soft costs are construction costs that are not related to the 
physical structure of the facility, such as design fees, legal costs, 
and consulting and inspections. 

[8] Substantial completion means that the area is completed enough to 
obtain a certificate of occupancy that can be issued on a partial or 
temporary basis. Building support systems and life safety systems must 
be working. 

[9] According to the RGMP, convention-ready areas include the south 
building, central plant area, portions of the north and middle 
buildings necessary to occupy the lower exhibit hall, and the west 
concourse necessary to serve the lower exhibit hall. 

[10] Final completion means the completion of all three buildings and 
minor items identified by WCCA during the final walk-through. 

[11] This work involves replacing all the curbs, sidewalks, and 
roadways around the new convention center, as well as installing new 
lighting and planting trees. 

[12] These costs are the result of design changes necessary to resolve 
conflicts between MEP design drawings and the structural and 
architectural design drawings. 

[13] WCCA anticipates reimbursements for equipment costs related to 
telecommunications and audiovisual. 

[14] U.S. General Accounting Office, District of Columbia: Status of 
the New Convention Center Project, GAO-02-335T (Washington, D.C.: Jan. 
18, 2002). 

[End of section] 

GAO's Mission: 

The General Accounting Office, the investigative arm of Congress, 
exists to support Congress in meeting its constitutional 
responsibilities and to help improve the performance and accountability 
of the federal government for the American people. GAO examines the use 
of public funds; evaluates federal programs and policies; and provides 
analyses, recommendations, and other assistance to help Congress make 
informed oversight, policy, and funding decisions. GAO’s commitment to 
good government is reflected in its core values of accountability, 
integrity, and reliability. 

Obtaining Copies of GAO Reports and Testimony: 

The fastest and easiest way to obtain copies of GAO documents at no 
cost is through the Internet. GAO’s Web site [hyperlink, 
http://www.gao.gov] contains abstracts and fulltext files of current 
reports and testimony and an expanding archive of older products. The 
Web site features a search engine to help you locate documents using 
key words and phrases. You can print these documents in their entirety, 
including charts and other graphics. 

Each day, GAO issues a list of newly released reports, testimony, and 
correspondence. GAO posts this list, known as “Today’s Reports,” on its 
Web site daily. The list contains links to the full-text document 
files. To have GAO e-mail this list to you every afternoon, go to 
[hyperlink, http://www.gao.gov] and select “Subscribe to daily E-mail 
alert for newly released products” under the GAO Reports heading. 

Order by Mail or Phone: 

The first copy of each printed report is free. Additional copies are $2 
each. A check or money order should be made out to the Superintendent 
of Documents. GAO also accepts VISA and Mastercard. Orders for 100 or 
more copies mailed to a single address are discounted 25 percent. 
Orders should be sent to: 

U.S. General Accounting Office: 
441 G Street NW, Room LM: 
Washington, D.C. 20548: 

To order by Phone: Voice: (202) 512-6000: 
TDD: (202) 512-2537: 
Fax: (202) 512-6061: 

To Report Fraud, Waste, and Abuse in Federal Programs: 

Contact: 

Web site: [hyperlink, http://www.gao.gov/fraudnet/fraudnet.htm]: 
E-mail: fraudnet@gao.gov: 
Automated answering system: (800) 424-5454 or (202) 512-7470: 

Public Affairs: 

Jeff Nelligan, managing director, NelliganJ@gao.gov, (202) 512-4800: 
U.S. General Accounting Office: 
441 G Street NW, Room 7149: 
Washington, D.C. 20548: