This is the accessible text file for GAO report number GAO-12-206T 
entitled 'Federal Courthouse Construction: Nationwide Space and Cost 
Issues Are Applicable to L.A. Courthouse Project' which was released 
on November 4, 2011. 

This text file was formatted by the U.S. Government Accountability 
Office (GAO) to be accessible to users with visual impairments, as 
part of a longer term project to improve GAO products' accessibility. 
Every attempt has been made to maintain the structural and data 
integrity of the original printed product. Accessibility features, 
such as text descriptions of tables, consecutively numbered footnotes 
placed at the end of the file, and the text of agency comment letters, 
are provided but may not exactly duplicate the presentation or format 
of the printed version. The portable document format (PDF) file is an 
exact electronic replica of the printed version. We welcome your 
feedback. Please E-mail your comments regarding the contents or 
accessibility features of this document to Webmaster@gao.gov. 

This is a work of the U.S. government and is not subject to copyright 
protection in the United States. It may be reproduced and distributed 
in its entirety without further permission from GAO. Because this work 
may contain copyrighted images or other material, permission from the 
copyright holder may be necessary if you wish to reproduce this 
material separately. 

United States Government Accountability Office: 
GAO: 

Testimony: 

Before the Subcommittee on Economic Development, Public Buildings, and 
Emergency Management, Committee on Transportation and Infrastructure, 
House of Representatives: 

For Release on Delivery: 
Expected at 10:00 a.m. EDT:
Friday, November 4, 2011: 

Federal Courthouse Construction: 

Nationwide Space and Cost Issues Are Applicable to L.A. Courthouse 
Project: 

Statement of Mark L. Goldstein, Director:
Physical Infrastructure Issues: 

GAO-12-206T: 

GAO Highlights: 

Highlights of GAO-12-206T, a testimony to the Subcommittee on Economic 
Development, Public Buildings, and Emergency Management, Committee on 
Transportation and Infrastructure, House of Representatives. 

Why GAO Did This Study: 

In 2000, as part of a multibillion-dollar courthouse construction 
initiative, the judiciary requested and the General Services 
Administration (GSA) proposed building a new courthouse in Los Angeles 
to increase security, efficiency, and space-—but construction never 
began. About $400 million was appropriated for the L.A. courthouse 
project. For this testimony, GAO was asked to report on (1) the status 
of the L.A. courthouse project, (2) challenges GAO has identified 
affecting federal courthouses nationwide, and (3) the extent to which 
these challenges are applicable to the L.A. courthouse project. 

This testimony is based on GAO-10-417 and GAO’s other prior work on 
federal courthouses, during which GAO analyzed courthouse planning and 
use data, visited courthouses, modeled courtroom sharing scenarios, 
and interviewed judges, GSA officials, and others. 

In GAO-10-417, GAO recommended that (1) GSA ensure that new 
courthouses are constructed within their authorized size or, if not, 
that congressional committees are notified, (2) the Judicial 
Conference of the United States retain caseload projections to improve 
the accuracy of its 10-year-judge planning, and (3) the Conference 
establish and use courtroom sharing policies based on scheduling and 
use data. GSA and the judiciary agreed with most of the 
recommendations, but expressed concerns with GAO’s methodology and key 
findings. GAO continues to believe that its findings were well 
supported and developed using an appropriate methodology. 

What GAO Found: 

GAO reported in 2008 that GSA spent about $33 million on design and 
site preparations for a new 41-courtroom L.A. courthouse, leaving 
about $366 million available for construction. However, project 
delays, unforeseen cost escalation, and low contractor interest had 
caused GSA to cancel the project in 2006 before any construction took 
place. GSA later identified other options for housing the L.A. Court, 
including constructing a smaller new courthouse (36 courtrooms) or 
using the existing courthouses—the Spring Street Courthouse and the 
Edward R. Roybal Federal Building and Courthouse. As GAO also 
reported, the estimated cost of the 36-courthouse option as of 2008 
was over $1.1 billion, significantly higher than the current 
appropriation. 

The challenges that GAO has identified in recent reports on federal 
courthouses include increasing rent and extra operating, maintenance, 
and construction costs stemming from courthouses being built larger 
than necessary. For example, in 2004, the judiciary requested a $483 
million permanent, annual exemption from rent payments to GSA due to 
difficulties in paying for its increasing rent costs. GAO found in 
2006 that these increasing rent costs were primarily due to increases 
in total courthouse space—and in 2010, GAO reported that more than a 
quarter of the new space in recently constructed courthouses is 
unneeded. Specifically, in the 33 federal courthouses completed since 
2000, GAO found 3.56 million square feet of excess space. This extra 
space is a result of (1) courthouses exceeding the congressionally 
authorized size, (2) the number of judges in the courthouses being 
overestimated, and (3) not planning for judges to share courtrooms. In 
total, the extra space GAO identified is equal in square footage to 
about 9 average-sized courthouses. The estimated cost to construct 
this extra space, when adjusted to 2010 dollars, is $835 million, and 
the estimated annual cost to rent, operate and maintain it is $51 
million. 

Each of the challenges GAO identified related to unnecessary space in 
courthouses completed since 2000 is applicable to the L.A. courthouse 
project. First, as GAO reported in 2008, GSA designed the L.A. 
Courthouse with 13 more courtrooms than congressionally authorized. 
This increase in size led to cost increases and delays. Second, in 
2004, GAO found that the proposed courthouse was designed to provide 
courtrooms to accommodate the judiciary’s estimate of 61 district and 
magistrate judges in the L.A. Court by 2011—which, as of October 2011, 
exceeds the actual number of such judges by 14. This disparity calls 
into question the space assumptions on which the original proposals 
were based. Third, the L.A. court was planning for less courtroom 
sharing than is possible. While in 2008 the judiciary favored an 
option proposed by GSA that provided for some sharing by senior 
judges, according to GAO’s 2010 analysis, there is enough unscheduled 
time in courtrooms for three senior judges to share one courtroom, two 
magistrate judges to share one courtroom, and three district judges to 
share two courtrooms. In 2011, the judiciary also approved sharing for 
bankruptcy judges. Additional courtroom sharing could reduce the 
number of additional courtrooms needed for the L.A. courthouse, 
thereby increasing the potential options for housing the L.A. Court. 

View [hyperlink, http://www.gao.gov/products/GAO-12-206T]. For more 
information, contact Mark L. Goldstein at (202) 512-2834 or 
goldsteinm@gao.gov. 

[End of section] 

Chairman Denham, Ranking Member Norton, and Members of the 
Subcommittee: 

We are pleased to be here to discuss our recent work on federal 
courthouse construction issues and on the Los Angeles (L.A.) 
courthouse in particular. Since the early 1990s, the General Services 
Administration (GSA) and the federal judiciary (judiciary) have 
undertaken a multibillion-dollar courthouse construction initiative 
that by June 2010 had resulted in 66 new courthouses or annexes, with 
29 additional projects in various stages of development. However, 
rising costs and other federal budget priorities threaten to stall the 
initiative. The L.A. courthouse is one of the projects that has not 
been constructed, even though in fiscal year 2000, the judiciary 
ranked Los Angeles, California, as its first priority for courthouse 
construction.[Footnote 1] Currently, in downtown Los Angeles at one of 
the nation's busiest federal district courts (L.A. Court), the 
judiciary's operations are split between two buildings--the Spring 
Street Courthouse and the Edward R. Roybal Federal Building and 
Courthouse. In 1996, the judiciary concluded that the split created 
operational inefficiencies, that it needed additional space in 
downtown Los Angeles, and that the Spring Street building had obsolete 
building systems and poor security conditions. The split court was a 
significant factor in the high priority ranking given to the L.A. 
courthouse project. For example, according to GSA officials, 
inefficiencies occur because the court's operations are split between 
these two buildings. GSA agreed in 2000 that the existing buildings 
did not meet the court's expansion and security requirements, among 
other things. Accordingly, the judiciary requested and GSA proposed 
building a new courthouse in downtown Los Angeles. 

In July 2000, GSA was congressionally authorized to begin designing a 
new courthouse in Los Angeles, and from fiscal year 2001 through 
fiscal year 2005, Congress appropriated about $400 million for the 
project.[Footnote 2] GSA initially estimated in 2000 that the L.A. 
Court could take occupancy of a new courthouse in fiscal year 2006, 
but construction never began. For this testimony, GAO was asked to 
address (1) the history and status of the L.A. courthouse project, (2) 
challenges we have identified affecting federal courthouses 
nationwide, and (3) the extent to which these challenges are 
applicable to the L.A. courthouse project. This testimony is based on 
GAO's prior work on federal courthouses,[Footnote 3] for which we 
analyzed courthouse planning and use data; reviewed relevant laws, 
regulations, and project planning and budget documents; visited key 
sites in Los Angeles and courthouses in many locations; analyzed 
selected courthouses as case studies; modeled courtroom sharing 
scenarios; contracted with the National Academy of Sciences to convene 
a panel of judicial experts, and conducted structured interviews with 
numerous other district and magistrate judges about the challenges and 
opportunities related to courtroom sharing; analyzed nationwide 
judiciary rent data generated from GSA's billing system, and 
interviewed judges, GSA officials, and others. This prior work was 
conducted from June 2004 through June 2010 in accordance with 
generally accepted government auditing standards. Those standards 
require that we plan and perform the audit to obtain sufficient, 
appropriate evidence to provide a reasonable basis for our findings 
and conclusions based on our audit objectives. We believe that the 
evidence obtained provides a reasonable basis for our findings and 
conclusions based on our audit objectives. More detail on our scope 
and methodology is available in the full reports on which this 
testimony is based. 

Background: 

The judiciary pays rent annually to GSA for court-related space. In 
fiscal year 2010, the judiciary's rent payments totaled over $1 
billion. The judiciary's rent payments are deposited into GSA's 
Federal Buildings Fund, a revolving fund used to finance GSA's real 
property services, including the construction and repair of federal 
facilities under GSA control. Since fiscal year 1996, the judiciary 
has used a 5-year plan to prioritize new courthouse construction 
projects, taking into account a court's projected need for space 
related to caseload and estimated growth in the number of judges and 
staff, security concerns, and any operational inefficiencies that may 
exist. Under current practices, GSA and the judiciary plan new federal 
courthouses based on the judiciary's projected 10-year space 
requirements, which incorporate the judiciary's projections of how 
many judges it will need in 10 years. 

The L.A. Court's operations are currently split between two buildings--
the Spring Street Courthouse built in 1938 and the Roybal Federal 
Building built in 1992. In 2008, we reported that the Spring Street 
building consists of 32 courtrooms--11 of which do not meet the 
judiciary's minimum design standards for size[Footnote 4]--and did not 
meet the security needs of the judiciary. The Roybal Federal Building 
consists of 34 courtrooms (10 district, 6 magistrate, and 18 
bankruptcy). (See figure 1.) 

Figure 1: U.S. District Courthouses in Los Angeles: 

[Refer to PDF for image: 2 photographs] 

Spring St. Courthouse, opened in 1938 (765,000 square feet). Court 
family tenants as of December 2004: U.S. District Court, U.S. 
Attorneys, U.S. Marshals Service, U.S. Circuit Court. 

Roybal Federal Building, opened in 1992 (1.2 million square feet). 
Court family tenants as of December 2004: U.S. Bankruptcy Court, U.S. 
District Court, U.S. Circuit Court of Appeals Satellite Library, U.S. 
Marshals Service. 

Source: GAO. 

[End of figure] 

Since 2000, the construction of a new L.A. courthouse has been a top 
priority for the judiciary because of problems perceived by the 
judiciary related to the current buildings' space, security, and 
operations. From fiscal year 2001 through fiscal year 2005, Congress 
made three appropriations for a new L.A. courthouse. Specifically, in 
fiscal year 2001, Congress provided $35.25 million to acquire a site 
for and design a 41-courtroom building, and in fiscal year 2004, 
Congress appropriated $50 million for construction of the new L.A. 
courthouse. In fiscal year 2005, Congress appropriated an additional 
$314.4 million for the construction of a new 41-courtroom building in 
Los Angeles, which Congress designated to remain available until 
expended for construction of the previously authorized L.A. courthouse. 

L.A. Courthouse Project Canceled After Delays and Increases in 
Estimated Costs: 

In our 2008 report, we found that GSA had spent $16.3 million 
designing a new courthouse for the L.A. court and $16.9 million 
acquiring and preparing a new site for it in downtown Los Angeles. In 
addition, we reported that about $366.45 million remained appropriated 
for the construction of a 41-courtroom L.A. courthouse. Subsequent to 
the initial design and site acquisition, we noted that the project 
experienced substantial delays. The project was delayed because GSA 
decided to design a larger courthouse than congressionally authorized, 
GSA and the judiciary disagreed over the project's scope, costs 
escalated unexpectedly, and there was low contractor interest in 
bidding on the project. We also reported that because of the delays, 
estimated costs for housing the L.A. Court had nearly tripled to over 
$1.1 billion, rendering the congressionally-authorized 41-courtroom 
courthouse unachievable with current appropriations. As a result of 
the delays and the increases in estimated cost, in 2006, GSA canceled 
the entire 41-courtroom courthouse project for which Congress had 
appropriated funds. 

By 2008, GSA was considering three options for a revised L.A. 
courthouse project, which would have required balancing needs for 
courtroom space, congressional approval, and additional estimated 
appropriations of up to $733 million. These options are summarized in 
Table 1. 

Table 1: Three Options for Housing the L.A. Court Currently under 
Consideration by GSA: 

Description: Option 1: Construct a new 36-courtroom, 45-chamber 
building to house district judges; add 4 more courtrooms to Roybal to 
house the magistrate and bankruptcy judges; 
and the L.A. Court vacates the Spring Street building; 
Total courtrooms: 74; 
Estimated completion date: 2014; 
Estimated new appropriations needed: $733.6 million. 

Description: Option 2: Construct a new 20-courtroom, 20-chamber 
courthouse to house about half of the district judges; add 12 more 
courtrooms to the Roybal building; 
and the L.A. Court vacates the Spring Street building; 
Total courtrooms: 66; 
Estimated completion date: 2014; 
Estimated new appropriations needed: $301.5 million. 

Description: Option 3: Add 13 more courtrooms in the Roybal building, 
retain 17 courtrooms and upgrade security in the Spring Street 
building, and house the remaining court functions in the federal 
building on L.A. Street (located in between the Spring Street and the 
Roybal buildings); 
Total courtrooms: 64; 
(some below design standards for size); 
Estimated completion date: 2016; 
Estimated new appropriations needed: $282.1 million. 

Source: GAO analysis of GSA data. 

[End of table] 

The L.A. Court supported the first of these options--building a 36- 
courtroom, 45-chamber courthouse to house all district and senior 
judges and adding 4 more courtrooms in the Roybal building to house 
all magistrate and bankruptcy judges--but it was the most expensive, 
pushing the total project costs to $1.1 billion at that time. While in 
2008, we took no position on the three options, it was clear that the 
process had become deadlocked. Moreover, none of the options 
considered in 2008 would have solved the issue of a split court, as 
all involved using two buildings to house the L.A. Court. 

GAO Found Judiciary's Rent Challenge Stems from Courthouses Having 
Unneeded Space with Higher Associated Costs: 

GAO Found That Increases in the Judiciary's Rent Costs Were Primarily 
Due to Increases in Space and That Courthouses Have Significant 
Unneeded Space: 

In 2004, the judiciary requested a $483 million permanent, annual 
exemption from rent payments to GSA because it was having difficulty 
paying for its increasing rent costs. GSA denied this request. GAO 
found in 2006[Footnote 5] that the federal judiciary's rental 
obligations to GSA for courthouses had increased 27 percent from 
fiscal year 2000 through fiscal year 2005, after controlling for 
inflation, and that these increasing rent costs were primarily due to 
the judiciary's simultaneous 19-percent increase in space.[Footnote 6] 
Much of the net increase in space was in new courthouses that the 
judiciary had taken occupancy of since 2000. In 2010, we found that 
the 33 federal courthouses completed since 2000 include 3.56 million 
square feet of unneeded space--more than a quarter of the space in 
courthouses completed since 2000. This extra space consists of space 
that was constructed as a result of (1) exceeding the congressionally 
authorized size, (2) overestimating the number of judges the 
courthouses would have, and (3) not planning for judges to share 
courtrooms. Overall, this space is equal to the square footage of 
about 9 average-sized courthouses. The estimated cost to construct 
this extra space, when adjusted to 2010 dollars, is $835 million, and 
the annual cost to rent, operate, and maintain it is $51 million. 

Most Federal Courthouses Constructed Since 2000 Exceed Authorized 
Size, Some by Substantial Amounts: 

In our 2010 report on federal courthouse construction, we found that 
27 of the 33 courthouses completed since 2000 exceeded their 
congressionally authorized size by a total of 1.7 million square feet. 
Fifteen exceed their congressionally authorized size by more than 10 
percent, and 12 of these 15 also incurred total project costs that 
exceeded the estimates provided to congressional committees. However, 
there is no statutory requirement to notify congressional committees 
about size overages. According to our analysis, a lack of oversight by 
GSA, including not ensuring its space measurement policies were 
understood and followed, and a lack of focus on building courthouses 
within the congressionally authorized size, contributed to these size 
overages. 

For example, all 7 of the courthouses we examined in case studies for 
this 2010 report included more building common and other space--such 
as mechanical spaces and atriums--than planned for within the 
congressionally authorized gross square footage. The increase over the 
planned space ranged from 19 percent to 102 percent. Regional GSA 
officials involved in the planning and construction of several 
courthouses we visited stated that they were unaware until we told 
them that the courthouses were larger than authorized. 

Further indicating a lack of oversight in this area, GSA relied on the 
architect to validate that the courthouse's design was within the 
authorized gross square footage without ensuring that the architect 
followed GSA's policies on how to measure certain commonly included 
spaces, such as atriums. Although GSA officials emphasized that open 
space for atriums would not cost as much as space completely built out 
with floors, these officials also agreed that there are costs 
associated with constructing and operating atrium space. In fact, the 
2007 edition of the U.S. Courts Design Guide,[Footnote 7] which 
reflects an effort to impose tighter constraints on future space and 
facilities costs, emphasizes that courthouses should have no more than 
one atrium. 

Because the Judiciary Overestimated the Number of Judges, Courthouses 
Have Much Extra Space after 10 Years: 

For 23 of 28 courthouses whose space was planned at least 10 years 
ago, the judiciary overestimated the number of judges who would be 
located in them, causing them to be larger and costlier than 
necessary. Overall, the judiciary has 119, or approximately 26 
percent, fewer judges than the 461 it estimated it would have. This 
leaves the 23 courthouses with extra courtrooms and chamber suites 
that, together, total approximately 887,000 square feet of extra 
space. A variety of factors contributed to the judiciary's 
overestimates, including inaccurate caseload projections, difficulties 
in projecting when judges would take senior status, and long-standing 
difficulties in obtaining new authorizations and filling vacancies. 
However, we found that the contribution of inaccurate caseload 
projections to inaccurate estimates of how many judges would be needed 
cannot be measured because the judiciary did not retain the historic 
caseload projections used in planning the courthouses. 

Low Levels of Use Show That Judges Could Share Courtrooms, Reducing 
the Need for Future Courtrooms by More than One-Third: 

According to our analysis of the judiciary's data,[Footnote 8] 
courtrooms are used for case-related proceedings only a quarter of the 
available time or less, on average. Furthermore, no event (case 
related or otherwise) was scheduled in courtrooms for half the time or 
more, on average. Using the judiciary's data, we designed a model for 
courtroom sharing, which shows that there is enough unscheduled time 
for substantial courtroom sharing. (For more information on our model, 
see appendix I). Specifically, our model shows that under dedicated 
sharing, in which judges are assigned to share specific courtrooms, 
three district judges could share two courtrooms, three senior judges 
could share one courtroom, and two magistrate judges could share one 
courtroom with time to spare. This level of sharing would reduce the 
number of courtrooms the judiciary requires by a third for district 
judges and by more for senior district and magistrate judges. 

In our 2010 report, we found that dedicated sharing could have reduced 
the number of courtrooms needed in courthouses built since 2000 by 126 
courtrooms--about 40 percent of the total number--accounting for about 
946,000 square feet of extra space. Furthermore, we found that another 
type of courtroom sharing--centralized sharing, in which all 
courtrooms are available for assignment to any judge based on need--
improves efficiency and could reduce the number of courtrooms needed 
even further. 

Some judges we consulted raised potential challenges to courtroom 
sharing, such as uncertainty about courtroom availability, but others 
with experience in sharing indicated they had overcome those 
challenges when necessary and no trials were postponed. In 2008 and 
2009, the Judicial Conference adopted sharing policies for future 
courthouses under which senior district and magistrate judges are to 
share courtrooms at a rate of two judges per courtroom plus one 
additional duty courtroom for courthouses with more than two 
magistrate judges. Additionally, the conference recognized the greater 
efficiencies available in courthouses with many courtrooms and 
recommended that in courthouses with more than 10 district judges, 
district judges also share. 

Our model's application of the judiciary's data shows that still more 
sharing opportunities are available. Specifically, sharing between 
district judges could be increased by one-third by having three 
district judges share two courtrooms in courthouses of all sizes. 
Sharing could also be increased by having three senior judges--instead 
of two--share one courtroom. We found that, if implemented, these 
opportunities could further reduce the need for courtrooms, thereby 
decreasing the size of future courthouses. 

GSA and the Judiciary Have an Opportunity to Align Courthouse Planning 
and Construction with the Judiciary's Real Need for Space: 

In 2010, we concluded that, for at least some of the 29 courthouse 
projects underway at that time and for all future courthouse 
construction projects not yet begun, GSA and the judiciary have an 
opportunity to align their courthouse planning and construction with 
the judiciary's real need for space. Such changes would reduce 
construction, operations and maintenance, and rent costs. We 
recommended, among other things, that GSA ensure that new courthouses 
are constructed within their authorized size or that congressional 
committees are notified if authorized sizes are going to be exceeded; 
that the Judicial Conference of the United States retain caseload 
projections to improve the accuracy of its 10-year-judge planning; and 
that the Conference establish and use courtroom sharing policies based 
on scheduling and use data. GSA and the judiciary agreed with most of 
the recommendations, but expressed concerns about our methodology and 
key findings. We continue to believe that our findings were well 
supported and developed using an appropriate methodology, as explained 
in the report.[Footnote 9] 

Challenges Related to Costs and Unneeded Space in Courthouses Are All 
Applicable to the L.A. Courthouse Project: 

The three causes of extra space--and the associated extra costs--in 
courthouses that we identified in 2010 are all applicable to the L.A. 
courthouse project. These causes, as described above, include (1) 
exceeding the congressionally authorized size, (2) overestimating the 
number of judges the courthouses would have, and (3) not planning for 
courtroom sharing among judges. 

In 2008, we reported that GSA's decision to design a larger courthouse 
in Los Angeles than was congressionally authorized had led to cost 
increases and delays. The design of a new courthouse in Los Angeles 
was congressionally authorized in 2000 and later funded based on a 41- 
courtroom, 1,016,300-square-foot GSA prospectus. GSA decided instead 
to design a 54-courtroom, 1,279,650-square-foot building to meet the 
judiciary's long-term needs. A year and a half later, after conducting 
the environmental assessments and purchasing the site for the new 
courthouse, GSA informed Congress that it had designed a 54-courtroom 
courthouse in a May 2003 proposal. However, the Office of Management 
and Budget (OMB) rejected this proposal, according to GSA, and did not 
include it in the President's budget for fiscal year 2005. GSA then 
designed a 41-courtroom building, but by the time it completed this 
effort, the schedule for constructing the building had been delayed by 
2 years, according to a senior GSA official involved with the project. 

With this delay, inflation pushed the project's cost over budget, and 
GSA needed to make further reductions to the courthouse in order to 
procure it within the authorized and appropriated amounts. However, 
GSA and L.A. Court officials were slow to reduce the project's scope, 
which caused additional delays and then necessitated additional 
reductions. For example, GSA did not simplify the building-high atrium 
that was initially envisioned for the new courthouse until January 
2006, even though the judiciary had repeatedly expressed concerns 
about the construction and maintenance costs of the atrium since 2002. 
In our 2010 report, we found that large atriums contributed to size 
overages in several courthouses completed since 2000. Moreover, 
according to GSA officials in 2010, GSA's current policy on how to 
count the square footage of atriums and its target for the percentage 
of space in a building that should be used for tenant space (which 
does not include atriums) should make it difficult, if not impossible, 
for a courthouse project to include large atriums spanning many 
floors--although relatively modest atriums should still be feasible. 

Second, overestimates of how many judges the L.A. Court would need led 
to the design of a courthouse with more courtrooms than necessary. 
Specifically, we reported in 2004 that the proposed L.A. courthouse 
was designed to include courtrooms for 61 judges (47 current district 
and magistrate judges and 14 additional judges expected by 2011), but 
in 2011, the L.A. Court still has 47 district and magistrate judges--
and none of the 14 additional judges that were expected. This outcome 
calls into question the space assumptions that the original proposals 
were based on. 

Third, in 2008 we reported that in planning for judges to share 
courtrooms, the judiciary favored an option proposed by GSA that 
provided for sharing by senior judges, but our 2010 analysis indicated 
that further sharing was feasible and could reduce the size and cost 
of the L.A. courthouse project. Specifically, GSA's proposal to build 
a 36-courtroom, 45-chamber building and add 4 courtrooms to Roybal's 
existing 34 courtrooms--which GSA estimated at the time would cost 
$1.1 billion, or $733.6 million more than Congress had already 
appropriated--would have provided the L.A. Court with 74 courtrooms in 
total--36 district courtrooms in the new building and 38 courtrooms 
(20 magistrate and 18 bankruptcy) in Roybal. The judiciary supported 
this proposal in part, it said, because, with more chambers than 
courtrooms included in the plan, it could fulfill its need for a 
larger building through courtroom sharing among senior judges who 
would occupy the extra chambers in the new building. In this option, 
the district and senior judges would be housed in the new courthouse, 
while the magistrate and bankruptcy judges would be housed in the 
Roybal building. As described above, our model suggested that 
additional courtroom sharing would be possible in a courthouse such as 
the L.A. courthouse, which could reduce the number of courtrooms 
needed for this project, broadening the potential options for housing 
the L.A. District Court. 

Chairman Denham, Ranking Member Norton, and Members of the 
Subcommittee, this concludes our testimony. We are pleased to answer 
any questions you might have. 

Contact Information: 

For further information on this testimony, please contact Mark L. 
Goldstein, (202) 512-2834 or by e-mail at goldsteinm@gao.gov. Contact 
points for our Offices of Congressional Relations and Public Affairs 
may be found on the last page of this statement. Individuals making 
key contributions to this testimony include Keith Cunningham, 
Assistant Director, Susan Michal-Smith, and Alwynne Wilbur. 

[End of section] 

Appendix I: Additional Information on GAO's Courtroom Sharing Model: 

To learn more about the level of courtroom sharing that the 
judiciary's data support, we used the judiciary's 2008 district 
courtroom scheduling and use data to create a simulation model to 
determine the level of courtroom sharing supported by the data. 

The data used to create the simulation model for courtroom usage were 
collected by the Federal Judicial Center (FJC)--the research arm of 
the federal judiciary--for its Report on the Usage of Federal District 
Court Courtrooms, published in 2008. The data collected by FJC were a 
stratified random sample of federal court districts to ensure a 
nationally representative sample of courthouses--that is, FJC sampled 
from small, medium, and large districts, as well as districts with 
low, medium, and high weighted filings. Altogether, there were 23 
randomly selected districts and 3 case study districts, which included 
91 courthouses, 602 courtrooms, and every circuit except that of the 
District of Columbia. The data sample was taken in 3-month increments 
over a 6-month period in 2007 for a total of 63 federal workdays, by 
trained court staff who recorded all courtroom usage, including 
scheduled but unused time. These data were then verified against three 
independently recorded sources of data about courtroom use. 
Specifically, the sample data were compared with JS-10 data routinely 
recorded for courtroom events conducted by district judges, MJSTAR 
data routinely recorded for courtroom events conducted by magistrate 
judges, and data collected by independent observers in a randomly 
selected subset of districts in the sample. We verified that these 
methods were reliable and empirically sound for use in simulation 
modeling. 

Working with a contractor, we designed this sharing model in 
conjunction with a specialist in discrete event simulation and the 
company that designed the simulation software to ensure that the model 
conformed to generally accepted simulation modeling standards and was 
reasonable for the federal court system. Simulation is widely used in 
modeling any system where there is competition for scarce resources. 
The goal of the model was to determine how many courtrooms are 
required for courtroom utilization rates similar to that recorded by 
FJC. This determination is based on data for all courtroom use time 
collected by FJC, including time when the courtroom was scheduled to 
be used but the event was canceled within one week of the scheduled 
date. 

The completed model allows, for each courthouse, user input of the 
number and types of judges and courtrooms, and the output states 
whether the utilization of the courtrooms does not exceed the 
availability of the courtrooms in the long run. When using the model 
to determine the level of sharing possible at each courthouse based on 
scheduled courtroom availability on weekdays from 8 a.m. to 6 p.m., we 
established a baseline of one courtroom per judge to the extent that 
this sharing level exists at the 33 courthouses built since 2000. In 
selecting the 8 a.m. to 6 p.m. time frame for courtroom scheduling, we 
used the courtroom scheduling profile that judges currently use, 
reflecting the many uses and flexibility needed for a courtroom. 
Judges stated that during trials courtrooms may be needed by attorneys 
before trial times in order to set up materials. This set up time was 
captured in the judiciary's data; other uses of a courtroom captured 
by the judiciary are time spent on ceremonies, education, training, 
and maintenance. We differentiated events and time in the model by 
grouping them as case-related events, nonjudge-related events, and 
unused scheduled time, and we allotted enough time for each of these 
events to occur without delay. Then we entered the number of judges 
from each courthouse and determined the fewest number of courtrooms 
needed for no backlog in court proceedings. 

[End of section] 

Footnotes: 

[1] California is divided into four judicial districts and Los Angeles 
is located in the Central District. 

[2] Before Congress makes an appropriation for a proposed project, GSA 
submits to the Senate Committee on Environment and Public Works and 
the House Committee on Transportation and Infrastructure detailed 
project descriptions, called prospectuses, for authorization by these 
committees when the proposed construction, alteration, or acquisition 
of a building to be used as a public building exceeds a specified 
threshold. For purposes of this testimony, we refer to approval of 
these projects or prospectuses by these committees as "congressionally 
authorized." See 40 U.S.C. § 3307. 

[3] See GAO, Federal Courthouse Construction: Better Planning, 
Oversight, and Courtroom Sharing Needed to Address Future Costs, 
[hyperlink, http://www.gao.gov/products/GAO-10-417] (Washington, D.C.: 
June 21, 2010); GAO, Federal Courthouse Construction: Estimated Costs 
to House the L.A. District Court Have Tripled and There Is No 
Consensus on How to Proceed, [hyperlink, 
http://www.gao.gov/products/GAO-08-889] (Washington, D.C.: Sept. 12, 
2008); GAO, Federal Courthouses: Rent Increases Due to New Space and 
Growing Energy and Security Costs Require Better Tracking and 
Management, [hyperlink, http://www.gao.gov/products/GAO-06-613] 
(Washington, D.C.: June 20, 2006); and GAO, L.A. Federal Courthouse 
Project: Current Proposal Addresses Space Needs, but Some Security and 
Operational Concerns Would Remain, [hyperlink, 
http://www.gao.gov/products/GAO-05-158] (Washington, D.C.: Dec. 20, 
2004). 

[4] The judiciary considers three of the courtrooms in the Spring 
Street Building to be hearing rooms and not courtrooms. 

[5] GAO, Federal Courthouses: Rent Increases Due to New Space and 
Growing Energy and Security Costs Require Better Tracking and 
Management, [hyperlink, http://www.gao.gov/products/GAO-06-613] 
(Washington, D.C.: June 20, 2006). 

[6] The judiciary's rent increased from $780 million in fiscal year 
2000 to $990 million in fiscal year 2005, after controlling for 
inflation. During this time, the judiciary's space increased from 33.6 
million to 39.8 million rentable square feet. 

[7] The U.S. Courts Design Guide specifies the judiciary's criteria 
for designing new court facilities and sets the space and design 
standards for court-related elements of courthouse construction. 

[8] Federal Judicial Center, The Use of Courtrooms in U.S. District 
Courts: A Report to the Judicial Conference Committee on Court 
Administration & Case Management, (Washington, D.C.: July 18, 2008). 

[9] [hyperlink, http://www.gao.gov/products/GAO-10-417]. 

[End of section] 

GAO’s Mission: 

The Government Accountability Office, the audit, evaluation, and 
investigative arm of Congress, exists to support Congress in meeting 
its constitutional responsibilities and to help improve the 
performance and accountability of the federal government for the 
American people. GAO examines the use of public funds; evaluates 
federal programs and policies; and provides analyses, recommendations, 
and other assistance to help Congress make informed oversight, policy, 
and funding decisions. GAO’s commitment to good government is 
reflected in its core values of accountability, integrity, and 
reliability. 

Obtaining Copies of GAO Reports and Testimony: 

The fastest and easiest way to obtain copies of GAO documents at no 
cost is through GAO’s website [hyperlink, http://www.gao.gov]. Each 
weekday afternoon, GAO posts on its website newly released reports, 
testimony, and correspondence. To have GAO e mail you a list of newly 
posted products, go to [hyperlink, http://www.gao.gov] and select “E-
mail Updates.” 

Order by Phone: 

The price of each GAO publication reflects GAO’s actual cost of 
production and distribution and depends on the number of pages in the 
publication and whether the publication is printed in color or black 
and white. Pricing and ordering information is posted on GAO’s 
website, [hyperlink, http://www.gao.gov/ordering.htm]. 

Place orders by calling (202) 512-6000, toll free (866) 801-7077, or 
TDD (202) 512-2537. 

Orders may be paid for using American Express, Discover Card, 
MasterCard, Visa, check, or money order. Call for additional 
information. 

Connect with GAO: 

Connect with GAO on facebook, flickr, twitter, and YouTube.
Subscribe to our RSS Feeds or E mail Updates. Listen to our Podcasts.
Visit GAO on the web at www.gao.gov. 

To Report Fraud, Waste, and Abuse in Federal Programs: 

Contact: 
Website: [hyperlink, http://www.gao.gov/fraudnet/fraudnet.htm]; 
E-mail: fraudnet@gao.gov; 
Automated answering system: (800) 424-5454 or (202) 512-7470. 

Congressional Relations: 

Ralph Dawn, Managing Director, dawnr@gao.gov, (202) 512-4400
U.S. Government Accountability Office, 441 G Street NW, Room 7125
Washington, DC 20548. 

Public Affairs: 
Chuck Young, Managing Director, youngc1@gao.gov, (202) 512-4800
U.S. Government Accountability Office, 441 G Street NW, Room 7149 
Washington, DC 20548.