This is the accessible text file for GAO report number GAO-11-891 
entitled 'Contingency Contracting: Improved Planning and Management 
Oversight Needed to Address Challenges with Closing Contracts' which 
was released on September 28, 2011. 

This text file was formatted by the U.S. Government Accountability 
Office (GAO) to be accessible to users with visual impairments, as 
part of a longer term project to improve GAO products' accessibility. 
Every attempt has been made to maintain the structural and data 
integrity of the original printed product. Accessibility features, 
such as text descriptions of tables, consecutively numbered footnotes 
placed at the end of the file, and the text of agency comment letters, 
are provided but may not exactly duplicate the presentation or format 
of the printed version. The portable document format (PDF) file is an 
exact electronic replica of the printed version. We welcome your 
feedback. Please E-mail your comments regarding the contents or 
accessibility features of this document to Webmaster@gao.gov. 

This is a work of the U.S. government and is not subject to copyright 
protection in the United States. It may be reproduced and distributed 
in its entirety without further permission from GAO. Because this work 
may contain copyrighted images or other material, permission from the 
copyright holder may be necessary if you wish to reproduce this 
material separately. 

United States Government Accountability Office:
GAO: 

Report to Congressional Addressees: 

September 2011: 

Contingency Contracting: 

Improved Planning and Management Oversight Needed to Address 
Challenges with Closing Contracts: 

GAO-11-891: 

GAO Highlights: 

Highlights of GAO-11-891, a report to congressional addressees. 

Why GAO Did This Study: 

Since 2002, DOD obligated at least $166.6 billion on contracts 
supporting reconstruction and stabilization efforts in Iraq and 
Afghanistan. Many of these contingency contracts, in particular those 
awarded in Iraq, need to be closed. Contract closeout is a key step to 
ensure the government receives the goods and services it purchased at 
the agreed upon price and, if done timely, provides opportunities to 
use unspent funds for other needs and reduces exposure to other 
financial risks. 

To assess DOD’s efforts to close its Iraq contracts, GAO examined the 
(1) number of contracts that are eligible for closeout and the extent 
to which they will be closed within required time frames, (2) factors 
contributing to contracts not being closed within required time 
frames, (3) steps DOD took to manage the financial risks associated 
with not closing contracts within required time frames, and (4) extent 
to which DOD captured and implemented lessons learned from closing its 
Iraq contracts. GAO reviewed contingency contracting guidance, 
analyzed contract and closeout data for contracts awarded between 
fiscal years 2003 and 2010, and interviewed DOD officials from six 
organizations responsible for awarding or closing out these contracts. 

What GAO Found: 

DOD does not have visibility into the number of its Iraq contracts 
eligible for closeout, but available data indicate that DOD must still 
review and potentially close at least 58,000 contracts awarded between 
fiscal years 2003 and 2010. GAO’s analysis indicates that relatively 
few of its contracts will be closed within required time frames. For 
example, about 90 percent of the limited number of contracts for which 
DOD could provide closeout data are already over age for closeout. The 
U.S. Central Command’s Contracting Command (C3) and its predecessors, 
which awarded many of DOD’s Iraq contracts, did not have sufficient 
internal controls to ensure that contracting data were accurate and 
complete. C3’s management visibility was further affected by 
limitations of its information systems, staff turnover, and poor 
contract administration. 

DOD’s ability to close its contracts has been hindered by the lack of 
advance planning, workforce shortfalls, and contractor accounting 
challenges. For example, DOD’s contingency contracting doctrine and 
guidance do not specifically require advanced planning for contract 
closeouts. DOD took steps in 2008 to address its backlog of contracts 
needing to be closed but such actions came too late to make 
significant difference in closing contracts within required time 
frames. DOD is now transitioning responsibility for closing out C3’s 
contracts to the Army Contracting Command. Staffing challenges, 
however, during this transition have hindered efforts to close these 
contracts. Efforts to close large, cost-type contracts have been 
further hindered by Defense Contract Audit Agency staffing shortages 
and unresolved issues with contractors’ accounting practices, which 
have delayed audits of the contractors’ incurred costs. 

DOD’s efforts to identify unspent contract funds and improper 
payments—-two examples of financial risks that timely closeout of 
contracts may help identify—-are hindered by limited visibility into 
its Iraq contracts. DOD identified at least $135 million in unspent 
funds that could potentially not be available to meet other DOD needs. 
If not used, these funds will be returned to the U.S. Treasury at the 
end of fiscal year 2011. Should DOD identify a need to pay for an 
unanticipated cost on these contracts, it will need to use other funds 
that are currently available. Additionally, instances of improper 
payments and potential fraud were sometimes found years after final 
contract deliveries were made, making it harder for DOD to recover 
funds owed to it and increasing the risk that it may need to pay 
contractors interest fees on late payments. 

DOD has identified and addressed some of the problems related to the 
closeout of Iraq contracts, but the growing backlog of over 42,000 
Afghanistan contracts that need to be closed suggests the underlying 
causes have not been resolved. DOD officials noted that the lessons 
learned in Iraq highlight the need to improve contract data, increase 
the emphasis on contract administration and closeout, and improve 
contingency contracting doctrine and guidance. DOD officials reported 
that actions are underway to correct these deficiencies in future 
contingencies, but fully implementing these initiatives may take 
several years. 

What GAO Recommends: 

GAO is making three recommendations to ensure DOD has sufficient 
resources to close its Iraq and Afghanistan contracts and to better 
plan for and improve visibility of closeout efforts in future 
contingencies. DOD concurred with each of the recommendations. 

View [hyperlink, http://www.gao.gov/products/GAO-11-891] for key 
components. For more information, contact John P. Hutton at (202) 512-
4841 or huttonj@gao.gov. 

[End of section] 

Contents: 

Letter: 

Background: 

DOD's Visibility into the Number of Contracts Eligible for Closeout Is 
Hindered by Inadequate Data: 

Planning, Workforce, and Contractor Accounting Issues Hinder Efforts 
to Close Contracts: 

DOD Has Taken Steps to Mitigate Potential Loss or Misuse of Funds but 
Limited Visibility into Its Contracts Hinders Such Efforts: 

Growing Backlog of Afghanistan Contracts Suggests Problems Related to 
Closing Contracts Will Continue: 

Conclusions: 

Recommendations for Executive Action: 

Agency Comments and Our Evaluation: 

Appendix I: Scope and Methodology: 

Appendix II: Comments from the Department of Defense: 

Appendix III: GAO Contact and Staff Acknowledgments: 

Tables: 

Table 1: Status of C3 Contracts Inventoried and Reviewed by the Task 
Force as of April 2011: 

Table 2: Closeout Status for Selected C3 Contracts as of May 2011: 

Table 3: DOD Iraq Contracts Reported Eligible and Over Age for 
Closeout: 

Table 4: Number of DOD Cost-Type Contracts Related to Iraq Eligible 
for Closeout: 

Table 5: Estimated Iraq Contract Funding that Potentially Could Return 
to Treasury at the End of Fiscal Year 2011: 

Table 6: Examples of Contracts with Overpayments that Were Not 
Recovered: 

Figures: 

Figure 1: Overview of Contract Closeout Process: 

Figure 2: Incurred Cost Audit for One Major Iraq Contractor's 2003 
Costs Was Delayed Until 2008 Due in Part to Repeated Inadequate 
Proposal Submissions: 

Abbreviations: 

ACC-RI: Army Contract Command-Rock Island: 

AFCEE: Air Force Center for Engineering and the Environment: 

C3: U.S. Central Command Contracting Command: 

DCAA: Defense Contract Audit Agency: 

DCMA: Defense Contract Management Agency: 

DFAS: Defense Finance and Accounting Service: 

DOD: Department of Defense: 

FAR: Federal Acquisition Regulation: 

LOGCAP: Logistics Civil Augmentation Program: 

USACE: U.S. Army Corps of Engineers: 

[End of section] 

United States Government Accountability Office: 
Washington, DC 20548: 

[End of section] 

September 27, 2011: 

Congressional Addressees: 

Since 2002, the Department of Defense (DOD) has reported obligations 
of at least $166.6 billion to acquire goods and services needed to 
support its reconstruction and stabilization efforts in Iraq and 
Afghanistan, according to the Commission on Wartime Contracting. Our 
work, as well as that of others, has documented shortcomings in DOD's 
strategic planning for operational contract support, contract 
administration and oversight, and its acquisition workforce in these 
contingency operations. Many of the contracts that were awarded to 
support these efforts have been completed and must be closed as the 
final step in the acquisition process. Contract closeout includes a 
number of administrative actions, including DOD confirming that all 
goods and services were received and issuing final payment to the 
contractor, the contractor acknowledging that the U.S. government does 
not owe it additional payment, and finally, the government 
deobligating any unspent funds. For contracts awarded on a cost-
reimbursable basis, the Defense Contract Audit Agency (DCAA) conducts 
audits to assist the contracting officer in determining that 
contractor costs are allowable, allocable, and reasonable. 

The Federal Acquisition Regulation (FAR) states that firm-fixed price 
contracts should be closed within 6 months after the contract is 
physically completed, which generally occurs when the government 
accepts final delivery of goods and services.[Footnote 1] Cost-type 
contracts should be closed within 36 months and can be more difficult 
to close than firm-fixed price contracts as they require the 
settlement of indirect cost rates.[Footnote 2] Closing contracts 
within these time frames can help to limit the government's exposure 
to certain financial risks by identifying and recovering improper 
payments and avoiding paying interest fees when the government does 
not pay contractors on time. Timely closeout also ensures that DOD 
deobligates and uses unspent funds from completed contracts before the 
funds are canceled and return to the U.S. Department of the Treasury 
(Treasury).[Footnote 3] The timing for when funds are canceled is set 
by statute. 

Many DOD organizations awarded contracts to support military 
operations in Iraq, but the majority in our review were awarded in 
theater by U.S. Central Command's Contracting Command (C3) and its 
predecessor organizations.[Footnote 4] In 2007, the Gansler Commission 
on Army Acquisition and Program Management in Expeditionary Operations 
found that only 5 percent of Iraq contracts were being closed. In 
response to these findings, the Army established a Contract Closeout 
Task Force Office (Task Force) to close C3's Iraq and Afghanistan firm-
fixed price contracts and estimated its mission would be completed in 
January 2011. C3, however, significantly underestimated the total 
number of contracts it needed to close and is now transferring the 
Task Force's mission to Army Contract Command-Rock Island (ACC-RI). 
ACC-RI is also responsible for managing the Army's Logistics Civil 
Augmentation Program (LOGCAP) contracts. C3 has also delegated 
closeout responsibilities of its cost-type contracts to the Defense 
Contract Management Agency (DCMA) Southern Europe. Additionally, U.S. 
Army Corps of Engineers (USACE) and Air Force's Center for Engineering 
and the Environment (AFCEE) also awarded many Iraq contracts but 
generally retained responsibility for closing those contracts. 

To assess DOD's efforts to close its Iraq contracts, under the 
authority of the Comptroller General to conduct evaluations on his own 
initiative to assist Congress with its oversight responsibilities, we 
examined the (1) total number of its contracts with performance in 
Iraq that are eligible for closeout and the extent to which DOD closed 
these contracts within required time frames, (2) factors that 
contributed to contracts not being closed within required time frames, 
(3) steps DOD took to manage the financial risks associated with not 
closing contracts within required time frames, and (4) extent to which 
DOD captured and implemented lessons learned from closing its Iraq 
contracts. 

To determine the number of DOD's Iraq contracts eligible for closeout 
and the extent to which DOD closed these contracts within required 
time frames, we reviewed the FAR and the Defense Federal Acquisition 
Regulation Supplement to determine when a contract is eligible for 
closeout and the time frames and the procedures for closing contracts. 
For the purpose of our review the term contracts refers to all base 
contracts, task orders, and blanket purchase agreement call orders. We 
obtained contract data from four DOD organizations that our prior work 
indicated had been responsible for awarding many of the contracts with 
performance in Iraq: C3, Army's ACC-RI, USACE, and AFCEE. These 
organizations may retain responsibility for administering and closing 
the contracts they awarded, or they may delegate such responsibilities 
to another organization. In those instances, we obtained contract data 
from that organization. From each organization, we requested the 
contract number, period of performance, contract type, contract 
status, total obligations, total unliquidated obligations, and 
physical completion dates for each contract for which they were 
responsible to close. The data we obtained from the Task Force also 
included contracts with performance in Afghanistan, which we 
identified separately in our analysis. In instances in which DOD did 
not have complete data, we used available data to determine the number 
of contracts eligible for closeout. We assessed the reliability of 
these data reported by the contracting organizations through 
interviews with knowledgeable officials and electronic data testing 
for missing data, outliers, and obvious errors within each database. 
While we found that C3's contract data from fiscal years 2003 through 
2008 were generally unreliable for determining the closeout status of 
contracts, they were sufficiently reliable for determining the minimum 
number of contracts awarded during this time period. We did not assess 
the reliability of the financial management systems used by DOD to 
provide financial data for our review. 

To identify the factors that contributed to contracts not being closed 
within required time frames, we reviewed DOD's closeout planning 
documents and interviewed officials at each of the contracting 
organizations, DCAA, and the Defense Finance and Accounting Service 
(DFAS), which is responsible for making payments on many Iraq 
contracts, and U.S. Army Central. We reviewed DOD's policy and 
guidance to determine how contract closeout should be incorporated 
into contingency contracting planning. To understand any challenges 
faced by DOD contracting personnel in closing individual contracts, we 
reviewed contract documents for 25 firm-fixed price contracts 
purposefully selected to obtain a variety of closeout organizations 
and a range of closeout difficulty and interviewed contracting 
personnel on their experiences with closing them. We also reviewed the 
Task Force's and ACC-RI's monthly closeout data to assess the Army's 
progress in closing C3's contracts. In addition, to identify the 
factors that affected the completion of audits of cost-type contracts, 
we purposefully selected eight contractors based on the number of over-
age task orders, the amount obligated on the contract, and the amount 
of unliquidated obligations. We reviewed completed audit reports and 
interviewed DCAA officials at headquarters and eight field offices to 
determine what factors affected their ability to complete planned 
audits associated with those contractors. 

To determine the steps DOD has taken to manage the financial risks 
associated with closing contracts, we reviewed the DOD Financial 
Management Regulation and closeout guidance and interviewed 
contracting and financial management personnel at the Office of the 
Under Secretary of Defense, Comptroller; Office of the Assistant 
Secretary of the Army, Financial Management & Comptroller; Joint 
Chiefs of Staff Force Structure, Resources, and Assessment Directorate 
(J-8); and USACE Resource Management. In addition, we analyzed 
unliquidated obligation data and interviewed contracting and financial 
management personnel at each contracting organization we met with to 
determine how these funds were managed and if any funds would be 
returned to Treasury. We also reviewed contracts with known improper 
payments and interviewed DFAS personnel to assess DOD's ability to 
recover such payments. 

To assess the extent to which DOD captured and implemented lessons 
learned from closing contracts in contingency operations, we 
interviewed contracting officials at each of the organizations we 
visited and reviewed C3 documents on contracting-related problems 
encountered in Iraq. We also interviewed senior contracting officials 
in Iraq and Afghanistan to identify any changes made in response to 
the lessons learned from closing the C3 contracts. We obtained and 
reviewed C3 data on the total number of contracts in Afghanistan that 
are eligible and over age for closeout to assess its progress in 
closing these contracts. We also interviewed Army, Joint Chiefs of 
Staff, and Acquisition, Technology, and Logistics' Office of Defense 
Procurement and Acquisition Policy officials responsible for setting 
policy and issuing guidance to identify changes made to respond to the 
problems encountered in Iraq. See appendix I for additional details on 
our scope and methodology. 

We conducted this performance audit from July 2010 through September 
2011 in accordance with generally accepted government auditing 
standards. Those standards require that we plan and perform the audit 
to obtain sufficient, appropriate evidence to provide a reasonable 
basis for our findings and conclusions based on our audit objectives. 
We believe that the evidence obtained provides a reasonable basis for 
our findings and conclusions based on our audit objectives: 

Background: 

DOD faces a number of long-standing and systemic challenges that have 
hindered its ability to achieve more successful acquisition outcomes, 
such as ensuring that DOD personnel use sound contracting approaches 
and maintaining a workforce with the skills and capabilities needed to 
properly manage the acquisitions and oversee contractors. While the 
issues encountered in Iraq and Afghanistan are emblematic of these 
systemic challenges, their significance and effect are heightened in a 
contingency environment.[Footnote 5] For example, in 2004, we raised 
concerns about DOD's ability to effectively administer and oversee 
contracts in Iraq, in part because of the continued expansion of 
reconstruction efforts, staffing constraints, and the need to operate 
in an unsecure and threatening environment.[Footnote 6] Similarly, we 
reported in July 2007 that DOD had not completed negotiations on 
certain task orders in Iraq until more than 6 months after the work 
began and after most of the costs had been incurred, contributing to 
its decision to pay the contractor nearly all of the $221 million 
questioned by auditors.[Footnote 7] In 2008, we reported that not 
having qualified personnel hindered oversight of contracts to maintain 
military equipment in Kuwait and provide linguistic services in Iraq 
and questioned whether DOD could sustain increased oversight of its 
private security contractors.[Footnote 8] 

The contract closeout process includes verifying that the goods or 
services were provided and that all final administrative steps are 
completed, including an audit of the costs billed to the government 
and adjusting for any over-or underpayments on the final invoice. To 
close a contract, DOD must complete a number of tasks, including 
making final payment to the contractor, receiving a release of claims 
from the contractor, and deobligating excess funds, among other tasks 
(see figure 1). A contract is eligible to be closed once the contract 
is physically complete, which is generally when all option provisions 
have expired and the contractor has completed performance and the 
government has accepted the final delivery of goods or services in the 
form of a receiving report or the government has provided the 
contractor a notice of complete contract termination.[Footnote 9] From 
this point, contracts should be closed within time frames set by the 
FAR--6 months for firm-fixed price contracts and 36 months for cost-
type contracts and time and materials contracts. Additional time is 
allowed for the closeout of these latter contract types as the 
contracting officer and DCAA may need to ensure any incurred costs are 
allowable, allocable, and reasonable. Additional time is also needed 
to set the final indirect overhead rates, which determine, in part the 
contractor's final payment on cost-type contracts.[Footnote 10] When 
the contract completion statement, also known as the DD 1594, is 
signed by the contracting officer, the contract is considered closed 
and contract documents can be stored and retained. 

Figure 1: Overview of Contract Closeout Process: 

[Refer to PDF for image: illustration] 

Contract awarded: 
Period of performance. 

Contract is physically complete and eligible for closeout: 
Receiving report; 
Confirm final receipt of goods/services; 
For cost-type contracts: Audit indirect cost rates and settle 
disallowed costs; 
Confirm all invoices, including final, have been paid; 
Obtain release of claims; 
Deobligate excess funds; 
Contract closed. 

Signed DD 1594. 

Source: GAO analysis of the Federal Acquisition Regulation and DOD 
guidance on contract closeouts. 

[End of figure] 

A contract not closed within the FAR time frames is considered to be 
over age for closeout and increases an organization's exposure to a 
number of financial issues. If contract closeout does not take place 
in a timely manner and funds are not deobligated when currently 
available, the agency loses the use of those funds for new 
obligations. Even if funds are expired when they are deobligated, the 
agency can still use them for up to 5 years after they expire to pay 
for authorized increases to existing obligations made from the same 
appropriation. Any funds remaining after the 5-year period are 
considered canceled and must be returned to Treasury. If closeout does 
not take place until after they are canceled, and the agency 
identifies a need for the government to pay the contractor for an 
unanticipated cost, the government must use other funds that are 
currently available. Additionally, the risk of late payments to 
contractors increases when contracts are not closed within required 
time frames and in turn may result in the government paying interest. 
Further, the longer an organization waits to close a contract the more 
difficult it becomes to identify and recover improper payments to 
contractors. In addition, closing a contract years after the 
performance is complete can be more time consuming because key 
documentation, such as invoices and receiving reports, and contracting 
personnel with first-hand knowledge of the contract may no longer be 
available. 

DOD's Visibility into the Number of Contracts Eligible for Closeout Is 
Hindered by Inadequate Data: 

DOD does not have visibility into the total number of its Iraq 
contracts eligible for closeout, but our analysis of available data 
indicates that relatively few of these contracts will be closed within 
the time frames prescribed by the FAR. C3, which awarded the majority 
of the Iraq contracts, did not have sufficient internal controls to 
ensure its contracting data were accurate and complete, and was 
further affected by limitations of its contracting systems, turnover 
in contracting personnel, and other competing demands. In 2009, to 
help reduce the backlog of contracts to be closed, C3 transferred 
66,760 Iraq contracts and 14,336 contracts in which a place of 
performance was not specified to the Task Force.[Footnote 11] As it 
was unclear how many of these contracts were closed before being 
shipped, Task Force personnel are in the process of reviewing each 
contract and, as appropriate, closing any open contracts. As of April 
2011, however, over 54,000 of these contracts still needed to be 
reviewed. DOD officials noted that record keeping generally improved 
for C3's firm-fixed price contracts awarded after fiscal year 2008. C3 
also improved visibility of its large, cost-type contracts awarded 
between fiscal year 2003 and 2010 after delegating contract 
administration, including closeout responsibilities, to DCMA Southern 
Europe in 2008. Based on available data provided by C3 and the other 
DOD contracting organizations we reviewed, there are at least an 
additional 4,298 Iraq contracts--90 percent of which are already over 
age--that need to be closed. 

C3's Visibility into Its Contracting Activity Improved in Fiscal Year 
2009 but Reliability of Prior Years' Data Is Questionable: 

C3 and its predecessor organizations awarded the majority of DOD's 
contracts to support reconstruction and stabilization efforts, yet 
weak internal controls, turnover in contracting personnel, and 
competing demands contributed to incomplete or inaccurate information 
that hindered management oversight of its contracting activities, 
including whether it was meeting FAR closeout requirements.[Footnote 
12] DOD officials noted C3 did not have a contract writing and 
management information system in Iraq between 2003 and 2008, which 
contributed to the use of multiple manual databases. Each regional 
contracting center awarded manually written contracts and documented 
contract actions on independent spreadsheets. C3 and Army officials 
noted some of the challenges with manually written contracts included 
duplicate or inaccurate contract numbers and inaccurate period of 
performance dates. They also noted that each regional contracting 
center maintained and managed its contract data on spreadsheets 
differently as there was not an Iraq-wide standard for how to maintain 
contract data and that data input was often unverified. These contract 
documentation challenges were exacerbated by the constant turnover of 
contracting personnel and the command's emphasis on awarding contracts 
to support the warfighter. Additionally, C3 and Army officials said 
that an unknown number of contracts were never input into C3's 
database and could not be accounted for because contract files were 
lost, damaged, or destroyed. 

Our analysis of C3's data on its Iraq contracts found at least 55,000 
contracts were recorded as being awarded between fiscal years 2003 and 
2008, but we determined that the data had numerous discrepancies. 
These discrepancies, which included missing or invalid period of 
performance and physical completion dates as well as invalid or 
duplicative contract numbers, affect the data needed to maintain 
visibility on the contracts eligible to be closed. Army officials 
acknowledged that the contract information reflected in C3's database 
through fiscal year 2008 was unreliable for determining the actual 
number of contracts it awarded or which contracts were eligible to be 
closed. Consequently, the Army underestimated the total number of 
contracts that the Task Force needed to close. In 2008, the Army 
estimated that the Task Force would need to close approximately 24,000 
contracts awarded by C3 in Iraq and Afghanistan from 2003 to 2008, but 
the Task Force recorded that C3 sent it 103,693 contracts (see table 
1). Our analysis of the Task Force's data indicates that C3 
transferred at least 66,760 Iraq contracts, including approximately 
8,500 more contracts awarded between fiscal years 2003 and 2008 than 
what was reflected in C3's database. Additionally, the Task Force 
inventoried another 14,336 contracts for which the place of 
performance was not specified.[Footnote 13] Army officials stated that 
C3 had closed some of these contracts before sending the files to the 
Task Force, but acknowledged that the C3 data did not accurately 
reflect which contracts were closed. Therefore, the Army required Task 
Force personnel to review each contract and close those that remain 
open. Army officials stated, however, that there have been no attempts 
to reconcile the C3 contracting data with the Task Force's findings. 

Table 1: Status of C3 Contracts Inventoried and Reviewed by the Task 
Force as of April 2011: 

Place of contract performance: Iraq; 
Reviewed: 26,735; 
Not reviewed: 40,025; 
Total contracts inventoried: 66,760. 

Place of contract performance: Not specified[A]; 
Reviewed: 0; 
Not reviewed: 14,336; 
Total contracts inventoried: 14,336. 

Place of contract performance: Afghanistan; 
Reviewed: 3,510; 
Not reviewed: 19,087; 
Total contracts inventoried: 22,597. 

Place of contract performance: Total; 
Reviewed: 30,245[B]; 
Not reviewed: 73,448; 
Total contracts inventoried: 103,693[C]. 

Source: GAO analysis of DOD data. 

[A] DOD generally uses a DOD Activity Address Code within the contract 
identification number to identify the office awarding the contract. 
According to C3's Acquisition Instruction, these contracts reflected 
Activity Address Codes that were not among those C3 personnel were 
authorized to use in Iraq and Afghanistan. We were unable to identify 
the place of performance for these contracts because there was no such 
data available in the Task Force's database as these contracts have 
not yet been reviewed for closeout. 

[B] GAO analysis indicates that 30,048 contracts were reviewed and 
closed, as appropriate, by Task Force personnel. There were an 
additional 129 contracts under review, but not closed, and another 68 
contracts under review with a place of performance other than Iraq or 
Afghanistan. 

[C] Nearly all of the contracts sent to the Task Force were awarded 
from fiscal year 2002 to 2008. Task Force data, however, also indicate 
that 3,165 Iraq contracts, 2,964 Afghanistan contracts, and 2 
unspecified contracts awarded between fiscal years 2009 and 2010 were 
sent to the Task Force. We could not determine the award year for 
another 287 contracts. 

[End of table] 

The extent to which the contracts that have not yet been reviewed by 
Task Force personnel and will need to be closed is uncertain, in part, 
because some that were reportedly closed by C3 still required contract 
administration. For example, Task Force personnel stated that 
contracts sometimes included a signed DD 1594 even though the 
contracts still required administrative actions. 

To improve the management of its contracts, C3 began using the 
Standard Procurement System in fiscal year 2009. Both Army and C3 
officials stated that the Standard Procurement System had better 
quality control checks to generate valid contract numbers with 
automated prompts requiring contracting personnel to insert required 
data fields, such as period of performance, at the time of award. 
These officials also said that the quality control checks improved the 
completeness and quality of C3's data and provided better insight 
needed to manage the contract closeout process. Army officials said 
that once the Standard Procurement System was deployed in Iraq, the 
regional contracting centers were able to transmit data back to Army 
locations in the United States which could be used to run automated 
reports on contracts closed, eligible for closeout, and over age for 
closeout. Army and C3 officials acknowledged that while the data 
improved, C3 continued to identify problems with the data input by 
contracting personnel. In a July 2010 memorandum, C3 directed its 
personnel to take actions to improve the overall quality, accuracy, 
and timelines of C3's contracting actions. For example, it identified 
specific data fields, including those that help to determine a 
contract's eligibility for closeout, that personnel are required to 
capture in C3's data systems. 

C3 obtained better visibility of its firm-fixed price contracts 
awarded in fiscal years 2009 and later as well as their large, cost-
type contracts. C3's data on these firm-fixed price contracts 
indicates that C3 closed over 9,600 of its Iraq contracts awarded 
between fiscal years 2009 and 2010. Similarly, DOD officials indicated 
that C3 had better visibility of its large, cost-type contracts 
awarded between fiscal years 2003 and 2010, in part because it 
generally delegated contract administration for these contracts, 
including closeout responsibilities, to DCMA Southern Europe in 2008. 
DCMA officials reported that when it accepted C3's cost-type 
contracts, the files were in generally poor condition and missing 
documents. DCMA officials reported, however, that they devoted the 
resources necessary to collect missing information for these contracts 
and developed their own data to manage the closeout of these contracts 
and task orders. Our analysis of these firm-fixed price and cost-type 
contracts indicates that 97 percent were over age as of May 2011 (see 
table 2). 

Table 2: Closeout Status for Selected C3 Contracts as of May 2011: 

Fiscal year awarded: 2009-2010; 
Contract type: Firm-fixed price; 
Eligible to close: 3,282; 
Over age: 3,192; 
Percent over age: 97%. 

Fiscal year awarded: 2003-2010; 
Contract type: Cost-type; 
Eligible to close: 109; 
Over age: 106; 
Percent over age: 97%. 

Fiscal year awarded: Total; 
Eligible to close: 3,391; 
Over age: 3,298; 
Percent over age: 97%. 

Source: GAO analysis of DOD data. 

[End of table] 

Other DOD Organizations Had Better Visibility of Contracts, but 
Challenges Remain for Closeout: 

ACC-RI, AFCEE, and USACE officials indicated that the use of existing 
contracting systems at the onset of military operations in Iraq 
provided them better visibility into the number of contracts they had 
awarded to support efforts in Iraq. Agency officials acknowledged, 
however, that they sometimes encountered challenges with using their 
existing systems. For example, USACE officials noted that the standard 
reports used to determine which Iraq contracts needed to be closed 
were initially inaccurate because period of performance or physical 
completion dates were not correctly entered into their contracting 
systems. As a result, USACE officials found in March 2011 that USACE's 
closeout reports underestimated the number of contracts eligible and 
over age for closeout due to inaccurate period of performance dates. 
USACE revised its reports using period of performance dates from other 
data sources, which identified that 639 contracts were eligible to be 
closed, more than 300 contracts than its initial report reflected. 
Similarly, AFCEE's data indicate that the period of performance ended 
for 154 of its Iraq contracts but the data did not reflect whether 
final goods and services had been delivered and whether the contract 
was physically complete. Our analysis indicates that the period of 
performance ended at least 3 years ago for 37 of these contracts, but 
AFCEE personnel stated that they cannot close these contracts until 
they receive final documentation that the goods and services have been 
delivered. Overall, we estimate that about 66 percent of these 
organizations' 907 eligible contracts are over age (see table 3). 

Table 3: DOD Iraq Contracts Reported Eligible and Over Age for 
Closeout: 

Contracting organization: ACC-RI LOGCAP; 
Contract type: Cost-type; 
Eligible to close: 18; 
Over age: 17; 
Percent over age: 94%. 

Contracting organization: AFCEE; 
Contract type: Firm-fixed price; 
Eligible to close: 5; 
Over age: 4; 
Percent over age: 80%. 

Contracting organization: AFCEE; 
Contract type: Cost-type; 
Eligible to close: 222; 
Over age: 83; 
Percent over age: 37%. 

Contracting organization: AFCEE; 
Contract type: Time and materials; 
Eligible to close: 23; 
Over age: 9; 
Percent over age: 39%. 

Contracting organization: USACE; 
Contract type: Firm-fixed price; 
Eligible to close: 572; 
Over age: 463; 
Percent over age: 81%. 

Contracting organization: USACE; 
Contract type: Cost-type; 
Eligible to close: 63; 
Over age: 20; 
Percent over age: 32%. 

Contracting organization: USACE; 
Contract type: Time and materials; 
Eligible to close: 4; 
Over age: 0; 
Percent over age: 0. 

Contracting organization: Total; 
Eligible to close: 907; 
Over age: 596; 
Percent over age: 66%. 

Source: GAO analysis of data reported by contracting organizations 
between January and June 2011. 

[End of table] 

Our analysis of data provided by these contracting organizations 
reflects a higher percent of eligible firm-fixed price contracts that 
are over age compared to eligible cost-type contracts, in part due to 
the longer period of time allowed by the FAR to close out cost-type 
contracts.[Footnote 14] For example, our analysis indicates that about 
81 percent of the firm-fixed price contracts eligible to be closed 
were over age compared to approximately 40 percent of eligible cost-
type contracts. Nevertheless, these organizations have closed few of 
their cost-type Iraq contracts. For example, USACE data indicate that 
it had closed 7 of its 77 Iraq cost-type contracts and AFCEE had 
closed just 10 of its 239 Iraq cost-type contracts awarded since 2003. 

Planning, Workforce, and Contractor Accounting Issues Hinder Efforts 
to Close Contracts: 

DOD's ability to close the contracts it awarded to support efforts in 
Iraq is hindered by several factors, including the failure to plan for 
or emphasize the need to close these contracts until reconstruction 
efforts were well underway, staffing shortfalls, and contractor 
accounting issues. DOD did not plan for or focus on closing its Iraq 
contracts until 2008, in part because DOD's contingency contracting 
policy and guidance do not emphasize the need to plan for contract 
closeouts during the early stages of a contingency operation. DOD has 
taken steps to reduce the number of firm-fixed price contracts it 
needs to close, but ACC-RI has not been able to hire enough personnel 
to replace Task Force personnel during the transition of closeout 
responsibilities, which has slowed these efforts. Similarly, efforts 
to close its large, cost-type contracts is hindered by staffing 
shortages at DCAA and unresolved issues with contractors' cost 
accounting practices that preclude completing the necessary audits of 
the contractors' incurred costs. As a result, DOD is unlikely to close 
226 cost-type contracts with over $19.1 billion in obligations in the 
near future. 

DOD Doctrine and Policy Do Not Emphasize Advanced Planning for 
Closeout: 

DOD contingency contracting doctrine and policy do not specifically 
include closeout as part of the advanced planning for a contingency 
operation. Since 2006, a contract support integration plan annex 
termed Annex W--which provide details on the contractor support 
required during a contingency, including the military's organizational 
requirements needed to acquire and oversee such support--has been 
required to be in DOD's most detailed operation plans.[Footnote 15] In 
October 2008, DOD established its first doctrine to standardize 
guidance for planning, conducting, and assessing operational contract 
support integration, contractor management functions, and contracting 
command and control in support of joint operations in its Joint 
Publication 4-10, Operational Contract Support.[Footnote 16] In part, 
this doctrine provides guidance for contingency contracting 
requirements that should be planned for within the Annex W. While it 
states that an Annex W should outline all activities necessary to 
execute contract support integration requirements in an operational 
area, it does not specifically direct DOD commands to determine an 
approach for closing contracts in advance or even during the initial 
stages of a contingency operation. Joint Publication 4-10 advises that 
contracts be closed as performance is completed, consistent with the 
requirements established in the FAR, but makes no reference for the 
need to plan for the resources needed to close contracts within 
required time frames. Instead, contract closeout is described as part 
of the redeployment and contract termination phase, the fourth and 
final operational phase of a contingency. In 2009, DOD issued a 
template for planners to use when developing Annex Ws and plans to 
incorporate the template into planning policy. The template does not, 
however, specifically call attention to the need to plan for the 
closeout of contracts. Furthermore, in March 2010, we reported that 
few of the operation plans approved by the Secretary of Defense or his 
designee even included an Annex W and when they did, those annexes 
restated broad language from DOD's high-level guidance on operational 
contract support.[Footnote 17] 

The contracting organizations included in our review generally did not 
conduct any planning to close the contracts they awarded to support 
operations in Iraq until several years after the contracts were 
initially awarded. DOD officials noted that the department initially 
assumed that post-conflict stability and reconstruction efforts would 
not last for an extended period and as such, any organization that 
awarded contracts to support these efforts would close contracts under 
the organization's standard processes. Officials acknowledged that as 
these efforts continued and the level of contracting activity 
increased, C3's predecessors attempted to close contracts as time and 
resources permitted, but did not develop a plan needed to do so. For 
example, 

* The Army did not develop a plan to close its Iraq contracts until 
2008, long after reconstruction efforts were underway in Iraq. 
According to the Army, the 2007 Gansler Commission report's finding 
that only 5 percent of eligible Iraq contracts were closed prompted 
the Army to begin planning for and taking steps to address the backlog 
of over-age Iraq contracts. To do so, in October 2008, the Army 
established the Task Force and delegated responsibility to DCMA 
Southern Europe to close a number of C3's cost-type contracts. 

* According to USACE personnel, they began focusing on contract 
closeouts after the Army identified that the Army had more than 
660,000 over-age contracts as of January 2009 and established a goal 
to close all of its over-age contracts by the end of fiscal year 2011. 
In January 2011, USACE established a contract closeout cell in 
Winchester, Virginia. 

* AFCEE personnel, with 96 over-age Iraq contracts, stated they have 
not developed an Iraq contract closeout plan and continue to close 
these contracts as part of their routine contracting activities. AFCEE 
personnel stated, however, only two contracting personnel are assigned 
to closing the Iraq contracts and do so only when time and other 
responsibilities permit. 

Commands Focused Limited Staff Resources on Awarding Contracts: 

DOD officials also noted that the need to focus limited staff 
resources on fulfilling urgent requirements in support of the war 
effort, and other contingency-related challenges, contributed to the 
backlog of contracts to be closed. One senior Army official noted that 
as there were not enough contracting officers in theater to handle 
both awards and closeouts, the command focused its attention on 
awarding contracts. Similarly, C3 and USACE contracting personnel we 
spoke with stated that they were responsible for awarding, 
administering, and closing contracts, but to meet urgent requirements, 
they prioritized contract awards over other activities. In addition, 
an Army official noted that contracting personnel have little 
incentive to close contracts, as their success is often measured by 
contracts awarded. Contracting personnel who are responsible for 
closing contracts stated, however, that emphasis on timely contract 
closeout is especially important in a contingency environment because 
the longer the time from when the contractor completes its work and 
when the contract is closed, the more difficult it becomes to 
determine the status of contracts, resolve documentation and 
administration issues, obtain a release of claims, and negotiate final 
payments. For example, 

* To close a $16.8 million guard services contract, contracting 
personnel in Iraq described the process of determining how payments 
were made as "putting together pieces of a puzzle." Personnel stated 
that they spent several weeks identifying what the contractor billed 
and was paid by reviewing invoices, contract modifications, and e- 
mails. 

* Similarly, contracting personnel in Iraq stated that resolving an 
overpayment of over $500,000 has delayed the closeout of another $17 
million guard services contract. The contracting officer who awarded 
and administered the contract was no longer in Iraq when the 
contracting personnel began closing the contract. These personnel 
stated that they relied on e-mails in the contract file and obtained 
payment information from DFAS to determine the extent to which the 
contractor was overpaid and are awaiting further guidance from DFAS on 
what steps are needed to recover funds from the contractor. 

* Task Force personnel noted that while closing a $1.3 million 
contract for life support services, they found that there was no 
documentation in the contract file to explain why services were not 
performed at three camp sites listed in the contract. The contractor 
told Task Force personnel that he was instructed not to perform the 
services but was never provided anything in writing. Task Force 
personnel noted that the contractor then refused to sign the release 
of claims, so personnel unilaterally deobligated the remaining funds 
on the contract to close the contract. 

* According to one senior C3 official, contracting officers sometimes 
relied on documents provided by the contractor to resolve claims 
because they were not maintained in the contract files. In one 
instance, while closing a vehicle lease contract, C3 personnel stated 
that they found 149 damage claims for vehicles, but oversight 
personnel often did not keep records or pictures of the condition of 
the vehicles when they were picked up and dropped off by the 
contractor. The contracting personnel stated that they are 
coordinating with the payment office and resource managers but said 
that it may not be possible to locate someone who can verify or 
dispute the claims. 

Task Force personnel stated that they often needed to perform routine 
contract administration tasks on contracts, including reconciling 
payments and obligations, acquiring receiving reports, contacting 
contractors in theater to obtain invoices and release of claims, and 
piecing together incomplete contract files to provide reasonable 
assurance that the government received what it paid for and the 
contract could be closed. Task Force personnel illustrated some of the 
challenges they often encounter in the following two examples: 

* In one case involving the closeout of a $55 million contract for 
shotguns, goggles, and radios, Task Force personnel stated that they 
had to reconcile payments against nine different task orders because 
payments were not made to the correct task orders, including one lump- 
sum payment for $8 million that did not correspond to any task order, 
and the contract was missing receiving reports and payment documents. 
Task Force personnel contacted DFAS to determine how much should have 
been paid on the task order and verified payments through a data 
system. Task Force personnel eventually closed all of the task orders 
between March and December 2010. 

* During the closeout of another contract for $101,000 to lease buses 
from an Iraqi contractor, Task Force personnel found that the 
contractor was not paid for 1 month of service and not compensated for 
damages to two of the buses. After contacting DFAS and determining 
that there were enough funds on the contract to cover the missing 
payment and repair costs, Task Force personnel notified the payment 
office to make a final payment to the contractor. Task Force personnel 
were able to close the contract after the contractor was paid and a 
release of claims was received. 

Workforce Challenges Associated with Transitioning Closeout 
Responsibilities Have Reduced Capacity to Close Firm-Fixed Price 
Contracts: 

C3 has taken steps to reduce the number of firm-fixed price contracts 
it needs to close, but difficulties with hiring ACC-RI personnel have 
slowed these efforts. The Army and C3 initially established the Task 
Force to address the backlog of C3's firm-fixed price contracts 
awarded before fiscal year 2009 and planned at that time to close any 
contracts awarded in fiscal year 2009 and later in theater. To ensure 
the contracts remaining in theater were closed, a senior C3 official 
established closeout goals in October 2010 and required each regional 
contracting center to appoint personnel responsible for completing 
contract closeout. While Army data indicate that progress was made in 
closing contracts in Iraq, C3 officials told us that closeout goals 
were tracked informally and acknowledged that some regional 
contracting centers were unable to meet these goals. By February 2011, 
the Army changed its strategy and decided that when the Task Force is 
shut down in September 2011, all C3 contracts, including those awarded 
after fiscal year 2009, would eventually be transferred to ACC-RI for 
closeout. According to C3's commanding general, this decision was made 
because ACC-RI has a workforce that can handle complex contract 
actions and has expertise in southwest Asia contracting. 

By June 2011, the Army had transferred about 15,000 Iraq and 
Afghanistan contracts awarded between fiscal years 2008 and 2010 from 
the Task Force to ACC-RI. According to the Army, ACC-RI personnel are 
in the process of inventorying these contracts and identifying which 
are closed or require additional administration. Army officials stated 
that they are reviewing ACC-RI closeout procedures and data collection 
efforts to ensure Army data are accurate and complete. 

During this transition period, ACC-RI has not been able to hire the 
number of individuals it estimated it needed to manage the anticipated 
workload and the number of contracts reviewed and closed by the Task 
Force has fallen considerably. According to Army officials, ACC-RI 
will need to hire 25 individuals by the time it fully assumes the Task 
Force's responsibilities. Army officials stated that ACC-RI has 
experienced challenges hiring contracting personnel in part due to 
potential applicants' hesitation to accept these positions, which are 
term positions that expire by October 2012. Army officials stated as 
of June 2011, ACC-RI had only hired 4 staff but efforts are underway 
to hire additional personnel. Until these positions can be filled, 
other ACC-RI personnel are temporarily supporting the closeout 
efforts. In addition, in July 2011, the ACC-RI issued a task order for 
contract closeout support to AbilityOne, which provides job 
opportunities on federal contracts for individuals who are blind or 
have other disabilities. According to one ACC-RI official, ACC-RI 
plans to hire nine AbilityOne employees under this contract. It 
remains uncertain, however, when the Army will be able to review and, 
as necessary, close the contracts that remain at the Task Force. 
Similarly, Army officials stated that the Task Force's capacity to 
close contracts has decreased, as 10 of its 25 staff have resigned in 
advance of the Task Force's planned closure. During the week of 
September 3, 2010, the Task Force closed 439 contracts but by the week 
of June 9, 2011, the Task Force only closed 267 contracts. 

Limited DCAA Staffing and Unresolved Contractor Accounting Challenges 
Hinder Closeout of Cost-Type Contracts: 

DOD's efforts to close its large, cost-type contracts are hindered by 
staffing shortages at DCAA and unresolved issues with contractors' 
cost accounting practices. DOD reported that it had 226 over-age, cost-
type Iraq contracts with approximately $19.1 billion in obligations 
(see table 4). A critical step to closing these contracts is to 
determine how to allocate a contractor's general administrative and 
overhead costs to each of its contracts. To do so, DCAA performs 
annual incurred cost audits on a contractor-by-contractor basis--
versus a contract-by-contract basis--by reviewing incurred cost 
proposals from the contractor for each year of performance. DCAA 
auditors test direct and indirect costs to determine whether they are 
allowable, allocable, and reasonable. The direct and indirect costs 
form the basis for DCAA's recommended indirect cost rate, which is 
usually used by the contracting officer to negotiate a final rate with 
the contractor. When the indirect cost rate for the final year of 
contract performance is settled and the final price of the contract is 
determined, contract closeout may proceed. 

Table 4: Number of DOD Cost-Type Contracts Related to Iraq Eligible 
for Closeout: 

Contracting organization: ACC-RI LOGCAP; 
Number of eligible contracts: 18; 
Number of over-age contracts: 17; 
Obligations on over-age contracts: $14.8 billion. 

Contracting organization: C3; 
Number of eligible contracts: 109; 
Number of over-age contracts: 106; 
Obligations on over-age contracts: $2.6 billion. 

Contracting organization: AFCEE; 
Number of eligible contracts: 222; 
Number of over-age contracts: 83; 
Obligations on over-age contracts: $1.4 billion. 

Contracting organization: USACE; 
Number of eligible contracts: 63; 
Number of over-age contracts: 20; 
Obligations on over-age contracts: $0.3 billion. 

Contracting organization: Total; 
Number of eligible contracts: 412; 
Number of over-age contracts: 226; 
Obligations on over-age contracts: $19.1 billion. 

Source: GAO analysis of data reported by contracting organizations 
between January and July of 2011. 

[End of table] 

DOD's cost-type contracts related to Iraq often spanned multiple years 
and as such DCAA must complete incurred cost audits for each year of 
performance. For example, on one contract with performance from 2004 
through 2008 and 5 divisions of the contractor claiming costs, DCAA is 
required to complete 25 audits of costs incurred, one for each year of 
performance per division. DCAA, however, is still completing audits 
for this contractor for costs incurred in 2004 and 2005, with audits 
of the remaining years scheduled for 2011 and after. DCAA officials 
told us that this condition is due in part to a DCAA-wide shortage of 
auditors. DCAA data indicates that from fiscal years 2000 to 2011, its 
workforce grew by 16 percent while DOD research and procurement 
spending, an indicator of DCAA's workload, increased by 87 percent. In 
addition, DCAA officials stated that in response to GAO's finding in 
2009 on problems with DCAA's audit quality, including insufficient 
testing of contractors' support for claimed costs, DCAA now requires 
more testing and stricter compliance with government auditing 
standards, which adds to the amount of staff time required to complete 
each audit.[Footnote 18] DCAA officials stated that as their workload 
increased and resources remained relatively constant, auditors 
prioritized time-sensitive activities, such as audits to support new 
awards, and incurred cost audits were not completed, creating a 
backlog. 

In planning for its fiscal year 2011 workload requirements, DCAA 
determined that it had the resources to complete only about half of 
its entire portfolio of required audits and activities, including both 
Iraq and non-Iraq work. As a result, DCAA prioritized its high-risk 
audits, which included the backlog of incurred audits for C3's 106 
over-age, cost-type contracts. As of July 2011, DCAA reported that of 
the 116 incurred cost audits needed to close these C3 contracts, it 
had completed 27 audits and estimated another 19 audits will be 
completed by the end of fiscal year 2011. The remaining 70 audits are 
planned to be completed after fiscal year 2011. DCMA contracting 
officials responsible for closing C3's cost-type contracts stated that 
regardless of whether DCAA completes the 19 audits as planned, none of 
the C3 contracts can be closed by the end of fiscal year 2011 because 
most of the contractors claimed costs through 2008 or 2009, and the 
audits will only be completed for costs incurred mostly through 2004 
and 2005. Further, there are an additional 31 AFCEE over-age cost-type 
contracts that will not have final incurred cost audits completed 
before the end of fiscal year 2011. 

To address its resource challenges, DCAA officials reported that it 
hired over 500 new employees in the past 2 years. DCAA has also 
requested authority to hire 200 auditors per year over each of the 
next 5 years. DCAA officials noted, however, that it often takes 
several years before auditors are properly trained to conduct an 
incurred cost audit. In addition, in January 2011, DOD issued a 
memorandum that shifted some audit responsibilities, such as lower 
dollar price proposal audits and purchasing system reviews, to DCMA to 
allow DCAA to devote more resources to high-risk work, like the 
incurred cost audits needed to support the closeout of Iraq contracts. 
DCAA officials also stated that they plan to dedicate additional 
auditors to solely focus on conducting incurred cost audits in fiscal 
year 2012. 

DCAA has identified a number of deficiencies at major defense 
contractors, which provided support in Iraq, that need to be resolved 
before the incurred cost audits can be completed. These deficiencies 
include: 

* inadequate incurred cost proposals and cost documentation; 

* inadequate contractor business systems; 

* accounting practices that are not compliant with cost accounting 
standards,[Footnote 19] leading to misallocation of costs; 

* delays in providing DCAA access to needed records; 

* disputes with contractors over unallowable costs; and: 

* other challenges, such as those due to ongoing litigation. 

The following examples illustrate the challenges that DCAA reported 
for several contractors. 

* Due to inadequate incurred cost proposals, DCAA has completed 
incurred costs audits only through 2003 for one major Iraq contractor 
that incurred costs through 2010. In total, DOD has $15.3 billion in 
obligations on over-age, cost-type Iraq contracts awarded to this 
contractor. DCAA reported that it issued the 2003 incurred cost audit 
5 years after the costs were incurred, in part because the contractor 
repeatedly submitted inadequate incurred cost proposals and did not 
provide adequate support for costs (see figure 2). Further, DCAA 
officials stated that the incurred cost proposals submitted by the 
contractor for 2004 through 2009 are inadequate but will continue its 
audits of the 2004 and 2005 proposals. 

Figure 2: Incurred Cost Audit for One Major Iraq Contractor's 2003 
Costs Was Delayed Until 2008 Due in Part to Repeated Inadequate 
Proposal Submissions: 

[Refer to PDF for image: timeline] 

December 2003: 
Contractor year ends. 

October 2004: 
Contractor submits incurred cost proposal. 

April 2005: 
DCAA deems proposal inadequate. 

March 2006: 
Contractor resubmits incurred cost proposal. 

July 2006: 
DCAA deems revised proposal inadequate. 

September 2007: 
DCAA provides list of inadequately supported transactions to 
contractor. 

April 2008: 
DCAA issues 2003 incurred cost audit report. 

Source: GAO analysis of DCAA's incurred cost audit report. 

[End of figure] 

* Additionally, DCAA reported that this contractor had deficient 
accounting systems, unresolved issues associated with unallowable 
costs, noncompliant accounting practices, and legal investigations 
that further delayed incurred cost audits. In 2006, DCAA reported that 
the contractor had significant deficiencies in its accounting system 
that resulted in the contractor charging over $370 million to 
incorrect task orders from 2002 to 2004, requiring reclassification of 
costs to the proper task orders. The reclassifications were completed 
in January 2005. Then, in 2009 and 2010, DCAA found over $185 million 
in unallowable costs that are pending negotiations with DCMA and 
settlement of contractor claims. In 2010, DCAA auditors found the 
contractor did not comply with the cost accounting standard associated 
with insurance costs, which resulted in an estimated $1.6 million in 
costs that were misallocated. DCAA reported that the contractor did 
not respond to DCAA's finding because it had not completed its 
management review of the allocated costs. Further, according to the 
auditors, DCAA's incurred cost audit reports could be delayed as the 
auditors coordinate the issuance of audit reports with various 
investigative agencies. DCAA auditors do not expect to complete the 
2004 and 2005 incurred cost audits for this contractor before the end 
of fiscal year 2011. In May 2011, the contractor withdrew its 2006 
through 2009 incurred cost proposals and stated that it plans to delay 
its submission of the 2010 incurred cost proposal until November 2011. 

* For another major contractor, DCAA identified that the contractor's 
accounting practices were not compliant with cost accounting 
standards. DOD has $316 million in obligations on over-age, cost-type 
Iraq contracts awarded to this contractor with performance between 
2004 and 2009. DCAA reported in 2006 that the contractor's accounting 
practices did not sufficiently remove unallowable costs from a cost 
proposal, which DCAA auditors stated put additional onus on them to 
test whether the costs were allowable. In one case, DCAA auditors 
found the contractor had included over $500,000 in bonuses to senior 
executives in the incurred cost proposal, even though these costs are 
expressly unallowable under law. The contractor disagreed with DCAA's 
findings but agreed to remove these costs from its proposal. As of 
July 2011, DCAA has completed 5 of the 18 incurred cost audits 
required to close the contracts. 

* DCAA identified deficient subcontract management systems, disputes 
over unallowable costs, and challenges with access to records as 
contributing to delays in completing incurred cost audits for another 
contractor. DOD has $212 million in obligations on over-age, cost-type 
Iraq contracts awarded to this contractor. In 2005, 2006, and 2009, 
DCAA auditors reported significant deficiencies in the contractor's 
subcontract management system that resulted in potential unreasonable 
and unallowable costs being billed to the government, subcontracts 
being awarded noncompetitively, and inadequate price analysis. As a 
result, DCAA auditors had to audit the subcontractors' costs, even 
though doing so is generally the prime contractor's responsibility. 
The contractor generally disagreed with DCAA's findings but stated it 
would evaluate and revise its procedures where necessary to comply 
with DCAA's recommendations. In addition, in 2010 and 2011, DCAA 
auditors reported the contractor had over $22.5 million in unallowable 
subcontract costs, some of which have been appealed by the contractor 
and some of which are being settled by DCMA. Finally, in 2010, DCAA 
auditors repeatedly requested but were denied access to support for 
the 2006 incurred cost proposal, including a $2.3 million procurement 
file. DCAA reported that its auditors requested the data over a period 
of 5 months and stated that when the contractor provided the data, 
they were still inadequate in supporting the claimed costs. DCAA 
auditors stated as a result, it deemed those costs as unallowable for 
reimbursement. 

DOD has taken steps to address the challenges with auditing 
contractors' incurred costs. For example, effective June 2011, the FAR 
was revised to list the minimum information that contractors must 
include for proposals to be adequate to address the delays resulting 
from inadequate incurred cost proposals. Also, to improve its 
oversight of contractor business systems, DOD revised the Defense 
Federal Acquisition Regulation Supplement in May 2011 to more clearly 
define contractor business systems, including accounting, estimating, 
and purchasing, and to allow payments to be withheld from contractors 
if their business systems contain significant deficiencies. 

DOD Has Taken Steps to Mitigate Potential Loss or Misuse of Funds but 
Limited Visibility into Its Contracts Hinders Such Efforts: 

DOD has taken steps to identify unspent contract funds and recover 
improper payments, but limited visibility into its contracts has 
hindered such efforts. For example, DOD has deobligated some funds to 
make them available to meet other DOD needs, but there remains at 
least $135 million that will potentially not be available for use by 
DOD at the end of fiscal year 2011. DOD generally cannot identify to 
which contracts these funds are associated. Additionally, instances of 
improper payments and potential fraud were sometimes found years after 
final deliveries were made, but contracting personnel may not be able 
to recover funds owed to the government. 

DOD's Efforts to Prioritize the Deobligation of Funds that Will Return 
to Treasury at the End of the Fiscal Year Are Affected by Poor 
Visibility into Its Contracts: 

DOD prioritizes deobligating funds that may potentially be returned to 
Treasury at the end of each fiscal year so these funds would be 
available for other DOD uses. DOD contracting organizations, however, 
have varying degrees of visibility into the amount of funds remaining 
on their Iraq contracts. Contracting organizations we met with 
generally could not identify the total and unliquidated obligations 
associated with their Iraq contracts, in part because the systems used 
to track contracting information were not linked with systems used to 
track financial and payment data. Similarly, DOD resource managers, 
who are responsible for maintaining information on the availability of 
funding, tracked unspent funds at the appropriation level but did not 
always have such information on a contract-by-contract basis. DOD 
estimates that at least $135 million in contract funding could return 
to Treasury by the end of fiscal year 2011 if not deobligated but 
there may be additional funds not yet identified (see table 5). 

Table 5: Estimated Iraq Contract Funding that Potentially Could Return 
to Treasury at the End of Fiscal Year 2011: 

Contracting organization: C3[A]; 
Estimated amount of funds: $18.6 million. 

Contracting organization: AFCEE[B]; 
Estimated amount of funds: unknown. 

Contracting organization: USACE[C]; 
Estimated amount of funds: $104.9 million. 

Contracting organization: ACC-RI LOGCAP[D]; 
Estimated amount of funds: $12.3 million. 

Contracting organization: Total; 
Estimated amount of funds: $135.8 million. 

Source: GAO analysis of DOD data. 

[A] Estimates for C3 include both cost-type and firm-fixed price 
contracts and are as of May and June 2011, respectively. 

[B] AFCEE did not track these data for their contracts in theater. 

[C] Estimates for USACE are as of March 2011. 

[D] Estimates for LOGCAP are as of June 2011. 

[End of table] 

C3, AFCEE, and USACE contracting organizations generally do not track 
unspent funds that could be returned to Treasury on a contract-by- 
contract basis. As a result, resource management personnel stated they 
are responsible for notifying contracting personnel of these funds. 
Resource management personnel, however, reported that identifying the 
appropriate contracting personnel can be time-consuming and labor- 
intensive, in part because of the rapid turnover of contracting 
personnel, which often caused the contact information listed in the 
data systems to be invalid. Contracting personnel stated that once 
they were aware that funds may be potentially returned to Treasury, 
they took steps to prioritize deobligating these funds, including 
checking whether there were pending invoices or claims requiring 
payments. For example: 

C3 did not maintain visibility of unspent funds at the contract level, 
in part due to limitations in its contracting and financial management 
systems, but available data indicate that DOD may lose $18.6 million 
for its use and which will be returned to Treasury at the end of 
fiscal year 2011. While C3 officials noted that some contracting 
officers may have tracked unspent funds for contracts for which they 
were responsible, we found that C3's contracting data systems did not 
maintain such financial data. After being delegated closeout 
responsibility for C3's large, cost-type contracts, DCMA Southern 
Europe undertook efforts to manually track unspent funds on a contract-
by-contract basis. DCMA personnel reported that $15.0 million of funds 
that could be returned to Treasury remained on C3's cost-type 
contracts as of May 2011, but anticipated having most of these funds 
deobligated by the end of July 2011. Similarly, without visibility 
into which firm-fixed price contracts had unspent funds, Task Force 
personnel focused their efforts on reviewing C3 contracts awarded in 
fiscal year 2006 to deobligate funds but told us they do not believe 
they will be able to close all of these contracts before these funds 
are returned to Treasury. Resource managers at U.S. Army Central--
which manages the funds associated with C3's contracts--stated they 
believe that, as of June 2011, $3.6 million on these contracts will 
potentially be returned to Treasury. 

AFCEE contracting personnel stated that they generally do not maintain 
visibility into AFCEE's unspent funds at the contract level. For 
AFCEE's own contracts, contracting personnel generally deobligate 
funds down to 10 percent of the total obligated amount, or $100,000, 
whichever is less, to pay for any additional costs that may be 
identified during DCAA's incurred cost audits. AFCEE contracting 
personnel reported that for these contracts, they do not believe any 
funds will be returned to Treasury at the end of fiscal year 2011. 
AFCEE contracting personnel stated that for the contracts awarded on 
behalf of other organizations, they are notified by the customers of 
unspent funds on an ad-hoc basis. AFCEE contracting personnel stated 
that they prioritize the deobligation of these funds when they are 
made aware of them, but do not track the total amount of funds that 
may be returned to Treasury. 

USACE contracting personnel stated that they do not maintain 
information on unspent funds on a contract level, but rather USACE 
resource managers tracked funds at the account level. For these 
accounts, USACE resource managers notify contracting personnel, who 
attempt to identify which contracts are associated with these funds 
and, as appropriate, take steps to deobligate these funds. USACE 
reported, however, that $104.9 million have not been deobligated as of 
March 2011. USACE personnel stated that a majority of these funds are 
on contracts awaiting DCAA audits.[Footnote 20] 

Conversely, ACC-RI's LOGCAP office tracked funds that could be 
returned to Treasury on a contract-by-contract basis. ACC-RI 
contracting personnel stated that they hold weekly meetings with the 
contractor and resource managers to reconcile financial records and 
identify funds that could be deobligated. ACC-RI personnel told us 
that $12.3 million of funds that could be returned to Treasury have 
not been deobligated as of June 2011, but anticipated having most of 
these funds deobligated by the end of July 2011. 

DOD Incurred Unnecessary Costs because Improper Payments Were 
Discovered Late: 

In some instances, DOD discovered improper payments during the 
contract closeout process years after the contractors delivered the 
final good or service, but some attempts to recover overpayments were 
unsuccessful and, at times, late payments to contractors resulted in 
interest fees.[Footnote 21] According to DFAS personnel responsible 
for recovering overpayments made on some Iraq contracts, if contracts 
were closed immediately after final payments are made, overpayments 
could be discovered earlier, which increases the likelihood of 
recovering payments. For example, when the contractor is still 
conducting business with the government, DFAS can reduce payments on 
one contract to offset overpayments made on another contract. Task 
Force personnel noted that for a 2005 vehicle lease contract, 
contracting personnel in theater found the contractor was overpaid by 
over $41,000 on several invoices and subsequently DFAS withheld 
payments on several of the contractor's other contracts to completely 
offset the overpayment. DFAS personnel, however, stated that the more 
time that has passed from when the contractor was mistakenly paid, the 
more difficult it becomes to recover those payments because the 
contractor may no longer be in business with the U.S. government or 
may have changed address or name. In several instances, overpayments 
on contracts for goods or services delivered in 2007 or earlier were 
not referred to DFAS until 2010 (see table 6). DFAS personnel stated 
that in these cases, despite numerous attempts to contact the 
contractor, they have yet to recover the overpayments. As of June 
2011, two of the contracts have been referred to Treasury and one 
contract has been referred to another DFAS office for further debt 
collection efforts. 

Table 6: Examples of Contracts with Overpayments that Were Not 
Recovered: 

Description of contract good or service: Gymnasium; 
Delivery date: 10/8/2004; 
Date referred to DFAS: 8/18/2010; 
Amount of unrecovered overpayment: $104,696. 

Description of contract good or service: Linguist building 
construction; 
Delivery date: 3/11/2007; 
Date referred to DFAS: 9/27/2010; 
Amount of unrecovered overpayment: $170,000. 

Description of contract good or service: Latrines with servicing; 
Delivery date: 10/31/2007; 
Date referred to DFAS: 10/5/2010; 
Amount of unrecovered overpayment: $27,200. 

Source: GAO analysis of Task Force and DFAS data. 

[End of table] 

In a few instances, Task Force personnel did not refer overpayments to 
DFAS because they determined the excess payments were relatively small 
in value or unlikely to be recovered. For example, Task Force 
personnel found that the U.S. government overpaid a contractor by 
$8,100 for trash services provided in 2006 and 2007. After 
unsuccessful attempts to contact the contractor, Task Force personnel 
closed the contract in 2009, noting that so much time had passed since 
the final payment that it was unreasonable to expect that the 
overpayment could be recovered. 

C3 is unable to mitigate the amount of interest payments that may be 
associated with late payments because the contracting and financial 
management systems cannot identify which contracts still require 
payment, especially for contracts awarded between 2003 and 2007. Task 
Force personnel stated that given the limitations of these systems, 
they must review the contract file to determine whether a contract 
requires additional payment. For example, while closing a $94,500 
contract for vehicle lease services in Iraq, Task Force personnel 
discovered the contractor may not have been paid for 2 months' worth 
of vehicle lease services, so the Task Force is attempting to contact 
personnel in theater to confirm whether services were rendered. 
Additionally, some contracts requiring final payments were not paid 
until years after the final delivery, which resulted in interest 
payments. DFAS personnel reported that DFAS has paid $2.8 million in 
interest payments on Iraq contracts as of June 2011, though it is not 
possible to determine the amount of interest payments associated with 
over-age contracts. 

DOD took steps to improve its payment processes in Iraq, but some 
challenges with timely payments remain. According to DFAS officials, 
in 2008, DFAS became responsible for making payments for contracts 
awarded in theater with obligations of $25,000 or more and in 2010 
DFAS and C3 agreed to lower this threshold to $3,000. DFAS officials 
stated this decision was made to improve internal controls by ensuring 
that adequate documentation was available before payments are made in 
theater. DFAS officials noted, however, there were some payment delays 
because payment documentation requirements were not always met. One C3 
official noted that these payment processing delays led to some Iraqi 
vendors being unwilling to do business with the U.S. government and 
walking off job sites. C3's commanding general stated that when 
contracts are not closed out and vendors have not been paid for goods 
and services that they provided to the U.S. government, this 
contributes to negative perceptions about Americans. 

Finally, late contract closeouts may hinder efforts to identify and 
address potential fraud found on the C3 contracts because they were 
reported to investigators years after the potential fraudulent 
activities took place and the contract files were poorly maintained. 
As Task Force personnel reviewed and closed C3 contracts, they 
identified 151 contracts with potential fraudulent activities and 
referred these contracts to the Army's Criminal Investigations 
Division. For example, in one contract for a cable fiber network, Task 
Force personnel stated that they found evidence that the contracting 
officer had made a payment of $84,000 in cash, but the contractor's 
invoice was only for $64,000. There was no documentation in the file 
to account for the $20,000 difference between the disbursement and 
invoice, so Task Force personnel referred this case to the Army's 
criminal investigators. According to an Army investigator, it was 
difficult to determine whether this case and other cases were due to 
fraudulent activity or contracting errors, in part because the 
contracts did not have enough documentation to build a case. 
Furthermore, the Army investigator stated that many of the referred 
contracts had been awarded many years ago so following up on these 
cases has been challenging, as many of the contracting personnel and 
contractors involved are no longer available. 

Growing Backlog of Afghanistan Contracts Suggests Problems Related to 
Closing Contracts Will Continue: 

DOD reported that actions are underway to address the lessons learned 
in Iraq, including developing deployable contract management systems 
and explicitly requiring that contract closeout requirements be 
incorporated into contingency contracting planning documents. DOD 
officials acknowledge, however, they are likely to face similar 
problems with closing contracts awarded to support efforts in 
Afghanistan. For example, the backlog of C3's Afghanistan contracts 
that need to be closed is growing steadily, but the Army's capacity to 
close these contracts in the United States remains in question due to 
challenges with transitioning closeout responsibilities from the Task 
Force to ACC-RI. 

DOD Has Identified and Addressed Some of the Problems Associated with 
Closing Iraq Contracts: 

In October 2010, as part of the Army's Operational Contract Support 
Lessons Learned Program, C3 identified lessons learned from 
contracting in Iraq between 2005 and 2010. As part of this effort, C3 
identified the need to improve and consolidate data management, 
improve contract oversight, and increase emphasis on contract 
administration and closeout. DOD officials told us they had already 
implemented or planned new practices, as the following examples 
illustrate. 

* C3 officials noted that they had implemented the Standard 
Procurement System in both Iraq and Afghanistan to better document 
information on contracts awarded during and after fiscal year 2009 and 
have worked to improve the data input into the system. Defense 
Procurement and Acquisition Policy officials and a representative from 
the Joint Chiefs of Staff told us they are also identifying and 
developing deployable contract writing and management systems with the 
intent that one day contingency contracting personnel will use the 
same contract management tools in theater that are used in the United 
States. 

* C3 also identified that contract oversight was a historic problem 
and noted the need to ensure contracting officer's representatives 
fulfilled their oversight responsibilities. In March 2010, the Under 
Secretary of Defense for Acquisition, Technology and Logistics issued 
new certification requirements for contracting officer's 
representatives to ensure they are experienced and trained before they 
are appointed to oversee contractor performance. In June 2011, we 
reported, however, that DOD personnel in Afghanistan were not always 
fully prepared for their roles and responsibilities to provide 
adequate oversight there.[Footnote 22] 

* Defense Procurement and Acquisition Policy has also issued and since 
updated the Defense Contingency Contracting Handbook, which includes 
reference material to ensure contingency contracting officers maintain 
proper contract documentation and complete closeout duties. For 
example, the handbook includes guidance on the essential documents 
that should be in a contract file, identifies steps to ensure 
contracts are properly enumerated to avoid duplicate contract numbers, 
and recognizes the need to close contracts as soon as possible. 

Finally, DOD is in the process of determining how it will address the 
problems C3 attributed to a lack of planning for the contracting 
requirements in Iraq. A senior C3 official recommended that 
operational campaign plans include a contracting annex, such as an 
Annex W. In such cases when an Annex W would be required, we found 
that Joint Publication 4-10 and DOD's Annex W guidance do not fully 
address the need to plan for contract closeout requirements--including 
identifying responsibilities, either in or outside of theater, for 
closing contracts. United States Forces-Iraq issued an Annex W in 
2011, which included directions for personnel to take steps to close 
contracts in Iraq, well after C3's backlog of contracts was 
identified. Representatives from the Joint Chiefs of Staff responsible 
for revising Joint Publication 4-10 and the Annex W guidance recognize 
the need to incorporate more specific language on the need to plan for 
contract closeout during the contingency contracting planning process. 
These officials stated that they plan to issue new Annex W guidance by 
the end of 2011 and intend to add more specific language regarding 
contract closeout. 

Steadily Increasing Backlog of C3's Afghanistan Contracts Suggests 
Closeout Problems May Persist: 

As was the case in Iraq, C3 officials stated that prior to the build-
up of forces in Afghanistan, contract closeout was a challenge because 
there were not enough contracting personnel in theater to meet 
competing contracting demands. To address its backlog of contracts 
awarded before fiscal year 2009, C3 delegated responsibility for 
closing at least 22,597 Afghanistan inactive contracts to the Task 
Force.[Footnote 23] Task Force data indicate that 3,510, or about 16 
percent, of these contracts have been reviewed as of April 2011. Task 
Force personnel stated that they faced the same challenges with 
closing the Afghanistan contracts as those associated with the Iraq 
contracts, such as poor contract documentation and improper payments. 

According to C3's commanding general and senior contracting officials, 
these challenges were exacerbated during the build-up of U.S. military 
personnel in Afghanistan, and the focus remains on meeting the 
warfighter's needs. C3 officials told us the number of contracting 
officers in Afghanistan increased from about 60 in 2008 to about 200 
in April 2011. In part, this increase in personnel enabled C3 to close 
over 18,600 contracts awarded between fiscal years 2009 and 2011. 
Despite these efforts, however, the number of contracts eligible to be 
closed continues to grow. For example, as of April 2008, C3 data 
indicated that 1,471 Afghanistan contracts remained in theater that 
were eligible but over age for closeout. As of May 2011, the number of 
contracts eligible but over age for closeout has increased to over 
16,900 contracts. Additionally, C3 will have to close over 7,000 other 
contracts awarded during this period that are eligible but not yet 
over age for closeout. C3 officials told us they expect that more 
Afghanistan contracts will be transferred out of theater to be closed 
by ACC-RI, likely after much of the remaining Iraq contracts are 
closed. As previously noted, however, the Army's ability to close 
contracts remains in question due to challenges with transitioning 
closeout responsibilities to ACC-RI. 

Conclusions: 

Contract closeout is a key step to ensure the government receives the 
goods and services it purchases at the agreed upon price and, if done 
in a timely manner, provides opportunities to utilize unspent funds 
for other DOD needs. In Iraq, however, contract closeout was often an 
afterthought or was done as time permitted. The complications DOD has 
faced with closing its Iraq contracts underscore the importance of 
advanced planning to close contracts awarded in a contingency 
environment, encouraging a greater command emphasis on completing and 
overseeing administrative requirements, establishing a process to 
provide better management visibility and insight into contracting 
efforts, and ensuring that DOD's contracting workforce has the 
capacity to provide appropriate contract administration and contractor 
oversight. Meeting warfighter needs is paramount, but doing so does 
not lessen the need to ensure that contracts are properly administered 
and executed. 

DOD's recognition in 2008 that it needed to address the backlog of 
contracts that are over age for closeout and its establishment of the 
Task Force came too late in the operation to make a significant 
difference in closing contracts within the required time frames. By 
not fully understanding the scope of the backlog and waiting to 
address it, DOD underestimated the efforts required to close these 
contracts. Further, the limited visibility provided by the contracting 
and financial management systems hindered DOD's ability to identify 
and address improper payments. Challenges with transitioning closeout 
responsibilities to ACC-RI appear to have hindered the progress the 
Army had made in closing its Iraq contracts. With over 100,000 C3 Iraq 
and Afghanistan contracts that need to be reviewed and closed, as 
appropriate, further delays in closing these contracts can be 
expected. Finally, closing the large cost-type contracts is further 
hindered by DCAA's shortage of auditors and problems with contractor 
accounting practices. DOD has recognized the need to increase DCAA's 
staffing and address contractor business systems, but fully 
implementing these initiatives will take several years. 

Recommendations for Executive Action: 

To help address the current backlog of contracts supporting the 
efforts in Iraq and Afghanistan that need to be closed out, we 
recommend that the Secretary of Defense direct the Secretary of the 
Army to take steps to ensure ACC-RI's planned resources are adequate 
to meet forecasted closeout demands. 

To help improve DOD's ability to manage the closeout of contracts 
awarded in support of future contingencies, we recommend that the 
Secretary of Defense, in coordination with the Chairman of the Joint 
Chiefs of Staff, take the following two actions: 

* revise DOD's contingency contracting doctrine and guidance to 
reflect the need for advanced planning for contract closeout; and: 

* require senior contracting officials to monitor and assess the 
progress of contract closeout activities throughout the contingency 
operation so steps may be taken if a backlog emerges. 

Agency Comments and Our Evaluation: 

DOD provided written comments on a draft of this report. DOD concurred 
with the three recommendations and identified a number of ongoing and 
planned actions to address them. For example, DOD noted that Army 
Contracting Command-Rock Island will utilize contractors and explore 
additional options, such as the Wounded Warrior program, to assist in 
closing contracts. DOD also noted that it recently amended the Defense 
Federal Acquisition Regulation Supplement and provided additional 
guidance to DOD personnel to underscore the need to understand the 
unique requirements and considerations associated with planning and 
executing contingency contract administration services in contingency 
operations. DOD also plans to further revise its guidance to address 
the need for contracting officers to do advance planning for closeout 
of contracts performed in contingency areas. DOD also indicated it 
intends to issue a revised Joint Publication 4-10, its contingency 
contracting planning doctrine, in June 2012 to reflect the need for 
such planning. DOD also provided technical comments, which were 
incorporated as appropriate. DOD's comments are reprinted in appendix 
II. 

We are sending copies of this report to the Secretary of Defense, the 
Secretaries of the Army and Air Force; the Under Secretary of Defense 
(Acquisition, Technology, and Logistics); the Director, Defense 
Procurement and Acquisition Policy; the Under Secretary of Defense 
(Comptroller) and Chief Financial Officer; the Chairman, Joint Chiefs 
of Staff; the Commander, U.S. Central Command; the Director, Defense 
Contract Audit Agency; the Director, Defense Finance and Accounting 
Service; and interested congressional committees. In addition, the 
report will be made available at no charge on GAO's Web site at 
[hyperlink, http://www.gao.gov]. 

If you or your staff have any questions concerning this report, please 
contact me at (202) 512-4841. Contact points for our Offices of 
Congressional Relations and Public Affairs may be found on the last 
page of this report. GAO staff who made major contributions to this 
report are listed in appendix III. 

Signed by: 

John P. Hutton: 
Director: 
Acquisition and Sourcing Management: 

List of Addressees: 

The Honorable Carl Levin: 
Chairman: 
The Honorable John McCain: 
Ranking Member: 
Committee on Armed Services: 
United States Senate: 

The Honorable Joseph I. Lieberman: 
Chairman: 
Committee on Homeland Security and Governmental Affairs: 
United States Senate: 

The Honorable Claire McCaskill: 
Chairman: 
Ad Hoc Subcommittee on Contracting Oversight: 
Committee on Homeland Security and Governmental Affairs: 
United States Senate: 

The Honorable Howard P. McKeon: 
Chairman: 
The Honorable Adam Smith: 
Ranking Member: 
Committee on Armed Services: 
House of Representatives: 

[End of section] 

Appendix I: Scope and Methodology: 

To assess the Department of Defense's (DOD) efforts to close its Iraq 
contracts, under the authority of the Comptroller General to conduct 
evaluations on his own initiative, we examined the (1) total number of 
its contracts with performance in Iraq that are eligible for closeout 
and the extent to which DOD closed these contracts within required 
time frames, (2) factors that contributed to contracts not being 
closed within required time frames, (3) steps DOD took to manage the 
financial risks associated with not closing contracts within required 
time frames, and (4) how DOD captured and implemented lessons learned 
from closing its Iraq contracts. 

To determine the number and value of DOD's Iraq contracts eligible for 
closeout and the extent to which DOD will close these contracts within 
required time frames, we reviewed the Federal Acquisition Regulation 
(FAR) and the Defense Federal Acquisition Regulation Supplement which 
provide the time frames and the procedures for closing contracts. For 
the purpose of our review the term contracts refers to all base 
contracts, task orders, and blanket purchase agreement call orders. We 
obtained contract data from four DOD organizations which our prior 
work indicated had been responsible for awarding the majority of 
contracts with performance in Iraq: CENTCOM Contracting Command (C3), 
Army Contracting Command-Rock Island (ACC-RI), US Army Corps of 
Engineers (USACE), and Air Force Center for Engineering and the 
Environment. These organizations may retain responsibility for 
administering and closing the contracts they awarded, or may they may 
delegate such responsibilities to another organization. In those 
instances, we obtained contract data from that organization, which 
includes Defense Contract Management Agency, ACC-RI, and C3's Contract 
Closeout Task Force Office (Task Force). From each organization, we 
requested the following data for contracts for which they are 
responsible: contract and order numbers, period of performance, 
contract type, contract status, total obligations, total unliquidated 
obligations, and physical completion dates. We identified contracts 
that were eligible for closeout and over age for closeout based on the 
time frames established in the FAR. We also identified contracts that 
did not have complete data to determine eligibility for closeout, but 
we determined these contracts to be eligible and over age according to 
data available. We assessed the reliability of these data reported by 
the contracting organizations through interviews with knowledgeable 
officials and electronic data testing for missing data, outliers, and 
obvious errors within each database. While we found that C3's contract 
data from fiscal years 2003 through 2008 were generally unreliable for 
determining the closeout status of contracts, they were sufficiently 
reliable for determining the minimum number of contracts awarded 
during this time period. We did not evaluate or assess the reliability 
of the financial management systems used to provide financial data for 
the purpose of our review. We also did not independently evaluate 
whether DOD closed individual contracts in accordance with the 
procedures outlined in the FAR or other DOD guidance. 

To identify the factors that contributed to contracts not being closed 
within FAR-required time frames, we analyzed data provided by and 
interviewed officials at each of the contracting organizations and the 
Defense Finance and Accounting Service (DFAS), which is responsible 
for making payments on some of the Iraq contracts. To understand any 
challenges faced by DOD contracting personnel in closing individual 
contracts, we reviewed contract documents for 25 firm-fixed price 
contracts purposefully selected to obtain a variety of closeout 
organizations and a range of closeout difficulty and interviewed 
contracting personnel on their experiences with closing them. We also 
reviewed Task Force and ACC-RI closeout data to assess the Army's 
ability to close C3's contracts. In addition, to identify the factors 
that affected the closeout of cost-type contracts, we interviewed 
personnel at each of the contracting organizations. In addition, we 
purposefully selected eight contractors with varying amounts of over- 
age cost-type contracts, obligations on contracts, and remaining 
unliquidated obligations and reviewed DCAA's incurred cost and other 
audit reports for these contracts, and interviewed DCAA officials at 
headquarters and eight field offices to determine the factors affected 
their ability to complete the audits. We also reviewed Joint 
Publication 4-10; the Defense Contingency Contracting Handbook; and 
the Defense Contract Management Agency's contract closeout guidance 
and handbook to assess the guidance provided to DOD contracting 
personnel regarding the need to plan the contract closeout process. 

To determine the steps DOD has taken to manage the financial risks 
associated with not closing contracts within FAR time frames, we 
reviewed the DOD Financial Management Regulation and each contracting 
office's closeout guidance. We also interviewed contracting and 
financial management personnel at the Office of the Under Secretary of 
Defense, Comptroller; Office of the Assistant Secretary of the Army, 
Financial Management & Comptroller; U.S. Forces - Iraq, Force 
Structure Resources and Assessment (J-8); U.S. Army Central Command; 
and USACE. In addition, we analyzed unliquidated obligation data 
provided by both the contracting personnel and financial management 
personnel to determine how these funds were managed. To determine the 
steps DOD has taken to manage other risks of not closing contracts 
timely, we reviewed data and interviewed officials from C3; the Task 
Force; DFAS, which is responsible for collecting overpayments and 
tracking interest payments; and the Army's Criminal Investigations 
Division, which is responsible for investigating instances of 
fraudulent activity found in contracts. 

To assess the extent to which DOD captured and implemented lessons 
learned from closing contracts in contingency operations, we 
interviewed contracting officials at each of the organizations we 
visited to identify any lessons learned and reviewed documentation 
when available. We also interviewed senior contracting officials in 
Iraq and Afghanistan to identify any changes made in response to the 
lessons learned from closing the C3 contracts. We reviewed DOD's 
current contingency contracting doctrine and guidance, and interviewed 
officials from the Joint Chiefs of Staff who are responsible for 
revising the doctrine and guidance. We also interviewed officials from 
the Office of Under Secretary of Defense for Acquisition, Technology, 
and Logistics' Office of Defense Procurement and Acquisition Policy 
and the Office of the Deputy Assistant Secretary for the Army 
(Procurement) to identify any policy changes that may result from the 
lessons learned in Iraq. We obtained and reviewed C3 data on the total 
number of its Afghanistan contracts eligible and over age for closeout 
to assess its ability to close these contracts. 

We conducted this performance audit from July 2010 through September 
2011 in accordance with generally accepted government auditing 
standards. Those standards require that we plan and perform the audit 
to obtain sufficient, appropriate evidence to provide a reasonable 
basis for our findings and conclusions based on our audit objectives. 
We believe that the evidence obtained provides a reasonable basis for 
our findings and conclusions based on our audit objectives. 

[End of section] 

Appendix II: Comments from the Department of Defense: 

Office Of The Under Secretary Of Defense: 
Acquisition, Technology And Logistics: 
3000 Defense Pentagon: 
Washington, DC 2030 1-3000: 

September 26, 2011: 

Mr. John T. Hutton: 
Director, Acquisition and Sourcing Management: 
U.S. Government Accountability Office: 
441 G Street, N.W. 
Washington, DC 20548: 

Dear Mr. Hutton: 

This is the Department of Defense (DoD) response to the GAO draft 
report 11-891, "Contingency Contracting: Improved Planning and 
Management Oversight Needed to Address Challenges in Closing 
Contracts," dated August 23, 2011 (GAO Code 120931). Detailed comments 
on the report recommendations are enclosed. Technical comments were 
provided separately for your consideration. 

The Department appreciates the opportunity to comment on the draft 
report. My point of contact for this effort is Mr. Bill Reich, 
william.reich@osd.mil, 571-256-7009. 

Sincerely, 

Signed by: 

Richard Ginman: 
Director, Defense Procurement and Acquisition Policy: 

Enclosure: As stated. 

[End of letter] 

GAO Draft Report Dated August 23, 2011: 
GAO-11-891 (GAO Code 120931): 

"GAO Draft Report, GAO-II-891, "Contingency Contracting: Improved 
Planning and Management Oversight Needed to Address Challenges with 
Closing Contracts," dated August 23, 2011 (GAO Code 120931): 

Department Of Defense Comments To The GAO Recommendations: 

Recommendation 1: The GAO recommends that the Secretary of Defense 
direct the Secretary of the Army to take steps to ensure Army 
Contracting Command-Rock Island's (ACC-RI) planned resources are 
adequate to meet forecasted closeout demands. 

DOD Response: Concur with comment. C-JTSCC, in coordination with ACC-
RI, will provide contract closeout data on a quarterly basis in order 
for the Deputy Assistant Secretary of the Army (DASA(P)) to meet the 
recommendation to ensure resources are adequate to meet forecasted 
closeout demands. The availability of ACC-RI rotational personnel was 
effectively leveraged to start work despite delays with hiring term 
personnel. Due to the availability of ACC-RI rotational personnel, ACC-
RI was able to make progress in closing contracts while striving 
towards hiring dedicated ACC-RI closeout personnel. Additionally. ACC-
RI issued a Task Order under an existing contract for six closeout 
specialists, a supervisor and two warehouse personnel. Funding was 
provided by DASA(P). The ACC-RI also identified the Wounded Warrior 
program as a potential source of personnel. The ACC-R1 will begin to 
utilize hiring flexibilities available under their authority. To 
assist ACC-RI, DASA(P) began recruitment actions for ACC-RI in the 
beginning of FY11. To date, three people from the Contract Closeout 
Task Force Office (CCTFO) have accepted offers and will relocate to 
ACC-RI after CCTFO drawdown 30 September 2011. Five additional 
personnel were hired from a list of qualified applicants provided to 
ACC-RI by the DASA(P). They reported in late June 2011. 

Recommendation 2: The GAO recommends that the Secretary of Defense 
revise DOD's contingency contracting doctrine and guidance to reflect 
the need for advanced planning for contract closeout. 

DOD Response: Concur. Joint Publication (JP) 4-10 is in the process of 
being updated by the Joint Staff J-4, Logistics Directorate. The Joint 
Staff Doctrine Sponsor and lead agent for this update have agreed to 
add this planning consideration to the revised publication, which is 
expected to be released by June 2012. The need to understand the 
unique requirements and considerations associated with planning and 
executing contingency contract administration services (CCAS) in 
contingency operations was recently added to Defense Federal Acquisition
Regulation Supplement and Procedures, Guidance, and Information (DFARS 
PGI) at 207.105(b)(20)(C)(8) and 225.7404. Draft DFARS PGI language is 
also being developed that addresses the need for contracting officers 
to do advance planning for closeout of contracts performed in 
contingency areas. 

Recommendation 3: The GAO recommends that the Secretary of Defense 
require senior contracting officials to monitor and assess the 
progress of contract closeout activities throughout the contingency 
operation so steps may be taken if a backlog emerges. 

DOD Response: Concur. C-JTSCC is monitoring and assessing the progress 
of contract closeout activities in Iraq and Afghanistan by identifying 
candidate contract closeouts through the Army Contracting Business 
Intelligence System (ACBIS) database and weekly updates from ACC-RI. 
Draft DFARS and PGI language is being developed that addresses this 
contract closeout requirements and contract administration in support 
of contingency operations, For future contingency operations, this 
recommendation will be addressed in the JP 4-10 update. 

[End of section] 

Appendix III: GAO Contact and Staff Acknowledgments: 

GAO Contact: 

John P. Hutton, (202) 512-4841 or huttonj@gao.gov: 

Acknowledgments: 

In addition to the individual named above key contributors to this 
report were Timothy DiNapoli, Assistant Director; Johana Ayers; Noah 
Bleicher; Seth Carlson; Morgan Delaney-Ramaker; Justin Jaynes; Julia 
Kennon; John Krump; Claire Li; Anne McDonough-Hughes; and Roxanna Sun. 

[End of section] 

Footnotes: 

[1] FAR § 4.804-1(a)(2). 

[2] FAR § 4.804-1(a)(3). 

[3] For appropriated funds, Congress specifies the period of time each 
appropriation can be used. Any funds not obligated within their period 
of availability are considered expired. Expired funds cannot be used 
for new obligations but can be used up to 5 years after they expire to 
pay for authorized increases to existing obligations made from the 
same appropriation. Any funds remaining after the 5-year period are 
considered canceled and must be returned to the Treasury. 

[4] C3 became the Joint Theater Support Contracting Command for Iraq 
and Afghanistan on June 11, 2010. C3 was preceded by the Joint 
Contracting Command - Iraq/Afghanistan, the Project and Contracting 
Office, and the Coalition Provisional Authority. 

[5] GAO, Contingency Contracting: Observations on Actions Needed to 
Address Systemic Challenges, [hyperlink, 
http://www.gao.gov/products/GAO-11-580] (Washington, D.C.: Apr. 25, 
2011). 

[6] GAO, Rebuilding Iraq: Fiscal Year 2003 Contract Award Procedures 
and Management Challenges, [hyperlink, 
http://www.gao.gov/products/GAO-04-605] (Washington, D.C.: June 1, 
2004). 

[7] GAO, Defense Contract Management: DOD's Lack of Adherence to Key 
Contracting Principles on Iraq Oil Contract Put Government Interests 
at Risk, [hyperlink, http://www.gao.gov/products/GAO-07-839] 
(Washington, D.C.: July 31, 2007). 

[8] GAO, Military Operations: DOD Needs to Address Contract Oversight 
and Quality Assurance Issues for Contracts Used to Support Contingency 
Operations, [hyperlink, http://www.gao.gov/products/GAO-08-1087] 
(Washington, D.C.: Sept. 26, 2008). 

[9] Files for contracts using simplified acquisition procedures should 
be considered closed when the contracting officer receives evidence of 
receipt of property and final payment, unless otherwise specified by 
agency regulations. FAR § 4.804-1(a)(1). 

[10] The FAR also prohibits the closing of contract files if the 
contract is in litigation, under appeal, or where the contract is 
being terminated and all termination actions have not been completed. 
FAR § § 4.804-1(c)(1) and (2). 

[11] C3 data reported a total of seven fiscal year 2002 contracts 
awarded before operations began in Iraq that we found to be coded 
incorrectly. 

[12] Internal controls should provide reasonable assurance that the 
objectives of the agency are being achieved in the following 
categories: effectiveness and efficiency of operations including the 
use of the entity's resources; reliability of financial reporting, 
including reports on budget execution, financial statements, and other 
reports for internal and external use; and compliance with applicable 
laws and regulations. GAO/AIMD-00-21.3.1 

[13] C3 also transferred 22,597 of its Afghanistan contracts that were 
awarded between 2002 and 2008 to the Task Force to be reviewed and 
closed. 

[14] FAR § § 4.804-1(a)(2) and (3). 

[15] An operation plan describes how DOD will respond to a potential 
event that might require the use of military force. It is composed of 
a base plan, which describes the concept of operations, major forces, 
sustainment concept, and anticipated time lines for completing the 
mission; and annexes, which provide further details on areas such as 
intelligence, logistics, personnel, communications, and operational 
contract support. Chairman of the Joint Chiefs of Staff Manual 
3122.03B, Joint Operation Planning and Execution System (JOPES) Volume 
II Planning Formats (Feb. 28, 2006). Superseded by Joint Chiefs of 
Staff Manual 3122.03C, Joint Operation Planning and Execution System 
(JOPES) Volume II Planning Formats (Aug. 17, 2007). 

[16] Joint Chiefs of Staff, Joint Publication 4-10, Operational 
Contract Support (Oct. 17, 2008). 

[17] GAO, Warfighter Support: DOD Needs to Improve Its Planning for 
Using Contractors to Support Future Military Operations, [hyperlink, 
http://www.gao.gov/products/GAO-10-472] (Washington, D.C.: Mar. 30, 
2010). 

[18] GAO, DCAA Audits: Widespread Problems with Audit Quality Require 
Significant Reform, [hyperlink, 
http://www.gao.gov/products/GAO-09-468] (Washington, D.C.: Sept. 23, 
2009). 

[19] The Cost Accounting Standards are accounting requirements for the 
measurement, assignment, and allocation of costs to government 
contracts. 

[20] USACE personnel stated that USACE also served as the payment 
office for a number of contracts awarded by C3 and AFCEE. USACE 
identified an additional $83.0 million that may potentially return to 
Treasury at the end of fiscal year 2011 for these contracts as of 
March 2011. USACE personnel could not identify which contracting 
offices were responsible for these contracts and is currently 
coordinating with the Task Force, AFCEE, and DCMA contracting 
personnel to identify which contracts they have to deobligate these 
funds. 

[21] Improper payments are defined as any payment that should not have 
been made or that was made in an incorrect amount (including 
overpayments and underpayments) under statutory, contractual, 
administrative, or other legally applicable requirements. It also 
includes any payment to an ineligible recipient or ineligible service, 
duplicate payments, payments for services not received, and any 
payment for an incorrect amount. In 2009, GAO reported that DOD's 
processes to conduct risk assessments, estimate improper payments, and 
develop corrective actions to reduce improper payments had significant 
weaknesses. See GAO, Improper Payments: Significant Improvements 
Needed in DOD's Efforts to Address Improper Payment and Recovery 
Auditing Requirements, [hyperlink, 
http://www.gao.gov/products/GAO-09-442] (Washington, D.C.: July 29, 
2009). 

[22] GAO, Operational Contract Support: Actions Needed to Address 
Contract Oversight and Vetting of Non-U.S. Vendors in Afghanistan, 
[hyperlink, http://www.gao.gov/products/GAO-11-771T] (Washington, 
D.C.: June 30, 2011). 

[23] We could not identify the place of performance for over 14,000 
other contracts that were sent to the Task Force to be closed. 

[End of section] 

GAO's Mission: 

The Government Accountability Office, the audit, evaluation and 
investigative arm of Congress, exists to support Congress in meeting 
its constitutional responsibilities and to help improve the performance 
and accountability of the federal government for the American people. 
GAO examines the use of public funds; evaluates federal programs and 
policies; and provides analyses, recommendations, and other assistance 
to help Congress make informed oversight, policy, and funding 
decisions. GAO's commitment to good government is reflected in its core 
values of accountability, integrity, and reliability. 

Obtaining Copies of GAO Reports and Testimony: 

The fastest and easiest way to obtain copies of GAO documents at no 
cost is through GAO's Web site [hyperlink, http://www.gao.gov]. Each 
weekday, GAO posts newly released reports, testimony, and 
correspondence on its Web site. To have GAO e-mail you a list of newly 
posted products every afternoon, go to [hyperlink, http://www.gao.gov] 
and select "E-mail Updates." 

Order by Phone: 

The price of each GAO publication reflects GAO’s actual cost of
production and distribution and depends on the number of pages in the
publication and whether the publication is printed in color or black and
white. Pricing and ordering information is posted on GAO’s Web site, 
[hyperlink, http://www.gao.gov/ordering.htm]. 

Place orders by calling (202) 512-6000, toll free (866) 801-7077, or
TDD (202) 512-2537. 

Orders may be paid for using American Express, Discover Card,
MasterCard, Visa, check, or money order. Call for additional 
information. 

To Report Fraud, Waste, and Abuse in Federal Programs: 

Contact: 

Web site: [hyperlink, http://www.gao.gov/fraudnet/fraudnet.htm]: 
E-mail: fraudnet@gao.gov: 
Automated answering system: (800) 424-5454 or (202) 512-7470: 

Congressional Relations: 

Ralph Dawn, Managing Director, dawnr@gao.gov: 
(202) 512-4400: 
U.S. Government Accountability Office: 
441 G Street NW, Room 7125: 
Washington, D.C. 20548: 

Public Affairs: 

Chuck Young, Managing Director, youngc1@gao.gov: 
(202) 512-4800: 
U.S. Government Accountability Office: 
441 G Street NW, Room 7149: 
Washington, D.C. 20548: