This is the accessible text file for GAO report number GAO-10-657 
entitled 'Electronic Records Archive: Status Update on the National 
Archives and Records Administration's Fiscal Year 2010 Expenditure 
Plan' which was released on June 11, 2010. 

This text file was formatted by the U.S. Government Accountability 
Office (GAO) to be accessible to users with visual impairments, as 
part of a longer term project to improve GAO products' accessibility. 
Every attempt has been made to maintain the structural and data 
integrity of the original printed product. Accessibility features, 
such as text descriptions of tables, consecutively numbered footnotes 
placed at the end of the file, and the text of agency comment letters, 
are provided but may not exactly duplicate the presentation or format 
of the printed version. The portable document format (PDF) file is an 
exact electronic replica of the printed version. We welcome your 
feedback. Please E-mail your comments regarding the contents or 
accessibility features of this document to Webmaster@gao.gov. 

This is a work of the U.S. government and is not subject to copyright 
protection in the United States. It may be reproduced and distributed 
in its entirety without further permission from GAO. Because this work 
may contain copyrighted images or other material, permission from the 
copyright holder may be necessary if you wish to reproduce this 
material separately. 

Report to Congressional Committees: 

United States Government Accountability Office:
GAO: 

June 2010: 

Electronic Records Archive: 

Status Update on the National Archives and Records Administration's 
Fiscal Year 2010 Expenditure Plan: 

GAO-10-657: 

GAO Highlights: 

Highlights of GAO-10-657, a report to congressional committees. 

Why GAO Did This Study: 

Since 2001, the National Archives and Records Administration (NARA) 
has been working to develop an electronic records archive (ERA) to 
preserve and provide access to massive volumes and all types of 
electronic records. NARA certified initial operating capability of the 
first two phases of ERA in June 2008 and December 2008 and plans to 
achieve full operating capability for the system by 2012. As required 
by the Consolidated Appropriations Act, NARA submitted an expenditure 
plan to Congress to support its request for fiscal year 2010 ERA 
funding. The act also requires that this plan meet six conditions, 
including a review by GAO. GAO’s objectives in reviewing the fiscal 
year 2010 plan were to (1) determine whether the plan satisfies the 
legislative conditions, (2) determine the extent to which NARA has 
implemented prior GAO recommendations, and (3) provide any other 
observations on the plan or the ERA acquisition. To do this, GAO 
reviewed the expenditure plan and other agency documents and 
interviewed NARA officials. 

What GAO Found: 

NARA’s fiscal year 2010 expenditure plan satisfies five of the six 
legislative conditions and partially satisfies one. Specifically, it 
partially satisfies the condition that NARA develop a process for 
reviewing the progress of capital investments. Best practices call for 
such a process to include an oversight entity to review a project’s 
progress, take corrective actions in response to cost or schedule 
problems, and ensure the corrective actions are implemented. However, 
while NARA has conducted regular meetings with senior-level agency 
management to review ERA progress, there is little evidence that 
officials identified corrective actions or ensured the actions were 
implemented. As a result, it is uncertain whether ERA is receiving the 
necessary level of executive oversight. 

NARA has fully implemented three of GAO’s five prior recommendations 
and partially implemented two. The agency implemented recommendations 
to provide additional information on its plans for the remainder of 
fiscal year 2009, add an analysis of costs and benefits associated 
with the ERA component dedicated to presidential records, and develop 
a contingency plan for ERA in case of system failure. NARA partially 
implemented a recommendation to provide additional information in the 
fiscal year 2010 expenditure plan by adding information on ERA’s cost, 
schedule, and performance. However, the plan lacks key information, 
including the total cost of one of the increments to be funded. NARA 
has also developed but not yet implemented a plan to implement best 
practices in its process for measuring program progress, as GAO 
recommended. 

GAO has three observations on the expenditure plan and ERA acquisition: 

* The estimated life-cycle cost of the ERA system has increased, and 
the development is behind schedule. Over the last 3 fiscal years, the 
estimated cost has increased by about 7 percent, from about $531 
million to about $567 million. In addition, the planned completion 
dates for the two increments currently under development are about 1 
year later than dates established in program planning documents. 

* NARA has not detailed what system capabilities will be delivered in 
the final two ERA increments. While the expenditure plan identifies 
some high-level functions, it does not identify specific capabilities 
to be delivered or dates for completion. 

* NARA has not effectively defined or managed ERA’s requirements to 
ensure that the functionality delivered satisfies the objectives of 
the system. Although NARA established an initial set of high-level 
requirements, it lacks firm plans to implement about 43 percent of 
them. In addition, NARA has not updated its requirements document to 
reflect reinterpreted requirements and did not provide evidence that 
it always conducted reviews required by its internal policies. 
Without ensuring adequate oversight and establishing specific plans to 
complete ERA, it is increasingly unlikely that NARA will deliver the 
completed ERA system by 2012 with the originally envisioned 
capabilities. 

What GAO Recommends: 

GAO is recommending that the Archivist of the United States ensure 
that NARA’s investment review process includes adequate executive-
level oversight and that ERA’s requirements are being managed using a 
disciplined process. In commenting on a draft of this report, the 
Archivist generally agreed and described steps taken or planned to 
address our recommendations. 

View [hyperlink, http://www.gao.gov/products/GAO-10-657] or key 
components. For more information, contact David A. Powner at (202) 512-
9286 or pownerd@gao.gov. 

[End of section] 

Contents: 

Letter: 

Conclusions: 

Recommendations for Executive Action: 

Agency Comments: 

Appendix I: Briefing to Staff of Congressional Committees on NARA's 
Fiscal Year 2010 Expenditure Plan: 

Appendix II: Comments from the National Archives and Records 
Administration: 

Appendix III: GAO Contact and Staff Acknowledgments: 

[End of section] 

United States Government Accountability Office:
Washington, DC 20548: 

June 11, 2010: 

The Honorable Richard J. Durbin:
Chairman:
The Honorable Susan M. Collins:
Ranking Member:
Subcommittee on Financial Services and General Government:
Committee on Appropriations:
United States Senate: 

The Honorable José E. Serrano:
Chairman:
The Honorable Jo Ann Emerson:
Ranking Member:
Subcommittee on Financial Services and General Government:
Committee on Appropriations:
House of Representatives: 

Since 2001, the National Archives and Records Administration (NARA) 
has been developing a modern Electronic Records Archive (ERA). This 
major information system is intended to preserve and provide access to 
massive volumes of all types and formats of electronic records, 
independent of their original hardware or software. NARA plans for the 
system to manage the entire life cycle of electronic records, from 
their ingestion through preservation and dissemination to customers. 

The ERA system is being developed in five phases, or increments, the 
first of which is referred to as the "ERA base." According to NARA, 
this portion of the system achieved initial operating capability (IOC) 
in June 2008. The second increment includes the Executive Office of 
the President (EOP) system or "ERA EOP," and NARA certified that it 
reached IOC in December 2008. NARA plans to complete development of 
the remaining increments and achieve full operating capability by 2012. 

As mandated by the Consolidated Appropriations Act,[Footnote 1] NARA 
is required to submit an expenditure plan before obligating multi-year 
funds for the ERA program. In November 2009, NARA submitted its fiscal 
year 2010 expenditure plan to support its request for $85.5 million in 
ERA funding, which includes $61.7 million in multi-year funds. As in 
the previous year, the plan must satisfy six legislative conditions, 
including a review by GAO. Our objectives in reviewing the plan were 
to (1) determine whether NARA's fiscal year 2010 expenditure plan 
satisfies the legislative conditions, (2) determine the extent to 
which NARA has implemented prior GAO recommendations, and (3) provide 
any other observations about the expenditure plan and the ERA 
acquisition. 

To assess compliance with the legislative conditions, we analyzed the 
expenditure plan submitted by NARA in November 2009 and reviewed its 
budget submission to the Office of Management and Budget (OMB), along 
with other program documentation. To determine the extent to which 
NARA had implemented our prior recommendations, we obtained and 
reviewed agency documents, which included quarterly reports to 
Congress and the ERA contingency plan. To develop observations on the 
ERA expenditure plan and acquisition, we analyzed fiscal year 2009 and 
2010 schedule information contained in the expenditure plan, the ERA 
requirements document, and other agency data. We also interviewed NARA 
officials. 

To assess the reliability of the data in the expenditure plan, we 
obtained and reviewed NARA budget documents as well as its 
consolidated financial statement results for the fiscal year 2009 
Performance and Accountability Report. We also interviewed NARA 
officials to gain an understanding of the data and discussed our use 
of the data. 

We conducted this performance audit from January 2010 to June 2010 at 
NARA's College Park, Maryland, location in accordance with generally 
accepted government auditing standards. Those standards require that 
we plan and perform the audit to obtain sufficient, appropriate 
evidence to provide a reasonable basis for our findings and 
conclusions based on our audit objectives. We believe that the 
evidence obtained provides a reasonable basis for our findings and 
conclusions based on our audit objectives. 

On April 6, 2010, we briefed your staffs on the results of our review. 
This report transmits the material we used at the briefing and 
provides the recommendations that we made to the Archivist of the 
United States. The full briefing materials, including details on our 
scope and methodology, are reprinted as appendix I. 

In summary, we made the following major points: 

* NARA's fiscal year 2010 expenditure plan satisfies five of the six 
legislative conditions and partially satisfies one. Specifically, it 
partially satisfies the condition that it develop a process for 
reviewing the progress of capitol investments. Best practices call for 
such a process to include an oversight entity to review a project's 
progress, take corrective actions in response to cost or schedule 
problems, and ensure the corrective actions are implemented. However, 
while NARA has conducted regular meetings with senior-level agency 
management to review ERA progress, there is little evidence that 
officials identified corrective actions to address performance 
problems or ensured the actions were implemented. As a result, it is 
uncertain whether ERA is receiving the necessary level of executive 
oversight. 

* NARA has fully implemented three of our prior recommendations and 
partially implemented two: 

- NARA implemented our recommendations to provide additional 
information to Congress describing plans for the remainder of fiscal 
year 2009, add an analysis of the cost and benefits of using the EOP 
system to respond to presidential records requests, and develop an ERA 
contingency plan. 

- NARA has partially implemented two recommendations. First, in 
response to our recommendation that NARA provide additional 
information in the fiscal year 2010 expenditure plan on what was spent 
and delivered for deployed increments, NARA added information on 
completed increments and those planned for fiscal year 2010 with their 
associated costs. However, our review of the Expenditure Plan showed 
that it does not fully describe how NARA will expend fiscal year 2010 
funds. Second, in response to our recommendation to strengthen its 
earned value management processes, NARA developed an action plan to 
implement best practices identified in GAO's Cost Estimating Guide; 
[Footnote 2] however, this plan has not been fully implemented. We 
currently have work under way to evaluate NARA's earned value process 
and its implementation of the action plan. 

* We made three observations related to the ERA program and fiscal 
year 2010 expenditure plan: 

- The cost of ERA is rising, and the development of several system 
components is behind schedule. Specifically, over the last 3 fiscal 
years, the estimated life-cycle cost has increased by about 7 percent, 
from about $531 million to about $567 million. NARA attributed the 
change to increases in the complexity of the system being developed. 
In addition, NARA plans to complete Increment 3 in June 2010 and 
Increment 4 in mid-2011, both of which are about 1 year later than the 
milestones established in program planning documents. NARA officials 
stated that the delivery date is consistent with the current project 
schedule, which was not documented because they determined it was not 
cost effective to do so. 

- NARA has not detailed what capabilities will be delivered by the 
final two ERA phases, or increments. For example, the expenditure plan 
indicates that NARA will begin implementing ERA's preservation 
framework in Increment 4 but does not contain specific dates for 
completion or identify the associated capabilities that are to be 
delivered. Without including detailed plans for the final two 
increments, including specific dates for completion and associated 
functionality to be delivered, Congress will have limited insight to 
evaluate NARA's ongoing progress. 

- NARA has not effectively defined or managed requirements for the ERA 
system. Among other things, requirements should be documented at a 
high level and traceable throughout the system's life cycle to ensure 
that functionality satisfies the objectives of the system. Further, 
any changes to the program's scope should be reflected by updating the 
requirements in a structured way. Although NARA established an initial 
set of high-level requirements to guide the system's development, 
these requirements are not traceable to work in later phases, or 
increments, of system. Specifically, about 43 percent of the 
requirements have not been allocated to the remaining two increments, 
and NARA officials stated that it is uncertain whether they will be 
implemented at all. Consequently, it is unclear whether system 
development work performed during the last two phases of the system's 
development will result in functionality that satisfies the intended 
objectives. Further, NARA has not updated its ERA requirements 
document to reflect reinterpreted requirements. These weaknesses can 
be attributed to the fact that NARA did not manage requirements by 
conducting and documenting requirement reviews near the beginning of 
each increment, as called for in its guidance. NARA officials stated 
that requirements reviews for Increment 3 were conducted throughout 
the increment's development but not specifically documented. They 
added that a requirements review for Increment 4 would be conducted 
during the week of March 29th. Without better defined and managed 
requirements, NARA will have little assurance that the ongoing system 
development will meet its needs. 

Conclusions: 

While NARA's fiscal year 2010 expenditure plan met five of the six 
legislative conditions, the lack of documentation demonstrating the 
appropriate level of senior management review, approval, and oversight 
limits NARA's ability to ensure that the project makes expected 
progress. In addition, the lack of a documented current baseline 
schedule leaves NARA with limited ability to identify significant 
delays. The lack of key oversight documentation limits NARA's 
assurance that schedule delays and cost increases will not continue 
during ERA's development. 

In addition, without specific plans for completing the final two 
increments, NARA lacks assurance that the remaining increments will 
adequately fulfill its mission needs. Specifically, NARA's failure to 
follow its own guidance on requirements management has resulted in a 
set of requirements that is incomplete and out of date, which could 
lead to the system being completed without addressing all necessary 
requirements or the development of functionality to meet requirements 
that are no longer valid. Addressing these weaknesses is becoming even 
more critical as the projected completion of the project approaches; 
if they continue, it will be increasingly unlikely that NARA will be 
able to deliver the ERA system by 2012 with the capabilities 
originally envisioned or to effectively use the system to meet the 
needs of its users in support of NARA's mission of preserving and 
providing access to the nation's electronic records. 

Recommendations for Executive Action: 

To enhance NARA's ability to complete the development of ERA within 
reasonable funding and time constraints, we are recommending that the 
Archivist of the United States take the following two actions: 

* Ensure that NARA's investment review process has adequate executive- 
level oversight by maintaining documentation of the results of 
reviews, including changes to the program's cost and schedule baseline 
and any other corrective actions taken as a result of changes in ERA 
cost, schedule, and performance. 

* Ensure that ERA's requirements are managed using a disciplined 
process that results in requirements that are traceable throughout the 
project's life cycle and are kept current. 

Agency Comments: 

In written comments on a draft of this report, which are reprinted in 
appendix II, the Archivist of the United States generally agreed with 
our recommendations and summarized NARA actions taken or planned to 
address them. Specifically, he stated that NARA is now documenting the 
minutes and actions of Senior Staff meetings where ERA is discussed 
and has recently begun an intensive effort to review ERA requirements 
within the context of new technologies and changing business needs. 
The Archivist also stated that NARA managers recently met to determine 
top ERA functional priorities to be completed by the end of the 
contract. Finally, he added that the ERA Requirements Manager is 
mapping these functional priorities to their underlying contract 
requirements and plans to update the ERA requirements document. 

We are sending copies of this report to the Archivist of the United 
States. The report will also be available at no charge on the GAO Web 
site at [hyperlink, http://www.gao.gov]. 

If you or your staffs have any questions concerning this report, 
please contact me at (202) 512-9286 or by e-mail at pownerd@gao.gov. 
Contact points for our Offices of Congressional Relations and Public 
Affairs may be found on the last page of this report. GAO staff who 
made major contributions to this report are listed in appendix III. 

Signed by: 

David A. Powner: 
Director, Information Technology Management Issues: 

[End of section] 

Appendix I: Briefing to Staff of Congressional Committees on NARA's 
Fiscal Year 2010 Expenditure Plan: 

Review of the National Archives and Records Administration's Fiscal 
Year 2010 Electronic Records Archive Expenditure Plan: 

Briefing for Staff Members of the Subcommittee on Financial Services 
and General Government, Committee on Appropriations, U.S. Senate
and the Subcommittee on Financial Services and General Government, 
Committee on Appropriations, House of Representatives: 

April 6, 2010: 

Contents: 
* Introduction; 
* Objectives, Scope, and Methodology; 
* Results in Brief Background Results; 
* Conclusions; 
* Recommendations for Executive Action; 
* Agency Comments and Our Evaluation; 
* Attachment: 
1. Comments from the Archivist of the United States. 

Introduction: 

Since 2001, the National Archives and Records Administration (NARA) 
has been working to develop a modern Electronic Records Archive (ERA). 
This major information system is estimated to cost more than $567 
million and is intended to preserve and provide access to massive 
volumes of all types and formats of electronic records, independent of 
their original hardware or software. NARA plans for the system to 
manage the entire life cycle of electronic records, from their 
ingestion through preservation and dissemination to customers. It is 
to consist of: 

* infrastructure elements, including hardware and operating systems; 

* business applications that will support the transfer, preservation, 
dissemination, and management of all types of records; and; 

* a means for public access via the Internet. 

Because of the system's complexity, NARA awarded a contract to 
Lockheed Martin to develop ERA in five phases, or increments, the 
first of which is referred to as the "ERA base." According to NARA, 
this system achieved initial operating capability (IOC) in June 2008. 
The second increment includes the Executive Office of the President 
(EOP) system or "ERA EOP," and NARA certified that it reached IOC in 
December 2008. NARA plans to complete development of the remaining 
increments and achieve full operating capability (FOC) by 2012.
	
As mandated by the Consolidated Appropriations Act,[Footnote 3] NARA 
is required to submit an expenditure plan before obligating multi-year 
funds for the ERA program. As in the previous year, the plan must 
satisfy the following legislative conditions: 

* meet the capital planning and investment control review requirements 
established by the Office of Management and Budget (OMB), including 
Circular A-11; 

* comply with the agency's enterprise architecture; 

* conform to the agency's enterprise life-cycle methodology; 

* comply with the acquisition rules, requirements, guidelines, and 
system acquisition management practices of the federal government; 

* be approved by the agency and OMB; and; 

* be reviewed by GAO. 

In November 2009, the agency submitted its fiscal year 2010 
expenditure plan to the relevant House and Senate appropriations 
committees to support its request for $85.5 million in ERA funding. Of 
this amount, $61.7 million is multi-year funds allocated to ERA. As of 
March 2010, the committees had released $23.7 million of the $61.7 
million multi-year funds. 

[End of section] 

Objectives, Scope, and Methodology: 

Our objectives were to: 

* determine whether NARA's fiscal year 2010 expenditure plan satisfies 
the legislative conditions; 

* determine the extent to which NARA has implemented prior GAO 
recommendations; and; 

* provide any other observations about the expenditure plan and the 
ERA acquisition. 

To assess compliance with the legislative conditions, we: 

* reviewed NARA's briefings to senior management and OMB, minutes of 
Information Technology Executive Committee meetings, and the fiscal 
year 2010 exhibit 300 submission[Footnote 4] to OMB to determine the 
extent to which the agency has complied with OMB's capital planning 
and investment control requirements; 

* obtained and reviewed data on NARA's enterprise architecture to 
determine the status of the agency's enterprise architecture efforts; 

* reviewed NARA's ERA system life-cycle processes, which include 
processes for managing system investments, configuration management, 
and managing risks, and reviewed related agency documentation 
describing how these processes were implemented for the ERA project, 
such as minutes of oversight boards and the risk management plan; 

* obtained and reviewed NARA's internal assessment of ERA compliance 
with federal requirements for agencies information technology 
acquisitions; 

* obtained and reviewed OMB's approval of the expenditure plan; and; 

* reviewed and analyzed the fiscal year 2010 expenditure plan 
submitted by the agency in November 2009. 

To determine the extent to which NARA has implemented our prior 
recommendations, we obtained and reviewed agency documents, which 
include quarterly reports to Congress, the ERA contingency plan, and 
NARA's earned value management (EVM) action plan. 

To develop observations on the ERA expenditure plan and acquisition, 
we analyzed fiscal year 2009 and 2010 schedule information contained 
in the expenditure plan, ERA briefings, and congressional status 
reports. We reviewed and analyzed agency documents such as the ERA 
Requirements Document, Online Public Access Search Functionality, and 
plans for the ERA preservation prototype. We also interviewed NARA 
officials. 

To assess the reliability of the data in the expenditure plan, we 
interviewed NARA officials in order to gain an understanding of the 
data and discussed our use of the data in this briefing. In addition, 
we obtained and reviewed NARA budget documents as well as its 
consolidated financial statement results for the fiscal year 2009 
Performance and Accountability Report. We did not, however, assess the 
accuracy and reliability of the information in these documents. 

We conducted this performance audit from January 2010 to April 2010 at 
NARA's College Park, Maryland, location in accordance with generally 
accepted government auditing standards. Those standards require that 
we plan and perform the audit to obtain sufficient, appropriate 
evidence to provide a reasonable basis for our findings and 
conclusions based on our audit objectives. We believe that the 
evidence obtained provides a reasonable basis for our findings and 
conclusions based on our audit objectives. 

[End of section] 

Results in Brief: 

NARA's fiscal year 2010 expenditure plan satisfies five of the six 
legislative conditions contained in the 2010 Consolidated 
Appropriations Act and partially satisfies one. Specifically, it 
partially satisfies the condition that it develop capital planning and 
investment control review processes designed to help ensure that 
projects are being implemented at an acceptable cost and within 
reasonable and expected time frames. NARA has conducted regular 
meetings with senior-level agency management to review ERA progress 
and regularly assesses risks, but there is little evidence that this 
process addresses other key investment management practices, including 
identifying corrective actions and ensuring that they are taken and 
being tracked to closure. As a result, it is uncertain whether ERA is 
receiving the necessary level of executive oversight to ensure that it 
is being implemented at an acceptable cost and within reasonable and 
expected time frames. 

	
NARA fully implemented three of our prior recommendations and 
partially implemented two: 

* NARA implemented our recommendations to provide additional 
information to Congress describing plans for the remainder of fiscal 
year 2009, add an analysis of the cost and benefits of using the EOP 
system to respond to presidential records requests, and develop an ERA 
contingency plan. 

* NARA has partially implemented two recommendations. First, in 
response to our recommendation that NARA provide additional 
information in the fiscal year 2010 expenditure plan on what was spent 
and delivered for deployed increments, NARA added information on 
completed increments and those planned for fiscal year 2010 with their 
associated costs. However, our review of the Expenditure Plan showed 
that it does not fully describe how NARA will expend fiscal year 2010 
funds. Second, in response to our recommendation to strengthen its 
earned value management processes, NARA developed an action plan to 
implement best practices identified in GAO's Cost Estimating Guide; 
[Footnote 5] however, this plan has not been fully implemented. We 
currently have work under way to evaluate NARA's earned value process 
and its implementation of the action plan. 

We have three observations related to the ERA program and fiscal year 
2010 expenditure plan: 

* The cost of ERA is rising and the development of several system 
components is behind schedule. Specifically, over the last 3 fiscal 
years, the estimated life-cycle cost has increased by about 7 percent, 
from about $531 million to more than $567 million. NARA attributed the 
change to increases in the complexity of the system being developed. 
In addition, NARA plans to complete Increment 3 in June 2010, and 
Increment 4 in mid-2011, both of which are about 1 year later than the 
milestones established in program planning documents. NARA officials 
stated that the delivery date is consistent with the current project 
schedule, which was not documented because they determined it was not 
cost effective. 

* NARA has not detailed what capabilities will be delivered by the 
final two ERA phases, or increments. For example, the expenditure plan 
indicates that NARA will begin implementing ERA's preservation 
framework in Increment 4 but does not contain specific dates for 
completion or identify the associated capabilities that are to be 
delivered. Without including detailed plans for the final two 
increments, including specific dates for completion and associated 
functionality to be delivered, Congress will have limited insight to 
evaluate NARA's ongoing progress.
		
* NARA has not effectively defined or managed requirements for the ERA 
system. Among other things, requirements should be documented at a 
high level and traceable throughout the system's life cycle to ensure 
that functionality satisfies the objectives of the system. Further, 
any changes to the program's scope should be reflected by updating the 
requirements in a structured way. Although NARA established an initial 
set of high-level requirements to guide the system's development, 
these requirements are not traceable to work in later phases, or 
increments, of the system. Specifically, about 43 percent of the 
requirements have not been allocated to the remaining two increments, 
and NARA officials stated that it is uncertain whether they will be 
implemented at all. Consequently, it is unclear whether system 
development work performed during the last two phases of the system's 
development will result in functionality that satisfies the intended 
objectives. Further, NARA has not updated its ERA requirements 
document to reflect reinterpreted requirements. These weaknesses can 
be attributed to the fact that NARA did not manage requirements by 
conducting and documenting requirement reviews near the beginning of 
each increment, as called for in its guidance. NARA officials stated 
that requirements reviews for Increment 3 were conducted throughout 
the increment's development but not specifically documented. They 
added that a requirements review for Increment 4 would be conducted 
during the week of March 29th. Without better defined and managed 
requirements, NARA will have little assurance that the ongoing system 
development will meet its needs. 

The identified deficiencies in NARA's management of the ERA project 
leave it with little assurance that ERA will be able to avoid 
additional cost increases and schedule delays. As a result, it is 
increasingly unlikely that NARA will be able to deliver the ERA system 
by the planned date of 2012 with the capabilities originally 
envisioned or to effectively use the system to meet the needs of its 
users in support of NARA's mission. 

To enhance NARA's ability to complete the development of ERA within 
reasonable funding and time constraints, we are recommending that the 
Archivist of the United States take the following two actions: 

* Ensure that NARA's investment review process has adequate executive-
level oversight by maintaining documentation of the results of 
reviews, including changes to the program's cost and schedule baseline 
and any other corrective actions taken as a result of changes in ERA 
cost, schedule, and performance. 

* Ensure that ERA's requirements are managed using a disciplined 
process that results in requirements that are traceable throughout the 
project's life cycle and are kept current.
		
In a letter commenting on a draft of this briefing, the Archivist of 
the United States stated that he would take steps to address our 
recommendations and identified several of the ERA program's recent 
accomplishments. However, he also stated that the briefing did not 
accurately describe the program's current state, including 
strengthened management oversight, adherence to a revised schedule, 
and that the program's history of success does not support our 
conclusion that ERA is unlikely to be completed as planned by 2012. We 
disagree. First, our briefing discusses delays in the current 
increments based on ERA's program management plan and information from 
last year's expenditure plan. NARA did not provide any evidence to 
demonstrate the existence of the rebaselined schedule described by the 
Archivist. Second, the lack of documentation, limited time remaining 
to complete development, and the lack of adequate controls in several 
key areas indicate critical weaknesses, rather than strong oversight. 
Because of the lack of adequate controls and the limited time 
remaining to complete ERA by its original deadline, we believe that on-
time completion of ERA that meets all of its original requirements is 
increasingly unlikely. 

The Archivists full comments are included as attachment 1. 

[End of section] 

Background: 

The ability to find, organize, use, share, appropriately dispose of, 
and save records—the essence of records management—is vital for the 
effective functioning of the federal government. In the wake of the 
transition from paper-based to electronic processes, records are 
increasingly electronic, and the volumes of electronic records 
produced by federal agencies are vast and rapidly growing, providing 
challenges to NARA as the nation's record keeper and archivist. 

Besides sheer volume, other factors contributing to the challenge of 
electronic records include their complexity and their dependence on 
software and hardware. Specifically, the computer operating systems 
and the hardware and software that are used to create electronic 
documents can become obsolete. If they do, they may leave behind 
records that cannot be read without the original hardware and 
software. Further, the storage media for these records are affected by 
both obsolescence and decay. Media may be fragile, have limited shelf 
life, and become obsolete in a few years. For example, few computers 
today have disk drives that can read information stored on 8-or 5 1/4-
inch diskettes, even if the diskettes themselves remain readable. 

Another challenge is the growth in electronic presidential records. 
The Presidential Records Act gives the Archivist of the United States 
responsibility for the custody, control, and preservation of 
presidential records upon the conclusion of a President's term of 
office.[Footnote 6] The act states that the Archivist has an 
affirmative duty to make such records available to the public as 
rapidly and completely as possible consistent with the provisions of 
the act. 

In response to these widely recognized challenges, the Archives began 
a research and development program to develop a modern archive for 
electronic records. In 2001, NARA hired a contractor to develop 
policies and plans to guide the overall acquisition of an electronic 
records system. In December 2003, the agency released a request for 
proposals for the design of ERA. In August 2004, NARA awarded two firm-
fixed-price[Footnote 7] contracts for the design phase, totaling about 
$20 million—one to Harris Corporation and the other to Lockheed Martin 
Corporation. On September 8, 2005, NARA announced the selection of 
Lockheed Martin Corporation to build the ERA system. The total value 
of the contract with Lockheed through 2012 is about $317 million, 
which includes provisions for award fees based on how well the 
contractor meets technical, program management, and cost-control 
criteria. As of fiscal year 2009, NARA has paid Lockheed $156.0 
million, including $144.2 million for development and $11.8 million 
for operations and maintenance. 

As currently planned, the ERA system is to consist of six key 
functions: 

* Ingest enables the transfer of electronic records from federal 
agencies. 

* Archival Storage enables stored records to be managed in a way that 
guarantees their integrity and availability. 

* Records Management supports scheduling,[Footnote 8] appraisal, 
[Footnote 9] description, and requests to transfer custody of all 
types of records, as well as ingesting and managing electronic 
records, including the capture of selected records data (such as 
origination date, format, and disposition). 

* Preservation enables secure and reliable storage of files in formats 
in which they were received, as well as creating backup copies for off-
site storage. 

* Local Services and Control regulates how the ERA components 
communicate with each other, manages internal security, and enables 
telecommunications and system network management. 

* Dissemination enables users to search descriptions and business data 
about all types of records, and to search the content of electronic 
records and retrieve them.
	
NARA currently plans to deliver these components in five separate 
increments. Each increment involves multiple releases that are to 
deliver specific functionality. Below is a summary of the specific 
releases delivered or planned for delivery in each increment: 

* Increment 1 was deployed in two releases. Release 1 established the 
ERA base system—the hardware, software, and communications needed to 
deploy the system. Release 2 enabled functional archives with the 
ability to preserve electronic data in their original format, enable 
disposition agreements and scheduling, and receive unclassified and 
sensitive data from four federal agencies; according to NARA 
officials, this increment was certified as complete in June 2008. 
However, additional enhancements were made to Increment 1, release 2, 
and were completed in March 2010. 

* Increment 2 includes the EOP system, which was designed to handle 
records from the Executive Office of the President. This increment was 
to include the content searching and management for special access 
requests.[Footnote 10] The EOP system was certified for initial 
operating capability (IOC) in December 2008. However, NARA did not 
finish ingesting the presidential records it received until September 
2009, 9 months after IOC. 

* Increment 3 is expected to include the following: 

- Storage and access capabilities for electronic records of the 
Congress and Supreme Court. NARA deployed the first release of 
Increment 3—the congressional component—in January 2010. 

- Upgrades to the ERA base system to, among other things, search, 
view, and print records. 

- Public access to provide the public with tools needed to search and 
access electronic records. NARA plans to launch a test version of 
public access capabilities for NARA staff use in April 2010, and 
public use of the system is to begin in December 2010. 

- Planning for preservation to include development of a preservation 
framework prototype. The prototype is to include the capability to 
plan, execute, and monitor preservation activities. 

- By June 2010, NARA plans to implement the remaining two releases of 
Increment 3. 

* Increment 4 is planned to build upon the base architecture delivered 
as part of Increment 3, and NARA plans to insert newly available 
technology, particularly for preservation capabilities. NARA plans to 
begin work on this increment in 2010 and complete it in fiscal year 
2011. 

* Increment 5 is expected to expand on system capabilities implemented 
in the prior increments. 

NARA plans for the ERA system to reach full operational capability 
(FOC) in 2012. As of February 2010, the life-cycle cost for ERA 
through March 2012 was estimated at more than $567 million, which 
includes not only the development contract costs, but also program 
management, research and development, and program office support, 
among other things. 
		
Table 1 shows reported spending from the program's inception to the 
end of fiscal year 2009. 

Table 1: Summary of ERA Spending from Fiscal Year 2002 through Fiscal 
Year 2009: 

Project category: Development Contract—Lockheed Martin; 
Spending: $156.0 million. 

Project category: System Analysis and Design Contracts—Lockheed Martin 
and Harris Corporation; 
Spending: $40.8 million. 

Project category: Program Management; 
Spending: $39.2 million. 

Project category: Program Office Support Team; 
Spending: $28.0 million. 

Project category: Research and Development; 
Spending: $22.6 million. 

Project category: Integrated Deployment and Support; 
Spending: $13.3 million. 

Project category: Independent Verification and Validation; 
Spending: $7.2 million. 

Project category: Security; 
Spending: $0.2 million. 

Project category: End of Year Balance; 
Spending: $0.3 million. 

Project category: Adjustments; 
Spending: -$1.9[A] million. 

Project category: Total; 
Spending: $305.6[B] million. 

Source: GAO analysis of NARA data. 

[A] Recoveries of prior year funds, adjustments to obligations 
incurred, obligations against prior years, and carryover funds 
expiring at the end of fiscal year 2009. 

[B] Total number may not equal the sum of individual items due to 
rounding. 

[End of table] 

NARA's estimated ERA obligations for fiscal year 2010, including both 
single-year and multi-year funds, are $85.6 million. Table 2 shows how 
NARA planned to distribute funds across the ERA program in fiscal year 
2010.
	
Table 2: Summary of NARA's Fiscal Year 2010 Estimated Obligations for 
ERA: 

Project Category: Development Contract; 
Description: Activities performed under the ERA system acquisition 
contract with Lockheed Martin (includes EOP); 
Estimated obligations: $59.2 million. 

Project Category: Program Management; 
Description: Salaries and benefits, supplies, equipment, and 
telecommunications; 
Estimated obligations: $10.0 million. 

Project Category: Research and Development; 
Description: Research performed with other agencies; 
Estimated obligations: $4.7 million. 

Project Category: Program Office Support Team; 
Description: Labor, contracts, and materials to support ERA program 
management; 
Estimated obligations: $5.2 million. 

Project Category: Integrated Deployment and Support; 
Description: Interagency agreements for ERA facilities[A]; 
Estimated obligations: $2.0 million. 

Project Category: Independent Verification and Validation[B]; 
Description: Verification and validation activities; 
Estimated obligations: $1.8 million. 

Project Category: Program Execution; 
Description: Contractor program and engineering management; 
Estimated obligations: $2.7 million. 

Project Category: Total; 
Estimated obligations: $85.6 million[C]. 

Source: GAO analysis of NARA data. 

[A] ERA facilities include Allegany Ballistics Lab at Rocket Center, 
West Virginia, and the Naval Meteorology and Oceanography Command at 
Stennis, Mississippi. 

[B] NARA contracted with Northrop Grumman to perform independent 
verification and validation on policies and plans produced by the ERA 
program and contract deliverables produced by Lockheed Martin. 

[C] Total may not equal the sum of individual items due to rounding. 
Totals include appropriated funds only. 

Note: NARA obligated $30,000 towards security, but this is not shown 
in the table because the amount is equal to zero when converted into 
millions and rounded to one decimal place. 

[End of table] 

Background: Prior GAO Work: 

We have issued several reports on ERA and its development.[Footnote 
11] In November 2009,[Footnote 12] we testified that NARA had 
completed two of its five planned increments, but experienced delays 
and cost overruns, and several functions planned for the system's 
initial release were deferred. We further testified that although NARA 
initially planned for the system to be capable of ingesting federal 
and presidential records in September 2007, the two system increments 
to support those records did not achieve initial operating capability 
until June 2008 and December 2008, respectively. In addition, NARA 
reportedly spent about $80 million on the base increment, compared to 
its planned cost of about $60 million. 

In our review[Footnote 13] of NARA's fiscal year 2009 expenditure 
plan, we made four observations about the expenditure plan and ERA 
acquisition: 

* The fiscal year 2009 expenditure plan did not specifically identify 
whether completed system increments included all planned functionality 
or what functionality would be included in future increments, 
including the outcomes NARA expected from the remainder of its fiscal 
year 2009 funding. 

* The expenditure plan stated that it relied on earned value 
management (EVM) for project management, which is intended to provide 
objective reports on program status. However, NARA did not fully 
implement practices necessary to make effective use of EVM, limiting 
the reliability of its progress reports. 

* Although NARA certified IOC for the EOP system in December 2008, 
less than 3 percent of the electronic records from the Bush 
administration had been ingested into the system at the time of our 
review, and NARA did not expect the remainder to be ingested until 
October 2009. 

* NARA lacked a contingency plan for the ERA system in the event of a 
failure or disruption. 

Accordingly, we made recommendations to NARA to improve the 
expenditure plan and ERA acquisition. 

[End of section] 

Results: Legislative Conditions: 

Objective 1: NARA's expenditure plan satisfies five of the fiscal year 
2010 legislative conditions and partially satisfies one. 

Table 3: Fiscal Year 2010 Expenditure Plan Provisions for Satisfying 
Legislative Conditions: 

Legislative condition: 1. Meets OMB capital planning and investment 
control review requirements; 
Status: Partially satisfied; 
Expenditure plan provisions: OMB requires agencies to develop capital 
review processes that planning and help ensure that projects are being 
implemented at acceptable cost and within reasonable and investment 
control expected time frames and that they are contributing to 
observable improvements in mission performance. In order to do this, 
agencies should establish an oversight entity that periodically 
reviews capital assets (e.g., the ERA system) to determine how mission 
requirements might have changed and whether the asset continues to 
fulfill mission requirements and deliver intended benefits to the 
agency and customers. Further, agencies should indicate (i.e., 
document) that the investment has been reviewed and approved by the 
responsible oversight entity. Additionally, best practices such as our 
IT investment management framework call for oversight boards to take 
corrective actions at the first sign of cost, schedule, and 
performance problems. They also call for oversight boards to ensure 
that corrective actions and related efforts are executed by the 
project management team and tracked until the desired outcomes occur. 
NARA partially meets this condition; it has established groups to 
oversee ERA's progress and provided them with regular briefings. 
However, NARA does not document the results of briefings to its senior 
management oversight group and thus there is little evidence that this 
body has reviewed and approved the progress of the ERA system. There 
is also little evidence that the group identified or took appropriate 
corrective actions or ensured that the actions were taken and tracked 
to closure. Without adequate oversight that evaluates ERA progress, 
including documenting feedback and action items from senior 
management, NARA will not be able to ensure that the system is being 
implemented at acceptable cost and within reasonable and expected time 
frames. 

Legislative condition: 2. Complies with	NARA's enterprise architecture; 
Status: Satisfied; 
Expenditure plan provisions: OMB requires NARA to include ERA in its 
agency-level enterprise architecture, which is updated on a yearly 
basis. NARA has developed an agencywide enterprise architecture that 
includes ERA. The current agency enterprise architecture—version 5.5 
updated in May 2009—includes ERA and consists of several component 
architectures, including business, data, systems, application, 
operations, and information technology security architectures. In 
addition, OMB requires that any major IT investment be mapped to and 
support the Federal Enterprise Architecture. The business case for the 
investment must also demonstrate the relationship between the 
investment and the business, performance, data, services, application, 
and technology layers of the agency's architecture. NARA's budget 
submission business case for the ERA system certifies compliance with 
these requirements and was approved by OMB. 

Legislative condition: 3. Conforms with NARA's enterprise life-cycle 
methodology; 
Status: Satisfied; 
Expenditure plan provisions: The ERA project conforms to NARA's life-
cycle methodology. For example, the expenditure plan includes 
descriptions of the incremental approach the agency has adopted for 
acquiring ERA and its management of program risks. In particular, the 
risk management methodology calls for the agency to identify and 
categorize risks, qualify the probabilities and consequences of the 
risks, specify a strategy to mitigate each risk, communicate risk 
status, and formulate actions needed to mitigate the risk. NARA 
manages risks using an agency-level risk review board, a program-level 
risk review board, and a technical risk review team. In addition, the 
ERA program office produces monthly reports that include top 
identified risks and specify associated mitigation strategies. The 
office also generates reports of pending or active risks from its risk 
management database that specify the probability and consequences of 
identified risks. Further, risk status is communicated to senior NARA 
management and OMB on a monthly basis and Congress on a quarterly 
basis. The quarterly reports also identify executive actions needed to 
mitigate risks. 

Legislative condition: 4. Complies with the acquisition rules, 
requirements, guidelines, and systems acquisition management practices 
of the federal government[A]. 
Status: Satisfied; 
Expenditure plan provisions: NARA satisfied this provision by 
implementing key processes that reflect best practices for acquiring 
software-intensive systems, like ERA. The quality of software is 
governed largely by the quality of the processes involved in 
developing or acquiring it and maintaining it. Carnegie Mellon 
University's Software Engineering Institute (SEI),[B] recognized for 
its expertise in software processes, has developed models and methods 
that define and determine organizations' software process maturity. 
NARA conducted internal assessments in 2002 and 2004 that used the 
institute's SA-CMM[C] methods to determine the maturity of ERA's 
system policies, processes, and practices and implemented a process to 
address the assessment's recommendations. In addition, NARA's Chief 
Information Officer certified that the ERA program continues to be in 
compliance with the Clinger Cohen Act on November 19, 2009.[D] 

Legislative condition: 5. Approved by NARA and OMB; 
Status: Satisfied; 
Expenditure plan provisions: 
* NARA—October 2009; 
* OMB—October 2009. 

Legislative condition: 6. Reviewed by GAO 
Status: Satisfied; 
Expenditure plan provisions: GAO — April 6, 2010, briefing to 
congressional appropriations subcommittees. 

Sources: GAO analysis of NARA data and the Consolidated Appropriations 
Act, 2010. 

[A] We did not review the program's compliance with the Federal 
Acquisition Regulation or other federal requirements beyond those 
encompassed by the Software Engineering Institute's Capability 
Maturity Model. 

[B] SEI is a federally funded research and development center operated 
by Carnegie Mellon University and sponsored by the Department of 
Defense. Its objective is to provide leadership in software 
engineering and in the transition of new software engineering 
technology into practice. 

[C] The Software Acquisition-Capability Maturity Model (SA-CMM) 
identifies key process areas that are essential to effectively 
managing software-intensive system acquisitions. 

[D] Among other things, the Clinger-Cohen Act of 1996 required OMB to 
establish processes to analyze, track, and evaluate the risks and 
results of major capital investments in IT systems made by executive 
agencies. As such, OMB developed policy and issued guidance for the 
planning, budgeting, acquisition, and management of federal capital 
assets. 

[End of table] 

Results: Prior Recommendation Status: 	
		
Objective 2: NARA has partially implemented our previous 
recommendations. 

In May 2009, we made five recommendations to NARA to help improve the 
expenditure plan and ERA acquisition. 

NARA has implemented three of our recommendations and partially 
implemented two. 

Table 4: Status of NARA's Progress in Implementing Prior GAO 
Recommendations: 

Prior GAO recommendation: Report to Congress on the specific outcomes 
to be achieved by ERA program funding for the remainder of fiscal year 
2009; 
Implementation status: Implemented; 
Status as of fiscal year 2010 plan: NARA provided quarterly reports to 
Congress that identified outcomes to be achieved with the remainder of 
ERA program funding for fiscal year 2009. These reports covered 
reporting periods March-June 2009 and July-September 2009. The reports 
include information on program costs, schedule, and performance. 

Prior GAO recommendation: Include in NARA’s next expenditure plan an 
analysis of the costs and benefits of using the EOP system to respond 
to presidential records requests compared to other existing systems 
currently being used to respond to such requests; 
Implementation status: Implemented; 
Status as of fiscal year 2010 plan: NARA’s 2010 expenditure plan 
includes a detailed explanation of alternatives considered, 
disadvantages of these alternatives, advantages, and the cost of using 
the EOP system to respond to presidential records requests compared to 
that of other existing systems. 

Prior GAO recommendation: Develop and implement an ERA contingency 
plan that follows contingency guidance for federal systems; 
Implementation status: Implemented; 
Status as of fiscal year 2010 plan: NARA developed and tested an ERA 
contingency plan. Testing was completed on August 5, 2009, and the 
plan was finalized on September 16, 2009. 

Prior GAO recommendation: Provide detailed information in future 
expenditure plans on what was spent and delivered for deployed 
increments of the ERA system and cost and functional delivery plans 
for future increments; 
Implementation status: Partially implemented; 
Status as of fiscal year 2010 plan: NARA's fiscal year 2010 
expenditure plan includes additional information on ERA cost, 
schedule, and performance. For example, NARA's 2010 plan discusses the 
amount it planned to spend on Increment 2, as reported in the fiscal 
year 2009 plan ($11.1 million), and the actual amount spent ($10.4 
million). It also compares planned and actual delivery dates (both 
December 2008). In addition, the plan identifies the overall cost for 
Increment 3 ($25.6 million for fiscal year 2009 and $16.6 million for 
fiscal year 2010, for a total of $42.2 million) and the planned 
completion date for the increment (fourth quarter of fiscal year 
2010). The plan also includes a high-level discussion of Increment 4 
plans and associated costs for fiscal year 2010. However, it does not 
fully discuss other key information. For example, although it 
estimates the funding needed for Increment 4 in 2010, it does not 
address the estimated total cost of the increment. In addition, the 
plan does not fully describe how NARA will use 2010 funds for public 
access and preservation capabilities, because it does not describe 
which records (by type, volume, or source) will be made available or 
preserved with 2010 funding. Finally, the plan does not discuss ERA's 
estimated life-cycle cost estimate or the reasons for increases in the 
estimate. Without this key information, the plan is of limited value 
for overseeing program progress. 

Prior GAO recommendation: Strengthen the earned value process so that 
it follows practices described in GAO’s cost estimating guide and more 
reliable cost, schedule, and performance information can be included 
in future expenditure plans and monthly reports; 
Implementation status: Partially implemented; 
Status as of fiscal year 2010 plan: In response to our recommendation, 
NARA developed but has not fully implemented an action plan to improve 
its earned value processes to follow 13 best practices described in GAO’
s Cost Estimating Guide.[A] For 2 of the best practices we assessed as 
not met, NARA plans to conduct a risk assessment analysis as part of 
Increment 3. Other actions are planned but not yet implemented to 
address the 6 practices we assessed as partially met. For example, the 
ERA program office is developing a program management tool to 
establish a joint performance measurement baseline between contractor 
and government activities. We have ongoing work to evaluate the 
adequacy of NARA’s EVM processes and implementation of its action plan. 

Source: GAO analysis of NARA data. 

[A] GAO, Cost Estimating and Assessment Guide: Best Practices for 
Developing and Managing Capital Program Costs, GAO-09-3SP (Washington, 
D.C.: March 2009). 

[End of table] 

Results: Observations: 
		
Objective 3: Observations about NARA's ERA Expenditure Plan and 
Acquisition: 

Observation 1: The ERA system is experiencing expected cost increases 
and schedule delays. 

According to NARA officials, between fiscal years 2008 and 2009, the 
ERA estimated life-cycle cost increased by about $20 million, from 
about $531 million to $551.4 million.[Footnote 14] From fiscal year 
2009 to 2010, the estimated life-cycle cost increased by an additional 
$16 million, from $551.4 million to $567.4 million. This represents a 
cumulative increase of 7 percent over the last three fiscal years. 
NARA attributed the cost increase of $16 million to the increasing 
complexity of the system being developed as determined by both NARA 
and contractor subject matter experts, such as system engineers. 

In addition, NARA currently plans to complete Increment 3 in June 
2010, and Increment 4 in mid-2011, both of which are approximately 1 
year later than the milestones established in its project management 
plan. The completion date for Increment 3 is also inconsistent with 
information in last year's plan, which included a graphic indicating 
that Increment 3 would be completed early in 2010. According to NARA's 
acquisition strategy and the project management plan, dated January 
2005 and April 2006 respectively, Increment 3 was to be delivered 
during calendar year 2009. NARA officials stated that the June 2010 
delivery date is consistent with the current project schedule, which 
was the result of a rebaselining in September 2006. However NARA 
officials told us there is no written evidence to show executive 
approval of this schedule change or link its current schedule to the 
rebaselining effort because, according to NARA officials, it revised 
its development methodology and determined that revising its program 
documents to reflect the change would not be cost effective. 

Further, ongoing updates to existing ERA increments have also fallen 
behind schedule. Although NARA certified Increments 1 and 2 as 
complete in 2008, it has continued to make enhancements to the 
functionality of both increments. Specifically, fiscal year 2009 funds 
provided for analysis, design, software development, integration and 
testing, acceptance testing, and deployment of additional software 
releases for Increment 1. These releases included, among other things, 
functionality that enhanced the system's ability to ingest large 
record files as well as properly displaying content in supported 
Internet browsers. Of the six enhancements completed since March 2009, 
four were delayed by between 17 and 140 days. NARA attributes these 
schedule delays to deficiencies identified during software testing as 
well as subsequent time needed to correct those deficiencies. 

Continued cost increases and delays raise concerns about NARA's 
ability to fully develop and implement the ERA system within budget 
and as scheduled for full operating capability in fiscal year 2012. 

Observation 2: NARA lacks detailed plans for completing the final two 
increments of ERA. 

Even though NARA plans to spend the bulk of its contract development 
funds for 2010 on Increment 4, it has not fully defined the 
functionality to be included in Increments 4 or 5. For Increment 4, 
NARA requested about $37 million in fiscal year 2010 funds to 
implement or expand a variety of capabilities, including those related 
to preservation, access, ERA base, and backup and restore. About $18 
million of this amount is dedicated to developing a framework for 
preservation capabilities. However, while the expenditure plan 
provides high-level descriptions of these capabilities, NARA does not 
have fully defined plans, including specific dates for completion and 
what associated capabilities are to be delivered. According to agency 
officials, NARA is developing an addendum to the 2010 plan that will 
expand on its plans for the remainder of the fiscal year. 

In addition, NARA has not established specific plans for Increment 5. 
While the prior year's expenditure plan provided a high-level 
description of functionality to be included in Increment 5, such as 
expanded preservation capacity and collaboration with other agencies, 
the fiscal year 2010 plan does not include detailed discussion of 
planned functionality for Increment 5. The 2010 plan's sole reference 
to planned functionality for Increment 5 is a single item, related to 
schedule resolution, in a table listing functions deferred from 
Increment 1. Without including detailed plans for the final two 
increments, including specific dates for completion and associated 
functionality to be delivered, Congress will have limited insight to 
evaluate NARA's ongoing progress. NARA intends to discuss Increment 5 
in more detail in the 2011 expenditure plan. 

Observation 3: NARA has not adequately defined or managed ERA's system 
requirements. 

System requirements describe the functionality needed to meet user 
needs and perform as intended in the operating environment and should 
be clearly defined and managed throughout the project in a disciplined 
way. Specifically: 

* Well-defined requirements are documented at a high (business) level 
and are traceable forward and backward throughout the project's life 
cycle, in order to ensure that the system's functionality satisfies 
the intended objectives of the higher-level requirements. 

* Well-managed requirements are maintained through a formal process 
that involves updating changes to requirements in response to 
modifications of project scope. As work products are developed and 
more is learned about the system that is being developed, information 
is occasionally found that requires a change to the original 
requirements. Therefore, projects need to manage these changes to 
requirements in a structured way.[Footnote 15] 

In 2003, NARA finalized a Requirements Management Plan for ERA which, 
among other steps, calls for system requirement reviews near the 
beginning of each increment. 

Although NARA developed a set of baseline system requirements for ERA, 
these requirements are not fully traceable to work in later system 
increments. NARA developed and documented a set of high-level business 
requirements for ERA designed to meet the needs of a variety of users 
such as NARA managers, researchers, and other federal agencies. NARA's 
Requirements Document, which represents the system's full operating 
capability, identifies 853 requirements that are to be developed and 
fully implemented by 2012. However, our analysis of these high-level 
requirements determined that more than 40 percent have yet to be 
allocated to any portion of the system development. Specifically, we 
found that 489 (57.3 percent) of the high-level requirements will be 
implemented as part of Increments 1 through 3 by fiscal year 2010, but 
that the remaining 364 requirements (42.7 percent) have not been 
allocated to the remaining two increments. NARA officials stated that 
it is uncertain when they will be allocated or whether they will be 
implemented at all. Since these requirements have not been allocated, 
it is unclear whether the system development work to be performed as 
part of increments 4 and 5 will result in functionality that satisfies 
the objectives of the higher-level requirements. 

Further, NARA has not updated the requirements document in response to 
changes as the project progressed. NARA acknowledged in its fiscal 
year 2010 Expenditure Plan that in response to technical challenges, 
it reinterpreted some of the requirements stated in the original 
Requirements Document but has not updated the document. NARA 
recognized that the lack of a current set of requirements is a 
significant risk, stating that a system designed and built without a 
clear understanding of the Requirements Document and strict adherence 
to its intent may not meet NARA's needs and user expectations.
	
Failure to follow its guidance on requirements management compounded 
problems with NARA's requirements development for ERA. Specifically, 
NARA conducted and documented system requirements reviews for 
increments 1 and 2, as called for in its requirements management plan, 
but there is no documentation demonstrating that such a review was 
conducted at the start of Increment 3. According to NARA officials, it 
conducted ongoing requirements reviews with the contractor throughout 
Increment 3, but did not document its reviews until recently because 
of a change in its development approach. However, our review of the 
Increment 3 documentation did not reveal any evidence of a 
requirements review at the start of the increment. In addition, after 
raising the issue with agency officials, they informed us that they 
had scheduled a system requirements review for Increment 4 for the 
week of March 29th, at which they plan to assess whether business 
process changes have rendered some of the original requirements no 
longer necessary. 

Without appropriately traceable and current ERA system requirements, 
NARA will have little assurance that ongoing development work is 
contributing to its mission needs. Further, NARA will lack an adequate 
basis for ensuring that its contractor is providing work that meets 
the needs of the agency and, ultimately, the system's users. 

[End of section] 

Conclusions: 

While NARA's fiscal year 2010 expenditure plan met five of the six 
legislative conditions, the lack of documentation demonstrating the 
appropriate level of senior management review, approval, and oversight 
limits NARA's ability to ensure that the project makes expected 
progress. In addition, the lack of a documented current baseline 
schedule leaves NARA with limited ability to identify significant 
delays. The lack of key oversight documentation limits NARA's 
assurance that schedule delays and cost increases will not continue 
during ERA's development. 

In addition, without specific plans for completing the final two 
increments, NARA lacks assurance that the remaining increments will 
adequately fulfill its mission needs. Specifically, NARA's failure to 
follow its own guidance on requirements management has resulted in a 
set of requirements that is incomplete and out of date, which could 
lead to the system being completed without addressing all necessary 
requirements or the development of functionality to meet requirements 
that are no longer valid. Addressing these weaknesses is becoming even 
more critical as the projected completion of the project approaches; 
if they continue, it will be increasingly unlikely that NARA will be 
able to deliver the ERA system by 2012 with the capabilities 
originally envisioned or to effectively use the system to meet the 
needs of its users in support of NARA's mission of preserving and 
providing access to the nation's electronic records. 

[End of section] 

Recommendations for Executive Action: 

To enhance NARA's ability to complete the development of ERA within 
reasonable funding and time constraints, we are recommending that the 
Archivist of the United States take the following two actions: 

* Ensure that NARA's investment review process has adequate executive-
level oversight by maintaining documentation of the results of 
reviews, including changes to the program's cost and schedule baseline 
and any other corrective actions taken as a result of changes in ERA 
cost, schedule, and performance. 

* Ensure that ERA's requirements are managed using a disciplined 
process that results in requirements that are traceable throughout the 
project's life cycle and are kept current. 

[End of section] 

Agency Comments and Our Evaluation: 

In a letter commenting on a draft of this briefing, the Archivist of 
the United States described several of the program's recent 
accomplishments and stated that he would take steps to address our 
recommendations, including documenting management reviews and actions 
and ensuring adequate discipline is maintained in the definition and 
allocation of requirements. However, he also stated that the briefing 
did not accurately describe the program in its current state, adding 
that NARA had strengthened its management oversight of the program 
which has moved forward, meeting the baseline schedule established in 
a corrective action plan for Increment 1. In addition, he stated that 
the program's history of success does not support our conclusion that 
ERA is unlikely to be completed as planned by 2012. We disagree for 
several reasons. First, as discussed in our briefing, our discussion 
on timeliness focuses on the increments currently being developed 
(Increments 3 and 4) and is based on ERA's currently documented 
management plan and information from last year's expenditure plan. 
NARA did not provide any evidence to demonstrate the existence of the 
rebaselined schedule described by the Archivist. Second, the lack of 
documentation supporting key management activities we describe—
including performance against the cost and schedule baseline, 
executive oversight, and requirements management—apparently contradict 
the robust oversight described by the Archivist. Finally, while NARA 
has made progress on several capabilities in the past year, the extent 
to which these capabilities are fulfilling the project's original 
goals cannot be determined due to NARA's lack of an adequate 
requirements management process. With the lack of adequate controls in 
several key areas and only about two years remaining to complete 
development, we believe that on-time completion of ERA that meets all 
of its original requirements is increasingly unlikely. 

The Archivists comments are attached. 

[End of section] 

Attachment 1: Comments from the Archivist of the United States: 

National Archives and Records Administration: 
8601 Adelphi Road: 
College Park Maryland 20740-6001: 
[hyperlink, http://www.archives.gov] 

April 2, 2010: 

Government Accountability Office: 
Director of Information Technology Management Issues: 
Mr. David A. Powner: 
441 G Street NW: 
Washington, DC 20548: 

Dear Mr. Powner: 

We thank you for the opportunity to review and comment on the advance 
copy of the GAO briefing, Review of the National Archives and Records 
Administration's Fiscal Year 2010 Electronic Records Archive 
Expenditure Plan for staff members of the Subcommittees on Financial 
Services and General Government, Committees on Appropriations, U.S. 
Senate and US. House of Representatives. 

It has been my understanding that the GAO reports in previous years 
have been very useful to improve the management of the program by the 
ERA Program staff. However, I am concerned that this briefing does not 
accurately describe the program in its current state. Specifically, 
the briefing focuses on issues which may have been appropriate in 
previous years but which are no longer valid. 

As you know the program experienced some delays and cost overruns in 
the early stages of Increment 1. Since that time, NARA has 
strengthened its management oversight of the program, and as a result 
the program has moved forward steadily meeting the baseline schedule 
established during the corrective action plan for Increment 1. As you 
noted in the briefing, ERA has stayed well within the plus/minus 10% 
cost threshold established by the Office of Management and Budget 
(OMB) for the work to date. 

Our history of success, both in terms of accomplishments, schedule and 
cost, does not seem to support your observation regarding assurances 
that ERA will not be able to avoid additional cost increases and 
schedule delays or that it is unlikely that NARA will be able to 
deliver a system by the planned date of 2012 that will effectively can 
be used to meet the needs of its users in support of NARA's mission. 
We are very proud of the accomplishments of the program and look 
forward to more success as we prepare for our next deployment, the 
Online Public Access (OPA) instance. Examples of our success in 
meeting major accomplishments include: 

* Deployment of the Increment 1 Initial Operating Capability ("Base 
Instance") which is now in use by NARA staff and staff from four 
"early adopter" agencies. Twenty-one additional agencies will be added 
within the next few months. By the end of the year we anticipate the 
base instance to store over one terabyte of records. 

* Deployment of the Executive Office of the President instance, which 
now stores and provides search and access capabilities for 
approximately 78 terabytes of electronic records, including 
photographs from the George W. Bush Administration. Over 54,000 
searches have been conducted since operations began. 

* Deployment of the Congressional Records Instance, which on March 11, 
2010 ingested two transfer groups of Homeland Security Committee 
electronic records from the House of Representatives, including MS-
Office files, pdf, film, databases, audio, video and other multimedia 
content. We remain ready to ingest additional files as they are 
provided to us. 

* Design of a pilot to provide public access to NARA's electronic 
records, which will be deployed to the public later this year. 

* Design of a prototype demonstrating a framework for preservation 
technologies, most of which are at an early stage of development. 

While I an, confident that structures now in place are adequate to 
ensure that the program will continue to meet its cost and schedule 
goals, we will take steps to address your recommendations. First, we 
will ensure that an adequate audit trail is maintained to document 
management reviews and actions. Second, we will review and adapt, as 
necessary, our existing requirements management proems to ensure 
adequate discipline is maintained in the definition and allocation of 
requirements. 

Again, I thank you for this opportunity and look forward to our future 
interactions as we continue the ERA acquisition process. 

Sincerely, 

Signed by: 

David S. Ferriero: 
Archivist of the United States: 

[End of Appendix I] 

Appendix II: Comments from the National Archives and Records 
Administration: 

National Archives at College Park: 
8601 Adelphi Road: 
College Park, Maryland 20740-6001: 

May 21, 2010: 

Government Accountability Office: 
Director of Information Technology Management Issues: 
Mr. David A. Powner: 
441 G Street NW: 
Washington DC, 20548: 

Dear Mr. Powner: 

We thank you for the opportunity to review and comment on the draft 
"Electronic Records Archives Status Update on the National Archives 
and Records Administration's Fiscal Year 2010 Expenditure Plan." 

This letter responds to the two conclusions provided in the report. To 
address your conclusion regarding the level of senior management 
review, approval and oversight, we are now documenting the minutes and 
actions for Senior Staff meetings where ERA is discussed. 

In response to your concern that ERA requirements have not been 
defined and managed, NARA has not made any changes to the original 
requirements documented in the 2003 Requirements Document. We have 
recently begun an intensive effort to review the requirements 
established in 2003 within the context of new technologies and 
changing business needs, such as the impact of the newly established 
National Declassification Center on ERA requirements relative to the 
protection of restricted information and requests for records made 
under the Freedom of Information Act. 

Further, in April, 2010, NARA managers met to determine top ERA 
functional priorities to be completed by the end of the current 
contract. Concurrently, the ERA requirements manager is mapping those 
functional priorities to their underlying contract requirements and 
will be updating the ERA Requirements Document as appropriate. The 
goal of these efforts is to identify the requirements from the 
Requirements Document that remain to be developed by March 2012. 

Again, I thank you for this opportunity and look forward to our future 
interactions as we continue the ERA acquisition process. 

Sincerely, 

Signed by: 

David S. Ferriero: 
Archivist of the United States: 
National Archives and Records Administration: 

[End of section] 

Appendix III: GAO Contact and Staff Acknowledgments: 

GAO Contact: 

David A. Powner (202) 512-9286 or pownerd@gao.gov: 

Staff Acknowledgments: 

In addition to the individual named above, key contributions to this 
report were made by James R. Sweetman, Jr., Assistant Director; Monica 
Perez Anatalio; Pamlutricia Greenleaf; Kush K. Malhotra; Lee A. 
McCracken; and Karl W. Seifert. 

[End of section] 

Footnotes: 

[1] Consolidated Appropriations Act, 2010, Pub. L. No. 111-117, div. 
C., title V, 123 Stat. 3034, 3193 (Dec. 16, 2009). 

[2] GAO, Cost Estimating and Assessment Guide: Best Practices for 
Developing and Managing Capital Program Costs, [hyperlink, 
http://www.gao.gov/products/GAO-09-3SP] (Washington, D.C.: March 2009). 

[3] Consolidated Appropriations Act, 2010, Pub. L. No. 111-117, div. 
C, title V, 123 Stat. 3034, 3193 (Dec. 16, 2009). 

[4] Agencies develop an exhibit 300, also known as the Capital Asset 
Plan and Business Case Summary, to justify each request for a major 
information technology investment. OMB sets forth requirements for the 
exhibit 300 in Circular A-11, Part 7, Planning, Budgeting, 
Acquisition, and Management of Capital Assets. 

[5] GAO, Cost Estimating and Assessment Guide: Best Practices for 
Developing and Managing Capital Program Costs, [hyperlink, 
http://www.gao.gov/products/GAO-09-3SP] (Washington, D.C.: March 2009). 

[6] 44 U.S.C. § 2203(f)(1). 

[7] According to the Federal Acquisition Regulation, a firm-fixed-
price contract provides for a price that is not subject to any 
adjustment on the basis of the contractor's cost experience in 
performing the contract. This type of contract places on the 
contractor maximum risk and full responsibility for costs and 
resulting profit or loss. 48 C.F.R. § 16.202-1. 

[8] A record schedule is a document that describes agency records, 
establishes a period for their retention by the agency, and provides 
mandatory instructions for what to do with them when they are no 
longer needed for current government business. 

[9] Records appraisal is the process of determining the value and the 
final disposition of records, making them either temporary or 
permanent. 

[10] These are requests NARA receives from the current and former 
administrations, the Congress, and the courts for access to 
presidential records. The priorities are determined by NARA's Office 
of Presidential Libraries based on experience with the records of 
previous administrations. 

[11] GAO, Information Management Challenges in Managing and Preserving 
Electronic Records, [hyperlink, 
http://www.gao.gov/products/GAO-02-586] (Washington, D.C.: June 17, 
2002); Records Management: Planning for the Electronic Records 
Archives Has Improved, [hyperlink, http://www.gao.gov/products/GAO-04-
927] (Washington, D.C.: Sept. 23, 2004); Information Management 
Acquisition of the Electronic Records Archives Is Progressing, vGAO-05-
802 (Washington, D.C.; July 15, 2005); Electronic Records Archives: 
The National Archives and Records Administration's Fiscal Year 2006 
Expenditure Plan, [hyperlink, http://www.gao.gov/products/GAO-06-906] 
(Washington, D.C.: Aug. 18, 2006); Information Management The National 
Archives and Records Administration's Fiscal Year 2007 Expenditure 
Plan, [hyperlink, http://www.gao.gov/products/GAO-07-987] (Washington, 
D.C.: July 27, 2007); and Information Management: Challenges in 
Implementing an Electronic Records Archive, [hyperlink, 
http://www.gao.gov/products/GAO-08-738T] (Washington, D.C.: May 14, 
2008). 

[12] GAO, National Archives: Progress and Risks in Implementing its 
Electronic Records Archive Initiative, [hyperlink, 
http://www.gao.gov/products/GAO-10-222T] (Washington, D.C.: Nov. 5, 
2009). 

[13] GAO, Electronic Records Archive: The National Archives and 
Records Administration's Fiscal Year 2009 Expenditure Plan, 
[hyperlink, http://www.gao.gov/products/GAO-09-733] (Washington, D.C.: 
July 24, 2009). 

[14] During a previous review, NARA officials told us that the 
estimated life-cycle cost in 2008 was $453 million. However, after 
reviewing information being used to develop this briefing, NARA 
officials told us that the figure they provided previously did not 
include costs for 2012, which account for approximately $78 million in 
additional costs. NARA did not document its life-cycle cost estimates 
in expenditure plans for fiscal years 2008 through 2010. 

[15] GAO, Business System Modernization: IRS Needs to Complete Recent 
Efforts to Develop Policies and Procedures to Guide Requirements 
Development and Management, [hyperlink, 
http://www.gao.gov/products/GA0-06-310] (Washington, D.C.: March 2006). 

[End of section] 

GAO's Mission: 

The Government Accountability Office, the audit, evaluation and 
investigative arm of Congress, exists to support Congress in meeting 
its constitutional responsibilities and to help improve the performance 
and accountability of the federal government for the American people. 
GAO examines the use of public funds; evaluates federal programs and 
policies; and provides analyses, recommendations, and other assistance 
to help Congress make informed oversight, policy, and funding 
decisions. GAO's commitment to good government is reflected in its core 
values of accountability, integrity, and reliability. 

Obtaining Copies of GAO Reports and Testimony: 

The fastest and easiest way to obtain copies of GAO documents at no 
cost is through GAO's Web site [hyperlink, http://www.gao.gov]. Each 
weekday, GAO posts newly released reports, testimony, and 
correspondence on its Web site. To have GAO e-mail you a list of newly 
posted products every afternoon, go to [hyperlink, http://www.gao.gov] 
and select "E-mail Updates." 

Order by Phone: 

The price of each GAO publication reflects GAO’s actual cost of
production and distribution and depends on the number of pages in the
publication and whether the publication is printed in color or black and
white. Pricing and ordering information is posted on GAO’s Web site, 
[hyperlink, http://www.gao.gov/ordering.htm]. 

Place orders by calling (202) 512-6000, toll free (866) 801-7077, or
TDD (202) 512-2537. 

Orders may be paid for using American Express, Discover Card,
MasterCard, Visa, check, or money order. Call for additional 
information. 

To Report Fraud, Waste, and Abuse in Federal Programs: 

Contact: 

Web site: [hyperlink, http://www.gao.gov/fraudnet/fraudnet.htm]: 
E-mail: fraudnet@gao.gov: 
Automated answering system: (800) 424-5454 or (202) 512-7470: 

Congressional Relations: 

Ralph Dawn, Managing Director, dawnr@gao.gov: 
(202) 512-4400: 
U.S. Government Accountability Office: 
441 G Street NW, Room 7125: 
Washington, D.C. 20548: 

Public Affairs: 

Chuck Young, Managing Director, youngc1@gao.gov: 
(202) 512-4800: 
U.S. Government Accountability Office: 
441 G Street NW, Room 7149: 
Washington, D.C. 20548: